Simons v. Wittmann

88 S.W. 791, 113 Mo. App. 357, 1905 Mo. App. LEXIS 221
CourtMissouri Court of Appeals
DecidedJune 1, 1905
StatusPublished
Cited by17 cases

This text of 88 S.W. 791 (Simons v. Wittmann) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simons v. Wittmann, 88 S.W. 791, 113 Mo. App. 357, 1905 Mo. App. LEXIS 221 (Mo. Ct. App. 1905).

Opinion

NORTONI, J.

(after stating the facts). — It is argued by appellant and we are cited to Lloyd on Building (2 Ed.), sec. 68, where the learned author says: “Where a breach consists in a failure to erect a building as agreed, the measure is the additional value which would have accrued to the land.” We have taken pains to examine closely all of the cases cited by the author in support of the text above stated and find that many of those cases were controversies between a landowner and a railroad company arising by virtue of an obligation on the part of a railroad to maintain a depot on or at the plaintiff’s premises. In some of those cases, plaintiff had conveyed to the railroad a right of way and depot grounds in consideration of its erecting and maintaining a depot thereat and in others, the railroad had sold plaintiff grounds for hotel purposes, agreeing to maintain a depot adjacent thereto-. Upon these facts, the courts hold the covenant as running with the land, and upon suits for a breach of the covenant in failing to maintain, or in removing the depots provided for, have universally held that inasmuch as the maintaining of such depots in connection with the railroad would necessarily enhance the value of the lands, and that this was an element in contemplation of the parties when the contract was made, that the true measure of damages in such case would be the difference in value of the land with the depot standing as provided by the contract and with the depot removed therefrom; or in other words, as plaintiff had parted with the right- of way and depot grounds in consideration that a depot was- to be established, which would enhance the value of their remaining lands, that the measure of their recovery should be such increased value occasioned by the location of the depot thereupon. [Mobile, etc., Ry. Co. v. Gilmer, 85 Ala. 422; Louisville, etc., Ry. Co. v. Sumner, 106 Ind. 55; Watterson v. Ry Co., 74 Pa. 208; Houston, etc., Ry. Co. v. Molloy, 64 Tex. 607.] No case can be found by us in the books where, for a breach of a builder’s con[364]*364tract, as in this case, it was held that the measure of recovery was the difference in the value of the real estate with and without the contemplated building, and we have been unable to find a Missouri case where the suit was for a total failure to perform a building contract. There are numerous well-considered authorities, however, from other jurisdictions which are in point and have materially aided us in arriving at our conclusions.

We cannot agree with appellant’s contention that the measure of damages in this case is the difference between the value of the land without the .buildings and the value thereof with the buildings erected thereon in accordance with the contract. If this were the measure of damages, it might be that one owning land would contract for the erection of a building much desired by the owner yet of such a character as not to enhance the value of the land and, in fact, depreciate the market value thereof. Upon a breach, the contractor could confess his fault, defend against and defeat a recovery upon the ground that the value of the real estate would not be enhanced by the erection of the buildings. Therefore, it has been well said that: “A man may do what he will with his own, having due reg’ard to the rights of others, and if he chooses to erect a monument to his caprice or folly on his premises, and employs and pays another to do it, it does not lie with the defendant who has been so employed and paid for building it to say that his own performance would not be beneficial to plaintiff.” [Chamberlain v. Parker, 45 N. Y. 569; 3 Sutherland on Dam. (3 Ed.), 697.]

The case of Real Estate Co. v. MacDonald, 140 Mo. 605, much relied upon by appellant in this behalf, is not in point here. In that case defendant had purchased from plaintiff certain grounds partially on credit, giving a deed of trust thereon and a certain bond for $35,000, which bond obligated defendants to erect buildings of the value of $35,000 thereon. One of the conditions of the sale on the partial credit extended was that [365]*365the defendant should build ten buildings on said ground at a cost of $35,000 before a given time, which, of course, would render the security for the debt secured by the deed of trust much more valuable. The defendant made default and failed to erect the buildings as required by his bond. In a snit by plaintiff on said bond, the Supreme Court held that the bond stood as a security for the difference between the land without and the land with the buildings upon it; that it was necessary for plaintiff to show the value of the land without the buildings and the value of the land with the buildings in order to arrive at the true measure of recovery. The decision was certainly a correct exposition of the law of that case.

