United States v. Bregman Construction Corp.

172 F. Supp. 517, 1959 U.S. Dist. LEXIS 3456
CourtDistrict Court, E.D. New York
DecidedApril 23, 1959
DocketCiv. 17584
StatusPublished
Cited by20 cases

This text of 172 F. Supp. 517 (United States v. Bregman Construction Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Bregman Construction Corp., 172 F. Supp. 517, 1959 U.S. Dist. LEXIS 3456 (E.D.N.Y. 1959).

Opinion

*518 ZAVATT, District Judge.

This is a suit on a Miller Act payment bond, 40 U.S.C.A. § 270a(a) (2), instituted by the use plaintiff, who furnished material to the defendant, Ben B. Greene, Inc., the electrical subcontractor of the defendant Bregman Construction Corp., the prime contractor. The subcontractor is in default of appearance and pleading and took no ■ part in the trial. The suit against the prime contractor and its surety, New Amsterdam Casualty Company, was instituted pursuant to 40 U.S. C.A. § 270b. The complaint also alleges a claim against the defendant, Ben B. Greene, Inc., for goods sold and delivered. After a trial to the court without a jury, the court makes the following findings of fact:

Findings of Fact

1. On February 24, 1956, the defendant, Bregman Construction Corp. (hereinafter referred to as the prime contractor), entered into a written contract (No. DA 30-075 Eng. 7083) with the United States of America (hereinafter referred to as the Government) to furnish all the labor and materials and perform all of the work required to construct a Special AAA Facility at Lloyd Harbor, New York, for the sum of $864,-442.

2. Said contract provided that the Government would make payments to the prime contractor, as the work progressed, at the end of each calendar month based on estimates made and approved by the Government’s contracting officer; that in making such payments the Government would retain 10% of the estimated amounts until final completion and acceptance of all of the work covered by the contract; that after 50% of the work had been completed the contracting officer could make payment of the remaining monthly payments without retaining 10% of the estimated amounts, if he found that satisfactory progress was being made by the prime contractor; that final payment, including retained percentages, was not to be made until the final completion and acceptance of the work.

3. On February 24,1956, pursuant to 40 U.S.C.A. § 270a(a) (2), the prime contractor furnished to the Government a payment bond in the sum of $432,221 signed by the prime contractor as Principal and the defendant, New Amsterdam Casualty Company, as Surety, conditioned upon the prompt payment by the prime contractor “to all persons supplying labor and material in the prosecution of the work provided for in said contract.”

4. On March 16, 1956, the prime contractor entered into a subcontract in writing with the defendant, Ben B. Greene, Inc. (hereinafter referred to as the subcontractor), by the terms of which the subcontractor agreed to furnish all labor, materials, tools, equipment, appliances and other things necessary to complete that portion of the electrical work (required to be performed under the prime contract) specified in the subcontract and the prime contractor agreed to pay to the subcontractor therefor the sum of $86,090 in monthly installments equal to 90% of the monthly estimate submitted by the subcontractor and accepted by the prime contractor. These monthly payments were not to be made, however, until the prime contractor received payment from the Government for the work performed by the subcontractor.

5. Shortly after the subcontractor entered into said subcontract with the prime contractor, the use plaintiff was advised by the subcontractor as to said subcontract and that the use plaintiff would receive orders from the subcontractor for the major part of the materials which it would require in the performance of its subcontract.

6. Between October 19, 1956 and January 14, 1957, the use plaintiff furnished materials in the prosecution of the work provided for in the prime contract by delivering the same to the site of the Special AAA Facility at Lloyd Harbor, New York. The materials were so furnished pursuant to a series of separate orders received by the use plaintiff from the subcontractor at agreed prices *519 which were fair and reasonable. Of the orders so received and the materials so furnished (not fully paid for) the dates of delivery, unpaid balances of the agreed prices and fair and reasonable values, subcontractor’s purchase order vouchers and subcontractor’s invoice numbers are as follows:

7. The use plaintiff billed the subcontractor separately for each separate order he received from the subcontractor and filled, including the orders enumerated under Finding of Fact No. 6, and as to each such separate invoice received from the use plaintiff which the subcontractor paid in full or in part the subcontractor made such payments with reference to a designated invoice and purchase order and the use plaintiff credited each payment accordingly. There was no entire contract between the use plaintiff and the subcontractor for all of the materials so furnished by the use plaintiff nor did they treat said orders and materials furnished pursuant thereto on a running account basis.

