United States v. Andrews

406 F.2d 790, 1969 U.S. App. LEXIS 9206
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 24, 1969
Docket12673
StatusPublished
Cited by10 cases

This text of 406 F.2d 790 (United States v. Andrews) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Andrews, 406 F.2d 790, 1969 U.S. App. LEXIS 9206 (4th Cir. 1969).

Opinion

406 F.2d 790

The UNITED STATES of America for the Use of NOLAND COMPANY, Appellee,
v.
Charles B. ANDREWS and Elbert L. Parrish, each individually and trading as Andrews & Parrish, and the Fidelity and Casualty Company of New York, Appellants.

No. 12673.

United States Court of Appeals Fourth Circuit.

Argued December 2, 1968.

Decided January 24, 1969.

G. Kenneth Miller, Richmond, Va. (May, Garrett, Miller & Newman, Joseph T. Mizell, Jr., and Mizell, Gayle & Binns, Richmond, Va., on brief), for appellants.

Jack B. Russell, Richmond, Va. (J. Terry Parsley and Browder, Russell, Little & Morris, Richmond, Va., on brief), for appellee.

Before SOBELOFF, WINTER and BUTZNER, Circuit Judges.

SOBELOFF, Circuit Judge:

This is an action arising under the Miller Act, 40 U.S.C.A. § 270a, in which use-plaintiff Noland Company seeks recovery from the general contractor, Andrews & Parrish,1 and its surety, the Fidelity and Casualty Company of New York. The claim is for the unpaid balance on open account for materials supplied to Wade Mechanical Corporation, the plumbing and fixture subcontractor on a renovation and construction project at Camp A. P. Hill, Virginia. Upon entry of judgment for Noland in the District Court, the defendants appealed.

Under the Miller Act, a materialman may call upon the general contractor to answer for debts of a subcontractor only if he has given notice of his claim in the manner and within the time required by section 270b(a).2 The defendants assert that the present action is barred for the reason that Noland's notice of claim on January 25, 1967 was not given "within ninety days from the date on which such person * * * supplied the last of the material for which such claim is made."

At trial it was shown that Andrews & Parrish, after being awarded the A. P. Hill contract by the Government, subcontracted the plumbing and fixture work to Wade. From time to time during 1966 Wade ordered materials from Noland for use on this job. On October 17 of that year, Andrews notified the Government that the work which Wade had been performing was complete. Thereupon the Government made a "final inspection" in which it found the work acceptable, except for a small list of deficiencies requiring correction. These corrections were made immediately, and the Government then accepted the job and took possession of the premises, not later than October 22, 1966. Apparently, Noland did not participate in the inspection which led to acceptance of the job.

The following January, while Mr. Wade was at Camp A. P. Hill in connection with an entirely unrelated matter, he discovered quite by chance that two gate valves, which it is undisputed were required under the contract between Andrews and the Government, had not been furnished or installed. Wade called the Government's attention to the omission, and it requested him to install the valves. Upon receipt of an order from Wade, Noland delivered them on or about January 17, 1967, and they were put in place by Wade. On January 25, Noland sent Andrews a written notice3 asserting that the latter was obligated to it on Wade's unpaid balance for all materials supplied by Noland for the A. P. Hill job, including those delivered in 1966. Wade apparently was then in financial difficulty and later went into bankruptcy.

The question for our determination is whether the notice of January 25, 1967 which was well within ninety days after the delivery of the valves, but not within ninety days after the delivery of the materials previously furnished for the job, complies with the requirement of 40 U.S.C.A. 270b(a) and permits Noland to recover for all materials furnished to Wade for use at the A. P. Hill site. The last delivery before the one in January was made on October 19, 1966.

The defendants vigorously maintain that the notice was too late, reasoning that January 17, 1967, when the valves were delivered, should not be held "the date on which such person * * * supplied the last of the material for which such claim is made." They contend that the valves were not furnished "in the prosecution of the work" because the Government had accepted the job and taken possession of the premises in October, 1966. Their theory is that the installation of the valves must be termed a mere "correction of a defect" which, under the decided cases, does not extend the time for giving notice under the Miller Act.

The plaintiff, on the other hand, relies on the undisputed fact that the valves were contracted for as part of Andrews' original undertaking. It maintains that the job was not complete until the valves were installed, regardless of the fact that the parties may have erroneously thought the work was finished in 1966. Accordingly, it submits that the January 25 notice, given within ninety days after the valves were delivered on January 17, fully complies with the statute and entitles it to recover the entire amount due.

The applicable legal test, as the parties correctly perceive and as the Ninth Circuit stated in United States ex rel. Austin v. Western Elec. Co., 337 F. 2d 568, 572-573 (9 Cir. 1964), is "whether the work was performed and the material supplied as a `part of the original contract' or for the `purpose of correcting defects, or making repairs following inspection of the project.'" It seems plain to us that the installation of the two missing valves cannot be characterized as a mere correction of a defect. The fact that the valves were called for by both the primary contract and the subcontract and were not furnished till January 17, 1967, is dispositive of the issue, notwithstanding the Government's acceptance of the premises at an earlier date under the mistaken impression that the work had been completed. The valves were installed by Wade at no extra charge to the Government or to the general contractor. Neither the contractor nor the subcontractor was ever in doubt as to its obligation to install the valves in order to finish the job.

It may be noted in passing that in the interval between the expiration on January 17, 1967 of the ninety day period following the last delivery in October, 1966 and January 25, 1967, the date of Noland's notice, Andrews made no payments to Wade, so that Andrews was in no way prejudiced by the fact that the notice was not given within ninety days from the October date upon which the defendants rely; but we do not rest our decision upon this circumstance.

It is our conclusion that the contract was not completed until the valves were installed, and that their delivery in January is the critical date from which to measure the Miller Act limitation period. United States ex rel. General Elec. Co. v. Gunnar I. Johnson & Son, Inc., 310 F.2d 899 (8 Cir. 1962); United States ex rel. Bourquin & Co. v. Chester Const. Co., 104 F.2d 648 (2 Cir. 1939). See also United States ex rel. Palmer Asphalt Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
406 F.2d 790, 1969 U.S. App. LEXIS 9206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-andrews-ca4-1969.