City of Charles City v. Rasmussen

232 N.W. 137, 210 Iowa 841
CourtSupreme Court of Iowa
DecidedApril 2, 1929
DocketNo. 39378.
StatusPublished
Cited by20 cases

This text of 232 N.W. 137 (City of Charles City v. Rasmussen) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Charles City v. Rasmussen, 232 N.W. 137, 210 Iowa 841 (iowa 1929).

Opinion

Albert, J.

In the year 1920, street improvements, consisting of curbing, guttering, and pavement on certain streets in the said city were constructed by the defendant Rasmussen. The work was done under five separate and distinct contracts, each covering work on certain designated streets. The work and improvements were all accepted by the city in the latter part of the year 1920. The contracts for the work are substantially the same in all cases, and the bonds given therewith are also substantially the same. Further reference will be made to both later in the opinion. . .

At various times during the succeeding years, notices were given to Rasmussen of defects in the improvements, and he repaired the same. Other defects arose later, and he refused to carry out the terms of his contract as to repairs. The city had some repairs made after Rasmussen’s refusal to perform, and notified him of other'defects which needed repair.

I. One of the errors claimed as a 'basis for reversal is the alleged prejudicial partisanship of the trial judge. While the court was rather generous in his remarks during the trial of the case, a careful study of the record satisfies us that there was no prejudicial error in his attitude or the conduct of-the trial.

II. Complaint is made that in the instructions the court referred to the “Rasmussen contract.” Reference was intended thereby to be directed to a contract with Rasmussen and some outside parties to do repair work. If there was any error in this instruction, it was in favor of the defendants, and they cannot complain of this reference to the so-called “Rasmussen contract.”

III. Under one of the contracts involved in this case, the *843 pavement was laid on certain streets which, at the time of the bringing of this action, were claimed to be in need of repair. No repair work had been done on the streets covered by this latter contract, but the jury was allowed to find damages in favor of the city for the cost of repair of said streets, and this damage was fixed at something over $1,400. It is now urged that the city was not entitled to recover for the repair work necessary on these streets, because it had not repaired the same or made any effort to do so, and therefore the action was premature, in so far as this item of damage is concerned.

The question, reduced to its last analysis, is: "Was it a condition precedent for the maintenance of such an action that the city must, in the first instance, repair, and thus measure its damages by the cost of such repair? Both sides have discussed this question without citation of authority.

In the case of National Sur. Co. v. City of Huntsville, 192 Ala. 82 (68 So. 373), the Alabama court had before it this identical question. The question there involved was the liability of the sureties on a paving contractor’s bond, for a breach thereof for a failure to repair certain paving in the streets of the city of Huntsville. The question there raised, as here, was that the city had not made the repairs, and that, until it did so repair, an action could not be maintained; or, in other words, that the actual repairing must be done by the city, as a condition precedent to maintaining the action. It was there held that the doing of the repair by the city was not a “condition precedent” to the maintenance of the action for damages on the bond.

In Wills v. Peace Creek Drainage Dist., 4 Fed. (2d Ser.) 519, the Circuit Court of Appeals for the Fifth Circuit had before it a contractor’s bond, where the contractor had abandoned the work, and suit was instituted for damages for breach of the contract. The court said:

“We are of the opinion that the plaintiff was not bound, as a condition precedent to recovery by it on the bond, to complete the work which the contractors had agreed to do. The contract secured to the plaintiff the right to have the drainage work done at an agreed cost. The contractors, by abandoning their eon- *844 tract, damaged the plaintiff in the amount represented by the reasonable cost of completing the work, over and above the cost stipulated in the contract. * * * That plaintiff’s right to recover is not dependent upon completion of the work which the contractors obligated themselves to do, is well settled. All-American Oil & Gas Co. v. Connellee, 3 Fed. (2d Ser.) 107; * * * Simons v. Wittmann, 113 Mo. App. 357 (88 S. W. 791); King v. Nichols & Shepard Co., 53 Minn. 453 (55 N. W. 604); * * * 3 Williston on Contracts (1920 Ed.), Section 1363; 2 Sedgwick on Damages (9th Ed.), Section 643; 3 Sutherland on Damages (4th Ed.), Section 699.”

