Ruberoid v. GLASSMAN CONSTRUCTION COMPANY, INC.

234 A.2d 875, 248 Md. 97, 1967 Md. LEXIS 303
CourtCourt of Appeals of Maryland
DecidedNovember 20, 1967
Docket[No. 627, September Term, 1966.]
StatusPublished
Cited by26 cases

This text of 234 A.2d 875 (Ruberoid v. GLASSMAN CONSTRUCTION COMPANY, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ruberoid v. GLASSMAN CONSTRUCTION COMPANY, INC., 234 A.2d 875, 248 Md. 97, 1967 Md. LEXIS 303 (Md. 1967).

Opinion

Barnes, J.,

delivered the opinion of the Court.

This appeal involves questions of whether an unpaid supplier of materials to a public school construction project has *99 the protection of the payment bond of the general contractor and its surety and if so, whether the entire amount of the materials, furnished are within such protection.

The basic facts are not in dispute. On June 18, 1963, Glass-man Construction Co., Inc., (Glassman, general contractor or principal) contracted in writing with the Board of Education of Prince George’s County, Maryland (owner), for the construction of the William Wirt Junior High School. In accordance with the provisions of Code, Article 90, section 11, Glass-man, as principal, and The Home Indemnity Company, as surety, executed and delivered to the owner a labor and material payment bond which contained the following relevant provisions :

The condition was that:

“if the Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of the Contract, then this obligation shall be void;* * *.”
“A claimant is defined as one having a direct contract with the Principal or with a subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the contract, * * *.”

On July 24, 1963, Glassman entered into a written subcontract for the resilient floor tile work on the school with James R. Miller, a sole proprietorship doing business as Miller Floor Company in Arlington, Virginia (Miller). This subcontract contained the following relevant provisions:

“4. * * * At the Contractor’s option payments may be made jointly to the Subcontractor and his suppliers.
“13. In the event that the Contractor shall require a Performance and/or Payment Bond after this agreement has been executed, the Subcontractor shall furnish such bond in an amount, form, and with a company acceptable to the Contractor. Cost of the bond *100 under these circumstances only, will be borne by the Contractor.
“14. The Subcontractor agrees to hold the Contractor harmless from any claims or disputes, and will defend any law suit or dispute brought against the Contractor for any reasons whatsoever, which may arise due to any act of the Subcontractor.
“22. The Subcontractor shall not assign or transfer this contract or any part thereof or any interest therein, without the written consent of the Contractor.
“24. The Contractor reserves the right to withhold all or any part of partial payments, in addition to retained percentage withheld, until final completion, due the Subcontractor, for non-compliance with any of the terms of this Agreement, and shall be withheld until such time as said non-compliance has been corrected to the satisfaction of the Contractor.
“25. (a) If, at any time, there shall be asserted any lien or any other claim of any kind for which the Contractor or the said premises might become liable, and which is chargeable to the Subcontractor or his subcontractors, the Contractor shall have the right to retain out of any payment then due or thereafter to become due, an amount sufficient to completely discharge or pay any such lien or claim, including attorney’s fees claimed by the lienor or other claimant, and to apply the amount thus retained for such discharge •or payment. Any such application of sums due or to become due hereunder shall be taken and deemed to have been made in satisfaction of the Contractor’s obligation for payment under this agreement. Should any such lien or claim be made or established after all payments are made, the Subcontractor shall refund and repay to the Contractor all monies that the latter may be compelled to pay in discharging or disposing thereof and of any other claim made in consequence of the Subcontractor’s default, and this agreement shall not be affected by the final certificates or the final payment.
“27. The Subcontractor, at any time or times dur *101 ing the course of this Agreement, upon the request of the Contractor, shall furnish the said Contractor evidence, in whatever form the Contractor may require, that all obligations of persons or firms performing work and/or supplying materials, equipment or services, or Social Security and Withholding Taxes, incurred by the Subcontractor under this Agreement have been met, paid, satisfied or discharged. Before commencing work, Subcontractor will furnish a complete list of his subcontractors and suppliers to the Contractor.”

