Glassell-Taylor Co. v. Magnolia Petroleum Co.

153 F.2d 527, 1946 U.S. App. LEXIS 3157
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 23, 1946
Docket11318
StatusPublished
Cited by49 cases

This text of 153 F.2d 527 (Glassell-Taylor Co. v. Magnolia Petroleum Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glassell-Taylor Co. v. Magnolia Petroleum Co., 153 F.2d 527, 1946 U.S. App. LEXIS 3157 (5th Cir. 1946).

Opinion

BORAH, District Judge.

The United States, for the use and benefit of the Magnolia Petroleum Company, sued Core & Planche, subcontractor, Robinson & Young, and Glassell-Taylor, prime contractors, and St. Paul Mercury Indemnity Company, insurance carrier for the prime contractors, on a statutory payment bond, to recover for gasoline and oils alleged to have been furnished and delivered to the subcontractor “in the prosecution of the work” under a contract with the United States Government in connection with the building of an airdrome near DeRidder, in Louisiana.

The suit finds life and is authorized by the Act of August 24, 1935, 49 Stat. 793, Title 40 U.S.C.A. §§ 270a and 270b, known as the Miller Act.

In July, 1942, the two contracting firms, Robinson & Young and Glassell-Taylor Company, acting as associate contractors, entered into a contract with the United States to “furnish the. material and perform the work necessary for the construction and completion of Perimeter and Dispersal Taxiways and Hard Standings, Concrete Aprons and Tie-Down Anchors for Hard Standings at DeRidder Airdrome, DeRidder, Louisiana.”

The work undertaken by the subcontractor, Core & Planche, was: “ * * * to furnish, haul, spread and set up approximately 45,000 cubic yards of sand clay gravel base course for $1.77 per cubic yard, a total of approximately $79,650.00. Approximately 13,000 cubic yards of aggregate for the asphaltic concrete surface course for $1.45 per cubic yard, approximately $18,850.00, delivered to your plant at Hite, Louisiana.”

By way of answer, all the defendants, save Core & Planche, which allowed judgment to go against it by default, entered pleas of general denial, and the insurance carrier further sought by cross-claim a recovery against the prime contractors as partnerships and also against each partner individually for any judgment that might be rendered against it.

The issues were tried by the court without the intervention of a jury, and at the conclusion of the trial, judgment was entered for the use plaintiff, Magnolia Petroleum Company, and against Core & Plan-che, Robinson & Young, and Glassell-Taylor Company, and St. Paul Mercury Indemnity Company, in solido, for the sum of $4,991.65 with 5% interest per annum from January 5, 1943. An additional judgment was decreed for the use plaintiff, Magnolia Petroleum Company, and against Core & Planche in the further sum of $517.50 with 5% interest per annum thereon from February 5, 1943. The judgment further provided that the use plaintiff’s right to sue Core & Planche for any additional indebtedness not covered by the judgment entered was reserved by it. Judgment was further decreed in favor of St. Paul Mercury Indemnity Company and against Robinson & Young, Glassell-Taylor Company, and each member of the two firms individually, in solido, for the sum of $4,991.65, with interest at the rate of 5% per annum from February 5, 1943; the judgment providing that on and after St. Paul Mercury Indemnity Company paid over to the use plaintiff, Magnolia Petroleum Company, such recited judgment, interest and costs, that thereupon the St. Paul Mercury Indemnity Company was to be legally subrogated to all the rights of use plaintiff against the two partnerships and each member of the partnerships individually, to the extent of the judgment rendered against it.

The prime contractors and surety have appealed from this judgment contending that the sale and delivery to the subcontractor of the materials that the use plaintiff is suing for were not proved; that even if said sale and delivery had been proved, much of the said material was not used in the prosecution of the work in question; that a considerable portion of same never reached the job site; that the use plaintiff failed to prove that part of the materials which was used in the prosecution of the work or that reached the job site; and that therefore the use plaintiff is not entitled to judgment against them for any amount whatsoever. The use plaintiff on cross-appeal contends that the judgment granted by the district cour1 *529 should have been for the full amount of the account, $5,509.15, and that the district court erred in rejecting a part of plaintiff’s demand amounting to $517.50.