It is to be observed that the court passed upon that case, being properly guided by the matters within the contemplation of the parties at the time the bond was executed, that is, the enhancing of the value of the security for the deferred payments of the purchase price which was secured by the deed of trust mentioned, and that case is unlike the case at bar. This measure, applied to the case in decision here, would be violative of that general rule and fundamental principle of the law of damages, resting upon the idea of compensation for the wrong done which seeks to compensate for the thing contracted for. [8 Am. & Eng. Ency. Law (2 Ed.), 635; The Pittsburg Coal Co. v. Shaeffer, 59 Pa. St. 365; Amer. Surety Co. v. Woods, 105 Fed. 741; 3 Sutherland on Dam. (3 Ed.), 697.]

We find that when a'contractor, as in this case, has, first, wholly failed to perform any part of his contract; or second, when he has partially completed and abandoned the building; or third, when he has substantially completed the building, not in accordance with the contract, the same being insufficient and defective in workmanship, skill or material furnished, when measured by the requirements of the contract, and there being no waiver on the part of the employer, that in either of [366]*366'Such, cases, the owner or employer had the right to erect the building which had been untouched by the defaulting contractor in the first instance or continue to completion the partially completed and unfinished building in the second instance, or.complete and make good the substantially completed building in the third instance, according to the requirements of the contract, and upon his having erected.such untouched building, or completed such partially completed and unfinished building, or made good such substantially and defectively completed building, he is entitled to recover against the defaulting contractor on account of such breach.

(a) The true measure of which recovery in the first instance, if the contractor has been paid in advance for the building, is the value of the building when completed in accordance with the contract.

(b) If he has not been paid in advance for such building, the measure of recovery is the. difference in the price at which the contractor agreed to erect the building and the reasonable cost to or the reasonable expenditure of the owner or employer in erecting the building in accordance with the contract requirements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sheppard v. East
192 S.W.3d 518 (Missouri Court of Appeals, 2006)
Dunning v. Alfred H. Mayer Company
483 S.W.2d 423 (Missouri Court of Appeals, 1972)
Edmonds v. Stratton
457 S.W.2d 228 (Missouri Court of Appeals, 1970)
Samuels v. Illinois Fire Insurance Company
354 S.W.2d 352 (Missouri Court of Appeals, 1962)
Hotchner v. Liebowits
341 S.W.2d 319 (Missouri Court of Appeals, 1960)
Prudence Co. v. Fidelity & Deposit Co. of Maryland
7 F. Supp. 392 (S.D. New York, 1934)
Guardian Trust Co. v. Brothers
59 S.W.2d 343 (Court of Appeals of Texas, 1933)
Noonan v. Independence Indemnity Co.
41 S.W.2d 162 (Supreme Court of Missouri, 1931)
City of Charles City v. Rasmussen
232 N.W. 137 (Supreme Court of Iowa, 1929)
In re Carrier
21 F.2d 589 (D. Massachusetts, 1927)
King v. Farmers Grain Co.
194 Iowa 979 (Supreme Court of Iowa, 1922)
Maryland Casualty Co. v. Town of Wellston
1915 OK 121 (Supreme Court of Oklahoma, 1915)
Taylor v. Massachusetts Bonding & Insurance
142 S.W. 1096 (Missouri Court of Appeals, 1911)
Connor v. Paul
119 S.W. 1006 (Missouri Court of Appeals, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
88 S.W. 791, 113 Mo. App. 357, 1905 Mo. App. LEXIS 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simons-v-wittmann-moctapp-1905.