On March 26, 1964, prior to having performed any work on the school construction, Miller incorporated his business under the laws of the Commonwealth of Virginia, as Miller Floor Company, Inc. (Miller, Inc.). After this change in form, the business in all material respects continued as before, with Miller as manager and sole owner of Miller, Inc. Miller, however, after the incorporation of the business did no more work under the sole proprietorship form of doing business.

In July, 1964, the construction work on the school having reached the stage for the installation of the resilient tile floors, Miller, Inc. ordered from The Ruberoid Co., a manufacturer of resilient floor materials at its plant in Newburgh, New York (Ruberoid) certain flooring materials in the amount of $16,-557.37. This order was placed by telephone and was later confirmed by a written purchase order which contained the heading “Miller Floor Company, Inc.” and designated the ordered materials to be for the William Wirt Junior High School project.

Ruberoid had first sold materials to Miller in December, 1963, and at that time knew that Miller was an individual trading as Miller Floor Company. In July, 1964, Ruberoid became aware that its customer was then Miller, Inc. since the letterheads and purchase order then received were so marked and Ruberoid received a report from Dun & Bradstreet that its customer had incorporated.

Ruberoid shipped the ordered materials by common carrier to the job site where they were received and signed for by Miller, Inc. At no time were any of the materials in the possession of Glassman. Of the materials furnished by Ruberoid in the total *102 amount of $16,557.37, materials of the value of $8,009.25 were not used on the school construction, but without the knowledge of Ruberoid, Glassman or the surety, were diverted by Miller, Inc. to some other use unknown to them. It was stipulated that the diverted materials were either tiles of a color not specified on the job by the owner or, if of a specified color, exceeded the quantity of tiles required for the construction of the school.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Matter of Petition of Featherfall Restoration
Court of Appeals of Maryland, 2025
Water Applications & Systems Corp. v. Bituminous Casualty Corp.
2013 IL App (1st) 120983 (Appellate Court of Illinois, 2013)
Pro-Edge L.P. v. Gue
419 F. Supp. 2d 1064 (N.D. Iowa, 2006)
Norlund v. Faust
675 N.E.2d 1142 (Indiana Court of Appeals, 1997)
Elzinga & Volkers, Inc. v. LSSC CORP.
838 F. Supp. 1306 (N.D. Indiana, 1993)
Graceman v. Goldstein
613 A.2d 1049 (Court of Special Appeals of Maryland, 1992)
Homa v. Friendly Mobile Manor, Inc.
612 A.2d 322 (Court of Special Appeals of Maryland, 1992)
Atlantic Sea-Con, Ltd. v. Robert Dann Co.
582 A.2d 981 (Court of Appeals of Maryland, 1990)
Atlantic Sea-Con. Ltd. v. Robert Dann Co.
560 A.2d 592 (Court of Special Appeals of Maryland, 1989)
Alexander & Alexander, Inc. v. Koelz
722 S.W.2d 311 (Missouri Court of Appeals, 1986)
Citizens Bank & Trust Co. v. Barlow Corp.
456 A.2d 1283 (Court of Appeals of Maryland, 1983)
Sun World Corp. v. Pennysaver, Inc.
637 P.2d 1088 (Court of Appeals of Arizona, 1981)
Nicolas M. Salgo Associates v. Continental Illinois Properties
532 F. Supp. 279 (District of Columbia, 1981)
Parkside Mobile Estates v. Lee
270 N.W.2d 758 (Supreme Court of Minnesota, 1978)
Rother-Gallagher v. Montana Power Company
522 P.2d 1226 (Montana Supreme Court, 1974)
Grinnell Co. v. City of Crisfield
287 A.2d 486 (Court of Appeals of Maryland, 1972)
Westinghouse Electric Corp. v. Minnix
269 A.2d 580 (Court of Appeals of Maryland, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
234 A.2d 875, 248 Md. 97, 1967 Md. LEXIS 303, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ruberoid-v-glassman-construction-company-inc-md-1967.