United States ex rel. General Electric Co. v. H. I. Lewis Construction Co.

375 F.2d 194
CourtCourt of Appeals for the Second Circuit
DecidedMarch 9, 1967
DocketNo. 246, Docket 30807
StatusPublished
Cited by7 cases

This text of 375 F.2d 194 (United States ex rel. General Electric Co. v. H. I. Lewis Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. General Electric Co. v. H. I. Lewis Construction Co., 375 F.2d 194 (2d Cir. 1967).

Opinion

WATERMAN, Circuit Judge:

On March 20, 1961, H. I. Lewis Construction Co., Inc., of Middletown, Pennsylvania (Lewis) entered into a contract with the United States to construct certain Radar Facilities at North Concord Air Force Station, North Concord, Vermont, and Aetna Insurance Company became surety on Lewis’s performance and payment bonds required by the Miller Act, 40 U.S.C. § 270a-e.1

On June 1, 1961, Lewis, as the prime contractor, subcontracted with The Dole [196]*196Company of Bangor, Maine (Dole) for the performance of the electrical work provided for in the General Contract between Lewis and the United States. The Aetna Casualty and Surety Company, a different company from Aetna Insurance Company, became surety in favor of Lewis on Dole’s subcontract performance and payment bonds. The Aetna Casualty and Surety Company’s performance bond was conditioned that Dole would perform according to its terms its subcontract with Lewis. Its labor and material payment bond was conditioned that Dole would pay all persons supplying Dole with labor and materials in the prosecution of the work provided for in the Dole subcontract with Lewis, subject to conditions stated therein, one of which was designed to meet the statutory requirements of 40 U.S.C. §§ 270b(a) and 270b (b). The condition in the bond was:

“(3) No suit or action shall be commenced hereunder by any claimant,
(a) Unless claimant shall have given written notice to any two of the following: The Principal, the Obligee, or the Surety above named, within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished, or for whom the work or labor was done or performed. * * *
(b) After the expiration of one (1) year following the date on which Principal ceased work on said subcontract.”

Promptly after June 1 Dole contacted General Electric Supply Company, a division of General Electric Company, at its outlet at 320 Pine Street, Burlington, Vermont, and ordered from it all the electrical items needed to perform its subcontract with Lewis. On June 6 and June 12, 1961, purchase orders for this material as required by the plans and specifications of the Lewis subcontract were placed. The materials were to be shipped when needed. There was some oral testimony to the effect that prior to completion of its work Dole may have purchased items from General Electric Supply Company in addition to the items contained in the purchase orders of June 6 and June 12, 1961. However, the only-invoices introduced, except one for a “rigid conduit” of August 23,1962, which has no bearing upon this case, and except the one of December 10, 1962 discussed in the text hereafter, were invoices of items contained in the purchase orders of June 6 and June 12.2

[197]*197Dole entered upon the performance of its subcontract with Lewis; all the materials required therefor that General Electric Supply Company at Burlington was to supply to Dole were shipped and delivered to Dole at the job site in North Concord between April 16, 1962 and August 3, 1962, both dates inclusive. Dole completed all work required under its subcontract with Lewis in the prosecution of the work provided for in the prime contractor’s contract with the Government on August 18, 1962, and, on August 27, 1962, submitted its statement to Lewis requisitioning the final unpaid balance due it from Lewis.

No further bill was ever sent by Dole to Lewis, but Dole ordered from General Electric Supply Company at 840 Hammond St., Bangor, Maine, two light fixtures to be shipped by the manufacturer, Miller Co. of Meriden, Conn., to Dole at Bangor, which were to replace two fixtures which had been broken after they were originally installed at North Con-eord. On December 10, 1962 these two fixtures were shipped by Miller to Bangor and thereafter were installed by Dole to replace the two broken fixtures.

These two fixtures were purchased on 3 separate purchase order, through a different General Electric Supply Company outlet than handled the original orders, were in addition to the original fixtures which had been furnished under the original purchase orders, cost Dole $26.70, $6.96 more than the two identical items ■cost on the original purchase order, were shipped 128 days after the last furnishing of the materials to Dole for the prosecution of the work provided for in its subcontract with Lewis and covered by the original purchase orders of June 1961, .and 104 days after Dole submitted its final requisition to Lewis. Dole, who ■installed them as a favor to the Corn-manding Officer of the military unit that had been moved into the completed facility at North Concord, never billed Lewis, or the United States, for them.

On January 17, 1963, General Electric first notified Lewis 3 that Dole had not paid for the materials furnished by it to Dole in the prosecution of the work provided for in Dole’s subcontract with Lewis. This notice was given more than 90 days, indeed 167 days, after General Electric’s final shipment of material of August 3 to the job site, and 143 days after Dole submitted its final requisition to Lewis — but within 90 days of the order for and the shipment of the two replacement fixtures.

General Electric Company not having received full payment from Dole, and Lewis and its surety Aetna Insurance Company having denied any liability for Dole’s debt, General Electric on September 25, 1963, as the use plaintiff, filed its action pursuant to the Miller Act, 40 U.S.C. § 270a, (b), in the United States District Court for the District of Vermont against Lewis and Aetna alleging that it had furnished materials to Dole for use on the North Concord project for which it had not been paid, that it had timely notified the prime contractor Lewis thereof, and that it was entitled to a judgment against the defendants of $9,066.69. The defendants answered on November 1, and also moved for leave to make Aetna Casualty and Surety Company a party to the action, attaching to its motion a third-party complaint against Aetna Casualty. This third-party complaint was served on January 20, 1964 and was answered by the third-party defendant on February 6, 1964. Dole itself, the purchaser of the material that had not been paid for, was never made a party.

[198]*198The district court tried the case without a jury, and awarded judgment of $6,676.75 to the use-plaintiff against the third-party defendant. From this judgment order and the denial of a motion to set aside the judgment, the third-party defendant appeals. We reverse the judgment below and remand with directions that judgment be entered for the third-party defendant-appellant, Aetna Casualty and Surety Company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
375 F.2d 194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-general-electric-co-v-h-i-lewis-construction-co-ca2-1967.