Westinghouse Electric Corp. v. Minnix

269 A.2d 580, 259 Md. 305, 1970 Md. LEXIS 809
CourtCourt of Appeals of Maryland
DecidedOctober 19, 1970
Docket[No. 9, September Term, 1970.]
StatusPublished
Cited by4 cases

This text of 269 A.2d 580 (Westinghouse Electric Corp. v. Minnix) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westinghouse Electric Corp. v. Minnix, 269 A.2d 580, 259 Md. 305, 1970 Md. LEXIS 809 (Md. 1970).

Opinion

Finan, J.,

delivered the opinion of the Court.

We must determine on this appeal the sufficiency of notice given a contractor by the supplier of materials to .a subcontractor of its claim for an unpaid balance. Involved is the question of sufficiency of notice as required by Code (1969 Repl. Vol.) Art. 90, § 11 (c), as well as the legal import of provisions of a payment bond which places a more onerous burden on the supplier regarding notice than does the Statute.

Westinghouse Electric Corporation, plaintiff-appellant and supplier of materials, sued A. C. Minnix and Sons, a general contractor, and Reliance Insurance Company, the surety, both defendants and appellees, on a payment bond for the unpaid balance due it for materials sold and delivered to an electrical subcontractor, Henry B. Johnson, Jr., incident to the construction of a public junior high school, in Montgomery County. The Circuit Court for *307 Montgomery County, rendering judgment for the defendants, disallowed the claim on the ground that the supplier had failed to give proper notice of its claim to the contractor as required by Code (1969 Repl. Vol.) Art. 90, §11 (c).

In addition to the notice which the Statute requires the supplier to give the contractor, the payment bond provided that the supplier give notice to any two of “The Principal, Owner or Surety * * The appellees, in the court below, raised the issue of the sufficiency of the notice viewed in light of the Statute, as well as the question of the legal effect of the dual notice requirement provided in the payment bond. However, the lower court disposed of the case on the basis of the failure of notice as required by the Statute and hence it became unnecessary for it to reach the issue regarding the legal significance of the notice provisions in the payment bond.

The appellant concedes that it made.no effort to give notice of its claim to either the Montgomery County Board of Education or the Reliance Insurance Company as required by the terms of the payment bond. The lower court also made findings of facts, which are not disputed on appeal, to the effect that $3,151.97 is the correct unpaid balance due and owing Westinghouse for materials, that the subcontractor Johnson is financially unable to pay the balance and, that the letter dated September 26, 1968, sent from Westinghouse to the contractor (which we will later discuss) was mailed and received within the 90 day statutory period. The question of the legal sufficiency of this letter as proper notice is the pivotal question in this case.

Article 90, § 11 (c) provides in pertinent part:

“* * * any person having direct contractual relationship with a subcontractor of the contractor * * * but no contractual relationship express or implied with the contractor furnishing said payment bond, shall have a right of action upon the payment bond upon giving written notice to *308 the contractor within ninety (90) days from the date of which such person did, or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed.”

The appellant supplied electrical material and equipment to the subcontractor during the period of February to August, 1968, in the total amount of $12,066.97. Of that sum, $8,915.00 has been paid to the appellant leaving an unpaid balance of $3,112.29. On September 26, 1968, the appellant mailed the following letter by certified mail to the contractor setting forth the then unpaid balance of $7,066.97.

“Allen C. Minnix & Sons Company
3903 14th Street, N.W. Washington, D. C.
Sub: Sherwood Olney High School Olney, Maryland
H. B. Johnson, Jr.
Electrical Contractor
Gentlemen:
On June 5, 1968, we notified you via certified mail that the above contractor had an unpaid balance of $8,835.34, which covers material supplied by us to the subject job.
On July 2, 1968, we received your Check #38496 in the amount of $5,000.00 which was made out jointly. We have credited the account of H. B. Johnson, Jr. in the amount of $5,000.00.
Since June 1, 1968, we have furnished additional materials to the subject job and wish to advise that we now carry an unpaid balance of $7,066.97; as of 8/21/68. A breakdown of this amount is attached for your information.
*309 Thank you for your prompt attention to this matter.
Very truly yours,
WESTINGHOUSE ELECTRIC SUPPLY COMPANY
F. T. Corcoran
Assistant Credit Manager
FTC/sp
Enel.
cc: H. B. Johnson, Jr.”

The appellant rests its case on the sufficiency of the above letter as proper notice under the Statute. The lower court, however, in a well reasoned, albeit, erroneous opinion, found the notice wanting. The court below structured its opinion on what is thought to be the interpretation given to the notice provisions of the Miller Act, 40 U.S.C. 270 b(a), similar to the Maryland Statute, by the Federal courts. In recent years this Court has on occasion looked for guidance to the Federal courts’ decisions construing provisions of the Miller Act which are parallel to the Maryland Statute. See Ruberoid Co. v. Glassman Construction Co., 248 Md. 97, 106, 234 A. 2d 875 (1967); Montgomery County v. Glassman, 245 Md. 192, 202, 225 A. 2d 448 (1967); Baltimore County v. Knott, 234 Md. 417, 424, 199 A. 2d 369 (1964); Hamilton v. Board of Education, 233 Md. 196, 200, 195 A. 2d 710 (1963).

However, clearly we are not bound to follow the Federal decisions and at least in the instant case we do not find the majority opinion in United States v. Baehner, 326 F. 2d 556 (2nd Cir. 1964), relied on by the lower court, persuasive. Furthermore, were we to agree with the interpretation given the notice requirement in Baehner, we think that a holding that the letter in the instant case constituted valid notice within the meaning of the Statute, would not be inconsistent with the rationale of Baehner.

In Baehner, the supplier mailed a letter to the con *310 tractor in which it informed the contractor of the subcontractor’s delinquency in payment for materials. The Court in determining whether there was a sufficiency of notice within the meaning of the Miller Act, found that there was not, stating through Judge Medina:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CTI/DC, Inc. v. Selective Insurance Co. of America
271 F. Supp. 2d 758 (D. Maryland, 2003)
Mayor of Baltimore v. Fidelity & Deposit Co.
386 A.2d 749 (Court of Appeals of Maryland, 1978)
Menish v. Polinger Company
356 A.2d 233 (Court of Appeals of Maryland, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
269 A.2d 580, 259 Md. 305, 1970 Md. LEXIS 809, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westinghouse-electric-corp-v-minnix-md-1970.