United States Ex Rel. Shannon v. Federal Insurance

251 F. App'x 269
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 4, 2007
Docket06-60906
StatusUnpublished

This text of 251 F. App'x 269 (United States Ex Rel. Shannon v. Federal Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Shannon v. Federal Insurance, 251 F. App'x 269 (5th Cir. 2007).

Opinion

PER CURIAM: *

Plaintiff Roy Shannon (“Shannon”) was employed as a project manager at White-sell-Green, Inc. (“WGI”). WGI entered into a joint venture (“Joint Venture”) with another company, W.G. Yates & Sons Construction Company (“Yates”), so that they could pool them resources and bid on construction contracts at Keesler Air Force Base in Biloxi, Mississippi (“Keesler”). Shannon assumed the position of project manager for the Joint Venture. He was put on the Joint Venture’s payroll in October of 1998. Shannon remained the project manager of the Joint Venture at Keesler until February 2004, when he was terminated.

Shannon’s contract with the Joint Venture was unwritten, and though the parties to this case all agree that a contract existed, they disagree about the terms. It is undisputed that Shannon’s position carried a salary of $2,000 per week, plus an annual Christmas bonus of at least $50,000. It is also undisputed that Shannon received this sum for approximately five and a half years. However, Shannon claims that he was entitled to receive additional compensation of three types. First, he claims that he was entitled to one-half the profits above and beyond the originally anticipated profits, if any, earned by the Joint Venture on the first project. Second, he says that once the Joint Venture began to bid on additional contracts, there was an unwritten agreement that he would receive one percent of the contract amount of each subsequent contract, regardless of profit. Third, Shannon says that an SUV, which was purchased by the company but used exclusively by him, was his to keep, and that the Joint Venture breached its unwritten agreement by repossessing the vehicle some six months after his termination. Having not received the compensation to which he believed he was entitled, Shannon filed this lawsuit, asserting claims for breach of contract, quantum meruit, and wrongful discharge.

Shannon also included a federal claim under the Miller Act, 40 U.S.C. §§ 3131, 3133, which explains how an otherwise ordinary contract case, raising several questions of Mississippi state law, ended up in *271 federal court. Under the Miller Act, before any contract of more than $100,000 for the construction, alteration, or repair of any public building or public work of the United States is awarded to any person, such person is required to furnish to the United States both a performance bond and a payment bond. The performance bond guarantees federal taxes on wages paid by the contractor to his or her employees. The payment bond is “for the protection of all persons supplying labor and material in carrying out the work provided for in the contract for the use of each person.” 40 U.S.C. § 3131(b)(2). The purpose of the Act is “to protect those whose labor and materials go into public projects,” MacEvoy Co. v. United States, 322 U.S. 102, 107, 64 S.Ct. 890, 88 L.Ed. 1163 (1944) (citations omitted). On this basis, Shannon brought a federal claim against the sureties charged with protection of the payment bond.

The district court granted summary judgment for the defendants on all four of Shannon’s claims, and Shannon appealed. We review motions for summary judgment de novo, applying the same standards as the district court. Fed. R. Civ. P. 56. Summary judgment is inappropriate whenever a genuine issue of material fact exists. A genuine issue of material fact exists when, in the context of the entire record, a reasonable fact-finder could return a verdict for the non-movant. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). All evidence must be construed in the light most favorable to the party opposing summary judgment. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587-88, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986) (citations omitted).

1. Breach of Contract

The district court granted summary judgment on Shannon’s breach of contract claim after finding that it was barred by the statute of limitations. There is no dispute that the relevant limitations period for breach of an unwritten contract is one year from the time the cause of action accrued. Miss.Code § 15-1-29 (1972). The only dispute is the date of accrual. In Mississippi, a cause of action accrues as soon as the cause of action exists. See, e.g., Greenlee v. Mitchell, 607 So.2d 97, 110 (Miss.1992). In breach of contract cases, that is the time “when the breach, not the injury, accrues,” or, in other words, “at the time of the breach regardless of when damages resulting from the breach occur.” First Trust Nat’l Ass’n v. First Nat’l Bank of Commerce, 220 F.3d 331, 334-35 (5th Cir.2000). Because the plaintiff, in effect, is alleging two different breaches, one for the first project and one for all subsequent projects, we treat them separately.

As to the first project, Shannon claims that he was entitled to one half of the profits above and beyond $2.5 million, which was the original estimated profit. As of September 29, 2003, Shannon knew that the operation would be more profitable than originally anticipated, and thus that he was entitled to some gain. However, at that point Shannon says he could not have known exactly how profitable the project would be, and thus could not know exactly how much money he would receive. Instead, he argues that the accrual date is the date the project was physically completed, which occurred some time in December of 2004. Shannon did not file his lawsuit until February, 2, 2005.

We find Shannon’s argument unavailing. First, the foregoing case law makes plain that the date of breach, not the date of injury (or, in Shannon’s case, the date on which the full extent of the injury was finally calculable) is the controlling date *272 for accrual purposes. Shannon has presented no case law to support the proposition that a party must know to a mathematical certainty the amount of recovery to which he is entitled. In fact, the analogous case law in Mississippi suggests otherwise. See, e.g., Jackson v. State Farm Mut. Auto. Insur. Co., 880 So.2d 336, 341 (Miss.2004) (holding, in uninsured motorist context, that action accrues once someone “knows, or reasonably should know, that the damages he or she claims to have suffered exceed the limits of insurance available to the alleged tortfeasor”). Second, we must note that Shannon drastically overstates his uncertainty as of September 2003.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Greenlee v. Mitchell
607 So. 2d 97 (Mississippi Supreme Court, 1992)
Glassell-Taylor Co. v. Magnolia Petroleum Co.
153 F.2d 527 (Fifth Circuit, 1946)
Perry v. Sears, Roebuck & Co.
508 So. 2d 1086 (Mississippi Supreme Court, 1987)
Levens v. Campbell
733 So. 2d 753 (Mississippi Supreme Court, 1999)
Jackson v. State Farm Mut. Auto. Ins. Co.
880 So. 2d 336 (Mississippi Supreme Court, 2004)
United States Ex Rel. Constructors, Inc. v. Gulf Insurance
313 F. Supp. 2d 593 (E.D. Virginia, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
251 F. App'x 269, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-shannon-v-federal-insurance-ca5-2007.