United States v. Thompson Construction Corp.

273 F.2d 873, 78 A.L.R. 2d 421, 1959 U.S. App. LEXIS 4655
Court of Appeals for the Second Circuit·Decided December 16, 1959·No. 25667·Published·Cited by 25 cases

Opinion

273 F.2d 873

UNITED STATES of America for the Use and Benefit of J. A. EDWARDS & CO., Inc., Plaintiff-Appellant,
v.
THOMPSON CONSTRUCTION CORP. and Standard Accident Insurance Company, Defendants-Appellees, and
Ben B. Greene, Inc., Defendant.

No. 72.

Docket 25667.

United States Court of Appeals Second Circuit.

Argued November 20, 1959.

Decided December 16, 1959.

Irving Levine, New York City, for plaintiff-appellant.

Carl E. Buckley, New York City (Nevius, Jarvis & Pilz, New York City, on the brief), for defendants-appellees.

Before MEDINA, MOORE and FRIENDLY, Circuit Judges.

FRIENDLY, Circuit Judge.

We must determine on this appeal whether sufficient notice was given defendant The Thompson Construction Corp. to entitle the use plaintiff, J. A. Edwards & Co., Inc., which furnished materials to a subcontractor, Ben B. Greene, Inc., to recover from Thompson and its surety under the bonds furnished by the latter pursuant to the Miller Act, 40 U.S.C.A. § 270a(a) (2) and 270b(a). Judge Dawson, in a reasoned opinion, held the notice did not meet the requirement of the statute. We agree.

In 1955 the United States entered into a contract with Thompson for the construction of a Nike site at Lewiston, N. Y. Pursuant to the Miller Act, 40 U.S. C.A. § 270a(a)(2), Thompson executed a standard government payment bond to the United States wherein Thompson was the principal and Standard Accident Insurance Company was the surety, "for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract for the use of each such person." Thompson employed a subcontractor, Ben B. Greene, Inc., for the performance of certain electrical work. Greene in turn requested Edwards to furnish electrical materials and supplies for use in Greene's subcontract. The Lewiston project was by no means the only Nike project where Greene did this. We have another such case in United States for use and benefit of J. A. Edwards & Co. v. Peter Reiss Construction Co., 2 Cir., 273 F.2d 880. United States for use and benefit of J. A. Edwards & Co. v. Bregman Construction Corp., D.C.E.D.N.Y.1959, 172 F. Supp. 517, is still another.

In the claim dismissed by the District Court, Edwards sought to recover from Thompson and its surety a balance of $7,313.70 due for deliveries of material between September 19 and October 13, 1956. Edwards did not contend it had any contractual relationship with Thompson. It relied rather on the proviso in § 270b(a) of the Miller Act, 40 U.S.C.A. § 270b(a), which we quote in the margin.1 It claims that the statutory requirement of notice was satisfied by a letter dated January 9, 1957 sent by Greene to Thompson at Edwards' instance which we quote below,2 at least when the letter is taken in conjunction with other facts.

Judge Dawson held the letter did not meet the statutory requirements because "the prime contractor, upon receipt of the notice from the subcontractor, was in no position to know that it had emanated from the materialman," [172 F. Supp. 164] because the letter did not set forth with substantial accuracy the amount claimed by Edwards, because the letter did not state it was related to material supplied for the subject contract, and because the letter afforded no indication that it was to be interpreted as a notice under the Miller Act. Accordingly he directed that the action be dismissed as against the contractor and the surety but awarded judgment against the subcontractor Greene, who had defaulted in the action.

The reason why the Miller Act conditions the rights of a person having "no contractual relationship express or implied with the contractor furnishing said payment bond" upon the giving of proper notice within ninety days from the date "on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made," is readily understandable. It was assumed that such third parties will first endeavor to collect from the subcontractor with whom they have a contract relation. During a reasonable period, while these efforts are going forward, the contractor withholds the payments due the subcontractor. If he receives a third party claim within ninety days, he reserves appropriate amounts from monies otherwise owing to the subcontractor. But, once ninety days have elapsed without such notice, he is free to pay the subcontractor for the latter's work without risk of liability under his bond to laborers and materialmen whose sole contractual relation is with the subcontractor. A statute which gave rights on the contractor's bond to laborers and materialmen having no contractual relations with him but which did not require timely and adequate notice to him, would lead either to double payments or to interminable delay in settlements between contractors and subcontractors to guard against these, — in either case with attendant prejudice to all concerned.

The notice which the Miller Act requires is one meeting this basic purpose. Its essence is, as said in United States for Use of Bruce Co. v. Fraser Construction Co., D.C.W.D.Ark.1949, 87 F.Supp. 1, 5, that it must show it "was intended to be the presentation of a claim," a claim against the contractor and its surety by the laborer or materialman in the latter's own right. In addition, it must state "with substantial accuracy" the amount claimed to be owing the laborer or materialman on the project and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. If it meets these simple and basic requirements, no degree of formality is needed. But meet them it must, for otherwise the purpose of the notice requirement would be frustrated. And while the United States has an interest in the payment of all persons furnishing labor and materials to government projects, it also has an interest in the prompt settlement of accounts between contractors and subcontractors and in avoiding undue and preventable losses to contractors and their sureties — costs which in the long run the public pays.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Thompson Construction Corp., 273 F.2d 873, 78 A.L.R. 2d 421, 1959 U.S. App. LEXIS 4655 (2d Cir. 1959).

273 F.2d 873 (United States v. Thompson Construction Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brox v. H.J. Stabile
21 F.3d 419 (First Circuit, 1994)
Chicago Rigging Co. v. Uniroyal Chemical Co., Inc.
718 F. Supp. 696 (N.D. Illinois, 1989)
Lezzer Cash & Carry, Inc. v. Aetna Insurance
537 A.2d 857 (Supreme Court of Pennsylvania, 1988)
Stauffer Construction Co. v. Tate Engineering, Inc.
27 Cont. Cas. Fed. 80,200 (Court of Special Appeals of Maryland, 1979)
Consolidated Concrete Co. v. Empire West Construction Co.
596 P.2d 106 (Idaho Supreme Court, 1979)
Westinghouse Electric Corp. v. Minnix
269 A.2d 580 (Court of Appeals of Maryland, 1970)
State Ex Rel. Komac Paint & Wallpaper Store v. McBride
392 P.2d 577 (New Mexico Supreme Court, 1964)
United States v. Van Riet
316 F.2d 912 (Fourth Circuit, 1963)