Coast Electric Co. v. Industrial Indemnity Co.

144 Cal. App. 3d 879, 193 Cal. Rptr. 74, 1983 Cal. App. LEXIS 1879
CourtCalifornia Court of Appeal
DecidedJuly 13, 1983
DocketCiv. 26485
StatusPublished
Cited by4 cases

This text of 144 Cal. App. 3d 879 (Coast Electric Co. v. Industrial Indemnity Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coast Electric Co. v. Industrial Indemnity Co., 144 Cal. App. 3d 879, 193 Cal. Rptr. 74, 1983 Cal. App. LEXIS 1879 (Cal. Ct. App. 1983).

Opinion

Opinion

STANIFORTH, J.

This is an appeal from a judgment in favor of plaintiff materialmen Coast Electric Co. (Coast) against defendant surety company Industrial Indemnity Company (Industrial). The sole question is whether Coast’s claim is enforceable as to electrical materials delivered more than 90 days before the “preliminary bond notice” was given pursuant to Civil Code section 3091. 1

Facts

Industrial issued a payment bond as required by Civil Code section 3247 at the request of Raymond A. Whitwer, the prime contractor on a public works project, Poway School No. 10. Industrial’s bond was for the principal sum of $1,524,250 and provided, upon default by Whitwer or any of his subcontractors, for payment for materials and supplies used in the construc *881 tion. Industrial, as surety, was obligated upon such default to pay all sums due together with a reasonable attorney fee. After acquiring this bond, Whitwer contracted with Universal Electric (Universal) to become the electrical subcontractor—to furnish electrical work and materials for the Poway school.

Coast agreed to supply Universal electrical materials for the Poway school project. On July 11 and 12, 1977, Universal issued two written purchase orders to Coast. These orders described the material Universal would buy from Coast and install on the Poway school job. Upon receipt of the purchase orders, Coast supplied the electrical materials described to Universal and these materials were in fact used on the work of improvement, the Poway school. Coast billed Universal for the reasonable value of materials in the sum of $49,608.10. These materials were accompanied by 26 separate invoices. The materials for each of the invoices were either picked up by Universal at Coast’s place of business or were shipped directly to the job site. The materials were delivered between November 14, 1977, and May 25, 1978.

In the course of construction of the school, Universal became insolvent, was unable to pay its debts. As a result Coast was not paid for any of the materials it supplied to Universal and used on the school. On August 11, 1978, within 90 days of the last materials delivery, Coast sent Whitwer a 90-day preliminary bond notice informing Whitwer Coast had provided material totaling $49,608.10, the amount was unpaid and Coast was making a claim against the payment bond. This bond notice was sent by certified mail, return receipt requested. The receipt was returned to Coast signed on behalf of Whitwer on August 12, 1978. Thus, the 90-day preliminary bond notice was mailed and received within 90 days of the date the last materials were furnished to the job site. Upon Whitwer’s and the bonding company’s refusal to pay the claim, Coast brought this action to recover $49,608.10 plus interest and attorney fees.

Discussion

I

Section 3091 of the Civil Code provides: “The notice is required only on public works, and is a necessary prerequisite to enforcement of a claim on a payment bond. The notice shall be in writing and shall state with substantial accuracy the amount claimed, and the name of the party to whom the claimant furnished labor, services, equipment, or materials. The notice shall be given within 90 days from the date on which the claimant furnished the last labor, services, equipment, or materials for which such claim is made. ”

*882 Industrial would construe the foregoing statute to mean that where there are a series of independent contracts for materials furnished a public project under an open account, a claim may be made only for materials delivered within 90 days of the date of the required notice. As to materials which were contracted for and delivered before the 90-day period immediately preceding the required notice, Industrial asserts the claim is not allowable. 2

Industrial’s contentions fail in several critical respects. Contrary to Industrial’s contention, the statute contains no language limiting a claimant to only those materials provided to the job site within the 90-day period immediately preceding the bond notice. The plain language of the statute is neither ambiguous nor does it expressly or by implication limit the claim to materials provided within 90 days of the date the notice is given.

Industrial asserts the words “such claim” must refer only to materials furnished within the 90-day period immediately preceding the notice, arguing the word “such” in the phrase “such claim” is either (1) surplusage or (2) expresses a statutory intent to limit the claim on the payments of bond and services and equipment or materials furnished within 90 days from the date last furnished and within 90 days of the notice given. Industrial’s reasoning process from the statutory words to this conclusion is opaque.

This argument improperly ignores other language in the statute. When the search for legislative intent is extended to include the two sentences preceding those quoted, the claim of surplusage, ambiguity, or Industrial’s 90 days before notice interpretation disappears. The words “such claim” plainly refers to the “claim” referred to in the two preceding sentences. The words “such claim” are intended to refer back to a “claim” on a “bond payment” and “the amount claimed.” A fair reading of the entire statute—and we must read it as a whole—means “[t]he notice shall be given within 90 days from the date on which claimant furnished the last . . . materials for which [claim on a payment bond] is made.” (Civ. Code, § 3091.) This interpretation is compelled by long standing rules of statutory construction. Industrial’s interpretation leads to an absurd result. Bond notices would be required every 90 days in the course of a continuing job if the materialman sought to protect himself by seeking recourse to the bond. This repetitious filing would be necessary even though there was no default, nor threat of default, then present.

There is no legislative intent to be gleaned anywhere of a limitation on a claim to only those materials furnished within 90 days of the notice given. *883 Such construction would abrogate much of the broad protection given materialmen and suppliers by the statute. Such a restriction would drastically amend the statute. The reasonable interpretation of the plain language of the statute does not support Industrial’s argument.

California courts have not ruled specifically on the issue of whether Civil Code section 3091 90-day notice entitles a claimant to recover for all materials provided to the project or limits the supplier to only those materials provided within the last 90 days before notice. However, by precise judgments several California cases have allowed a plaintiff’s claim for all materials provided to a job site, not just those provided within 90 days of the notice. In General Elec. Co. v. Central Surety & Ins. Corp. (1965) 232 Cal.App.2d 590 [43 Cal.Rptr. 48], the plaintiff sued for the value of materials provided an electrical subcontractor who went bankrupt while installing materials on a California public works project. The action, as is the case at bench, was on the general contractor’s public works bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hasso v. Hasso
55 Cal. Rptr. 3d 667 (California Court of Appeal, 2007)
Granite Constr. Co. v. Am. Motorists Ins. Co.
29 Cal. App. 4th 658 (California Court of Appeal, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
144 Cal. App. 3d 879, 193 Cal. Rptr. 74, 1983 Cal. App. LEXIS 1879, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coast-electric-co-v-industrial-indemnity-co-calctapp-1983.