In the case of Board of Education v. Maryland Cas. Co., 27 Fed. (2d Ser.) 20, the Casualty Company gave a bond assuring the performance of Burke Bros. Company, who engaged to erect a building of a certain kind at a named cost for the plaintiff. The court there said:

“Breach of the contract faithfully to perform was likewise a breach of the bond, and on that breach the rights of the plaintiff municipal corporation and the liability of the defendant surety company became fixed. United States v. U. S. Fidelity Company, 236 U.S. 512, 524, 35 S. Ct. 298, 59 L. Ed. 696. Failing, because of the breach, to obtain the building contracted for, the plaintiff next had a right to damages. * * * As the contractor failed to perform, its surety may be called upon at once to pay the damages, without waiting for the completion of the building by the owner or another party. Indeed, the building may never be .completed; for, unless otherwise provided by the contract, and the owner is not required to complete the work abandoned by the contractor as a condition precedent to recovery on a bond of assurance * * * [citing, among other cases, Cincinnati & S. R. Co. v. Incorporated Village of Carthage, 36 Ohio St. 631], yet the surety will be liable for damages occasioned by the breach.”

In 3 Sutherland on Damages (4th Ed.) 2600, it is said:

“It is immaterial to the right to recover according to the rule stated, that the defects complained of have not been remedied.”

This pronouncement is made on the strength of Logansport, *845 C. & S. W. R. Co. v. Wray, 52 Ind. 578; Eckstrand v. Barth, 41 Wash. 321.

In King v. Nichols & Shepard Co., 53 Minn. 453 (55 N. W. 604), there was a breach of a contract to pnt machinery in good repair and condition, and allegations as to what it would cost to put it in good repair and condition. The court said:

"Upon such a contract as this, — to wit, to put the machine in good repair and condition, — it was not necessary that, in order to recover, plaintiff should himself put it in that condition! As soon as defendant failed to do what it agreed to do, plaintiff might recover the reasonably necessary cost of doing it. ’ ’

In Newton v. Consolidated Const. Co., 184 Mich. 63 (150 N. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Marshall v. American General Insurance Co.
623 S.W.2d 445 (Court of Appeals of Texas, 1981)
Lake View Trust & Savings Bank v. Filmore Construction Co.
393 N.E.2d 714 (Appellate Court of Illinois, 1979)
Mayor of Baltimore v. Fidelity & Deposit Co.
386 A.2d 749 (Court of Appeals of Maryland, 1978)
State Surety Co. v. Lensing
249 N.W.2d 608 (Supreme Court of Iowa, 1977)
Westinghouse Electric Corp. v. Minnix
269 A.2d 580 (Court of Appeals of Maryland, 1970)
Powers Regulator Co. v. Seaboard Surety Co. of New York
204 Cal. App. 2d 338 (California Court of Appeal, 1962)
Town of Troy v. AMERICAN FIDELTY COMPANY
143 A.2d 469 (Supreme Court of Vermont, 1958)
MacDonald v. Standard Accident Insurance
111 A.2d 347 (Connecticut Superior Court, 1955)
Commercial Standard Ins. Co. v. West
249 P.2d 830 (Arizona Supreme Court, 1952)
Narveson v. Schmid
46 N.W.2d 288 (North Dakota Supreme Court, 1951)
State Ex Rel. Switzer v. Overturff
33 N.W.2d 405 (Supreme Court of Iowa, 1948)
Nueces County v. Fletcher & Co.
181 S.W.2d 970 (Court of Appeals of Texas, 1944)
Community Savings Bank v. Western Surety Co.
8 N.W.2d 427 (Supreme Court of Iowa, 1943)
Jaeger Manufacturing Co. v. Massachusetts Bonding & Insurance
294 N.W. 268 (Supreme Court of Iowa, 1940)
Strong v. Incorporated Town of Beaver
1937 OK 416 (Supreme Court of Oklahoma, 1937)
Sioux City v. Western Asphalt Paving Corp.
271 N.W. 624 (Supreme Court of Iowa, 1936)
County of Los Angeles v. Margulis
44 P.2d 608 (California Court of Appeal, 1935)
Kimbrell v. Heffner
161 S.E. 175 (Supreme Court of South Carolina, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
232 N.W. 137, 210 Iowa 841, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-charles-city-v-rasmussen-iowa-1929.