The evidence shows that Core & Plan-che, the subcontractor, opened pits and moved sand and gravel to the airdrome, which was under construction near De-Ridder, Louisiana. They used in the movement of this sand and gravel about thirty trucks, ten of which they owned and the other twenty were rented. These trucks would report in the morning at the filling station and were allowed to take gasoline and oil at wholesale prices. The drivers of the trucks would sign a credit slip. The trucks were then driven to the airdrome site to ascertain if any material was needed. If there was hauling to be done the trucks would then go to one of the pits and haul the type of material the foreman or engineer was ready to use. If there was no work the truck driver went wherever he pleased and burned the gasoline and oil as he saw fit, either to work at another job or to travel at his pleasure. In the course of their operations it was sometimes necessary for the trucks to consume extra mileage in traveling'to the filling station at DeRidder for replenishment of fuel and on one occasion oil and gasoline were taken from this DeRidder filling station to transport the entire fleet of subcontractor’s equipment and trucks a distance of one hundred miles. This was done at the instance and for the benefit of the prime contractors in connection with their contract at Alexandria, Louisiana.

The entire amount of gasoline and oils used by the subcontractor was purchased from the use plaintiff, which provided tanks at points designated by the subcontractor. Sand and gravel were furnished under the direction of the supervising engineers, who called for the kind they desired. At a later time washed gravel was shipped in to go into the building of the airdrome. The three pits from which the sand and gravel were taken were known as the Gimmich, the Wellborn and Cooley pits and they were located around and near DeRidder. The office, repair shops and truck garage were located by the subcontractor in DeRidder. The use plaintiff furnished a filling station at DeRidder and at the Cooley pit.

The invoices from the use plaintiff were made in triplicate and show the time, the place and the amount of each delivery to the subcontractor and the name of the employee receiving the goods on behalf of the subcontractor. A copy of each invoice was retained in the local office of use plaintiff, a copy was mailed to its district office and a copy was furnished to the subcontractor.

The invoices numbers 1 to 127, inclusive, showing accurately the date, amount of purchase, place, and who signed in receipt for the subcontractor, were properly received in evidence under the Act of June 20, 1936, 49 Stat. 1561, 28 U.S.C.A. § 695, and when considered in the light of the testimony proved conclusively that the use plaintiff sold and delivered to the subcontractor the materials in the amount claimed. No materials of like nature were furnished by any other materialman.

The further contentions of appellants are likewise without merit. There is no provision in the statute requiring that materialmen must deliver the materials at the job site or that the materials be “used” in the prosecution of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Hirani Engineering & Land
58 F.4th 1250 (D.C. Circuit, 2023)
United States Ex Rel. Shannon v. Federal Insurance
251 F. App'x 269 (Fifth Circuit, 2007)
J D Fields & Co, Inc v. Gottfried Corp
272 F.3d 692 (Fifth Circuit, 2001)
United States v. Avanti Constructors, Inc.
750 F.2d 759 (Ninth Circuit, 1984)
Slagle-Johnson Lumber Co. v. Landis Const. Co.
379 So. 2d 479 (Supreme Court of Louisiana, 1980)
Solite Masonry Units Corp. v. Piland Construction Co.
232 S.E.2d 759 (Supreme Court of Virginia, 1977)
Kuhn v. Torr Construction Co.
64 Pa. D. & C.2d 332 (Cambria County Court of Common Pleas, 1974)
State ex rel. Evans Equipment Co. v. Johnson Construction Co.
160 N.W.2d 637 (South Dakota Supreme Court, 1968)
Ruberoid v. GLASSMAN CONSTRUCTION COMPANY, INC.
234 A.2d 875 (Court of Appeals of Maryland, 1967)
Robson v. United Pacific Insurance Company
391 S.W.2d 855 (Supreme Court of Missouri, 1965)
State Ex Rel. Komac Paint & Wallpaper Store v. McBride
392 P.2d 577 (New Mexico Supreme Court, 1964)
International Harvester Co. v. L. G. DeFelice & Son, Inc.
197 A.2d 638 (Supreme Court of Connecticut, 1964)
United States ex rel. Betts v. Continental Casualty Co.
224 F. Supp. 857 (W.D. Pennsylvania, 1964)
United States v. Aetna Casualty & Surety Company
297 F.2d 665 (Second Circuit, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
153 F.2d 527, 1946 U.S. App. LEXIS 3157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glassell-taylor-co-v-magnolia-petroleum-co-ca5-1946.