8. On February 15, 1957, the use plaintiff gave written notice to the prime contractor and the surety that it claimed $9,598.42 for electrical supplies furnished to the subcontractor for use in the prosecution of the work provided in the prime contract; that the materials were so furnished at various times between August 20, 1956 and January 14, 1957. Said notice was served by mailing the same by registered mail, postage prepaid, addressed to the prime contractor at the place where it conducted its business and by similarly mailing a copy of said notice to the surety addressed at 60 John Street, New York 38, N.Y. The said addressees received said notices on February 18, 1957.

9. The prime contract was finally settled on September 30, 1957.

10. This suit was commenced on May 2, 1957, within one year after the date of final settlement of the prime contract.

Timeliness of the 90 day notice Defendants’ Contention

The defendants, Greene and Bregman, contend that the 90 day notice was not timely as to the materials furnished during the month of October 1956 and that, therefore, the use plaintiff is not entitled to judgment based upon the first four deliveries listed above, the agreed prices of which total $7,480.77. They thereby concede that the use plaintiff is entitled to judgment as to the remaining items totalling $1,978.88.

*520 The defendants contend that, since the materials were not furnished pursuant to an entire contract or on a running account basis but, rather, on a separate order basis, § 270b, required the use plaintiff to serve separate notices within 90 days from the date of the last delivery under each separate order; that, therefore, the 90 day notice is not timely as to the materials furnished between October 19 and October 27, 1956. Because there were separate orders, billed separately, the defendants contend in their memorandum of law that each order and delivery pursuant thereto was a separate contract; that the use plaintiff treated each order “as completely independent orders having nothing to do with the other orders which the plaintiff now lumps.”

The defendants cite no decision in which the Miller Act has been so construed. It would appear from the memo-randa of law submitted to the court by counsel for the use plaintiff and counsel for the defendants and the independent research of the court that this is a case of first impression.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City Rentals, LLC v. BBC Co.
947 N.E.2d 1103 (Massachusetts Appeals Court, 2011)
Specialty Products & Insulation Co. v. St. Paul Fire & Marine Insurance
788 N.E.2d 604 (New York Court of Appeals, 2003)
Specialty Products & Insulation Co. v. St. Paul Fire & Marine Insurance
287 A.D.2d 852 (Appellate Division of the Supreme Court of New York, 2001)
Insurance Co. of North America v. Genstar Stone Products Co.
656 A.2d 1232 (Court of Appeals of Maryland, 1995)
United States v. William L. Crow Construction Co.
826 F. Supp. 647 (E.D. New York, 1993)
United States v. Santa Fe Engineers, Inc.
822 F.2d 547 (Fifth Circuit, 1987)
Coast Electric Co. v. Industrial Indemnity Co.
144 Cal. App. 3d 879 (California Court of Appeal, 1983)
United States ex rel. Noland Co. v. Andrews
406 F.2d 790 (Fourth Circuit, 1969)
United States v. Andrews
406 F.2d 790 (Fourth Circuit, 1969)
Russell v. Travelers Indemnity Co.
244 F. Supp. 419 (W.D. Missouri, 1965)
Triangle Erectors, Inc. v. James King & Son., Inc.
41 Misc. 2d 12 (New York Supreme Court, 1963)
United States v. Thompson Construction Corp.
273 F.2d 873 (Second Circuit, 1959)
United States v. Peter Reiss Construction Co.
273 F.2d 880 (Second Circuit, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
172 F. Supp. 517, 1959 U.S. Dist. LEXIS 3456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-bregman-construction-corp-nyed-1959.