United States v. Thompson Construction Corp.

273 F.2d 873
CourtCourt of Appeals for the Second Circuit
DecidedDecember 16, 1959
DocketNo. 72, Docket 25667
StatusPublished
Cited by2 cases

This text of 273 F.2d 873 (United States v. Thompson Construction Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Thompson Construction Corp., 273 F.2d 873 (2d Cir. 1959).

Opinion

FRIENDLY, Circuit Judge.

We must determine on this appeal whether sufficient notice was given defendant The Thompson Construction Corp. to entitle the use plaintiff, J. A. Edwards & Co., Inc., which furnished materials to a subcontractor, Ben B. Greene, Inc., to recover from Thompson and its surety under the bonds furnished by the latter pursuant to the Miller Act, 40 U.S.C.A. § 270a(a) (2) and 270b(a). Judge Dawson, in a reasoned opinion, held the notice did not meet the requirement of the statute. We agree.

In 1955 the United States entered into a contract with Thompson for the construction of a Nike site at Lewiston, N. Y. Pursuant to the Miller Act, 40 U.S. C.A. § 270a(a)(2), Thompson executed a standard government payment bond to the United States wherein Thompson was the principal and Standard Accident Insurance Company was the surety, “for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract for the use of each such person.” Thompson employed a subcontractor, Ben B. Greene, Inc., for the performance of certain electrical work. Greene in turn requested Edwards to furnish electrical materials and supplies for use in Greene’s ■subcontract. The Lewiston project was by no means the only Nike project where ■Greene did this. We have another such case in United States for use and benefit •of J. A. Edwards & Co. v. Peter Reiss Construction Co., 2 Cir., 273 F.2d 880. United States for use and benefit of J. A. Edwards & Co. v. Bregman Construction Corp., D.C.E.D.N.Y.1959, 172 F. Supp. 517, is still another.

In the claim dismissed by the District Court, Edwards sought to recover from Thompson and its surety a balance of $7,313.70 due for deliveries •of material between September 19 and October 13, 1956. Edwards did not contend it had any contractual relationship with Thompson. It relied rather on the proviso in § 270b (a) of the Miller Act, 40 U.S.C.A. § 270b(a), which we quote in the margin.1 It claims that the [875]*875statutory requirement of notice was satisfied by a letter dated January 9, 1957 sent by Greene to Thompson at Edwards’ instance which we quote below,2 at least when the letter is taken in conjunction with other facts.

Judge Dawson held the letter did not meet the statutory requirements because “the prime contractor, upon receipt of the notice from the subcontractor, was in no position to know that it had emanated from the materialman,” [172 F. Supp. 164] because the letter did not set forth with substantial accuracy the amount claimed by Edwards, because the letter did not state it was related to material supplied for the subject contract, and because the letter afforded no indication that it was to be interpreted as a notice under the Miller Act. Accordingly he directed that the action be dismissed as against the contractor and the surety but awarded judgment against the subcontractor Greene, who had defaulted in the action.

The reason why the Miller Act conditions the rights of a person having “no contractual relationship express or implied with the contractor furnishing said payment bond” upon the giving of proper notice within ninety days from the date “on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made,” is readily understandable. It was assumed that such third parties will first endeavor to collect from the subcontractor with whom they have a contract relation. During a reasonable period, while these efforts are going forward, the contractor withholds the payments due the subcontractor. If he receives a third party claim within ninety days, he reserves appropriate amounts from monies otherwise owing to the subcontractor. But, once ninety days have elapsed without such notice, he is free to pay the subcontractor for the latter's work without risk of liability under his bond to laborers and materialmen whose sole contractual relation is with the subcontractor. A statute which gave rights on the contractor’s bond to laborers and material-men having no contractual relations with him but which did not require timely and adequate notice to him, would lead either [876]*876to double payments or to interminable delay in settlements between contractors and subcontractors to guard against these, — in either case with attendant prejudice to all concerned.

The notice which the Miller Act requires is one meeting this basic purpose. Its essence is, as said in United States for Use of Bruce Co. v. Fraser Construction Co., D.C.W.D.Ark.1949, 87 F.Supp. 1, 5, that it must show it “was intended to be the presentation of a claim,” a claim against the contractor and its surety by the laborer or material-man in the latter’s own right. In addition, it must state “with substantial accuracy” the amount claimed to be owing the laborer or materialman on the project and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. If it meets these simple and basic requirements, no degree of formality is needed. But meet them it must, for otherwise the purpose of the notice requirement would be frustrated. And while the United States has an interest in the payment of all persons furnishing labor and materials to government projects, it also has an interest in the prompt settlement of accounts between contractors and subcontractors and in avoiding undue and preventable losses to contractors and their sureties — costs which in the long run the public pays.

The letter of January 9, 1957 did not measure up to this test. The letter was a request by Greene that Thompson consent to Greene’s assigning to Edwards monies payable to Greene by Thompson under the subcontract the relevant paragraph of which is quoted below3 — that and nothing more. It was signed by Greene, the subcontractor, not by Edwards, the materialman. It in no way indicated that Edwards was making any direct claim against Thompson and Thompson’s surety for materials furnished on the Lewiston project or that Greene was making any such claim on Edwards’ behalf. The letter refers only to amounts owing by Thompson to Greene; it says nothing about amounts owed by anyone to Edwards and certainly nothing about amounts owed by Greene to Edwards for materials supplied by Edwards on the Lewiston job, the only item for which the Miller Act gave Edwards a claim against Thompson and the surety. To be sure, Thompson would hardly have thought Greene was making Edwards a present of Greene’s claim against Thompson; but it could perfectly well have thought that Edwards had been fully paid for materials on the Lewiston project and that the assignment related to other Greene-Edwards transactions. It is of no consequence that the balance of $7,527.98, which was then thought to be the amount owing to Greene from Thompson, approximates the amount of $7,313.70 now claimed by Edwards against Greene for materials at Lewiston. So far as appears, this is pure coincidence. In any event, there was nothing in the letter to show, as the Act requires, how much Edwards claimed to be due it from Greene for materials furnished to the particular work. The facts, made much of by plaintiff, that the letter was signed by Greene at plaintiff’s instance and that plaintiff’s vice-president put it in the mail, are equally irrelevant. For while we assume that Thompson did not suppose the letter was spontaneous with Greene, nothing on its face gave Thompson any reason to think that a direct claim against Thompson and the surety was being asserted on Edwards’ behalf for Lewiston materials.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Cas. and Sur. Co. v. Honeywell, Inc.
380 So. 2d 1385 (Mississippi Supreme Court, 1980)
United States v. Thompson Construction Corp.
273 F.2d 873 (Second Circuit, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
273 F.2d 873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-thompson-construction-corp-ca2-1959.