Prudence Co. v. Fidelity & Deposit Co. of Maryland

7 F. Supp. 392, 1934 U.S. Dist. LEXIS 1623
CourtDistrict Court, S.D. New York
DecidedJune 6, 1934
StatusPublished
Cited by3 cases

This text of 7 F. Supp. 392 (Prudence Co. v. Fidelity & Deposit Co. of Maryland) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prudence Co. v. Fidelity & Deposit Co. of Maryland, 7 F. Supp. 392, 1934 U.S. Dist. LEXIS 1623 (S.D.N.Y. 1934).

Opinion

GALS TON, District Judge.

By stipulation this cause was tried by a jury of one.

On September 24, 1929, the plaintiff and the Central Park Properties, Inc., entered into a building loan agreement, by the provisions of which the Prudence Company agreed to lend the sum of $6,650,009. This loan was to be secured by a bond and mortgage as a first lien upon premises on the south side of West Fifty-Ninth street in the city of New York.

The borrower 'agreed to erect, according to the plans and specifications submitted and approved in writing by the Prudence Company, a modern forty-story and basement fireproof hotel containing 1,269 rooms and 687 bathrooms, together with the usual equipment installed in buildings of that type, but not including hotel furniture and furnishings. This building will - hereafter be referred to as “The Essex House.”

It was agreed that the building was to be completed and ready for oeeupaney by December 16, 1939.

The building loan agreement contained the following clause: “The Borrower shall furnish to the Lender a surety bond in the amount of $3,000,909., in a company satisfactory to Lender, to be in form and contents satisfactory to Lender, conditioned upon and guaranteeing completion of said building within the time hereinafter specified in strict accordance with said plans and specifications and this agreement and free from elaims of liens.”

In pursuance of the foregoing provision of the building loan agreement, the borrower procured for the plaintiff the bond of the defendants herein in the amount of $3,000,000, conditioned upon and guaranteeing the completion of the building described in the building loan agreement not later than the 16th day of December, 1930, in strict accordance with the plans and specifications of the building loan agreement and free from elaims of liens.

The surety bond contained, among others, the following provisions:

“And said building loan agreement and all and singular the terms thereof are hereby made a part of this bond by reference thereto with the same force and effect as if set forth in full in the body hereof.”
“No changes from said plans and specifications above referred to, including any changes in the design or cubic contents of or the materials or equipment in said building or in the performance of the work of eon-structión of said building, and no delay, neg-' lect or failure of the Obligee to proceed promptly or otherwise to enforce the eomplettion of said building by the Principal or enforce any remedy it may have against the Principal, 'and no act done or omission of or action o-r proceeding taken by the Obligee in case of any default by the Principal, shall in any respect release or relieve the Principal or Surety from their obligations hereunder (which shall also include all such changes.)”

At or about the time of the execution of the building loan, advance payments totaling $3,250,009 were made to the borrower. From then on various other advances were made, bringing the total to $6,650-,000, of which the sum of $75,009 was deposited by the Central Park Properties, Inc., with the Prudence Company for the purpose of meeting various expenditures in connection with the completion of the building; and the said sum of $75,909 was thereafter applied by the plaintiff on account of tne said principal sum of $6,659,009,

The plaintiff’s cause of action arises out of the failure of the borrower to complete the building and have it ready for oeeupaney,as a modern hotel on or before December 16, 1930.

On December 23, 1930, the Central Park Properties, Inc., abandoned the completion of the building, leaving it in an unfinished state. The- plaintiff also alleges that the Central Park Properties, Inc., did not construct and complete the building in accordance with the plans and specifications of the building loan contract; and the defendants, it is alleged, have not made good the defaults on the part of the Central Park Properties, Inc. In consequence, the plaintiff employed contractors to complete the building in general accordance with the plans and specifications of the building loan agreement, and it was made ready for oeeupaney on or about the 1st day of October, 1931.

The plaintiff alleges that it has expended certain sums for labor and materials in com[394]*394pleting the building; and that also by reason of the omissions of labor and material called for by the building loan agreement and the plans and specifications, and, because of substitutions made by the Central Park Properties, Inc., of inferior materials, plaintiff was additionally damaged, in that it was compelled to pay taxes, and suffered loss of interest, making total damages of $830',086.69; which sum includes interest to May 15,1934.

The defendants interposed a general denial and also set up ten separate defenses, of which, however, the first, second, third, fourth, fifth, seventh, eighth, and ninth were stricken out on plaintiff’s motion before trial. Prudence Co. v. Fidelity & Deposit Co. of Maryland et al. (D. C.) 2 F. Supp. 454.

The sixth defense alleges that on the 5th day of December, 1930, the plaintiff and the Central Park Properties, Inc., agreed that all the work required for the completion of the building provided for in the building loan agreement had been done except work which could be completed for the sum of $75,000; and that by the deposit of that sum the liability of the defendants on their bond was released and discharged.

The tenth defense is that the omissions of items and the substitution of materials, of which the plaintiff complains, were made with the knowledge and approval of the plaintiff; and that accordingly the plaintiff waived strict performance of the terms and provisions of the building loan agreement, and the plaintiff is estopped thereby from alleging that these omissions and substitutions were contrary to the plans and specifications and to the said building loan agreement.

At the opening of the ease, the defendants’ counsel asserted a defense of fraud. This defense was not proved.

Exhibit 84 sets forth a list of payments made by the Prudence Company in completing the building. The reasonableness of some of these items is challenged. It includes a painting expenditure of $72,882. It is claimed that this is an excessive amount; and that at the time of final payment by the Prudence Company, the painting was separated from the other items, and it was estimated that $25,000 would cover the cost of completion of the painting. Defendants also emphasize the fact that the plaintiff’s inspectors reported that $14,000 would be sufficient to complete the painting. As against that, however, we have the testimony that what was done was; in strict compliance with the provisions of the building loan agreement and the plans and specifications, with the exception that there was included a removal of molding and repair ting necessitated by such removal. Howe’s er, the net figure of $71,650' is arrived at affair having made suitable deduction for such labor and material as were not called for by the' plans and specifications. It nowhere appears that either Schermerhom or Billsbor-row, plaintiff’s inspectors, submitted detailed estimates in respect to the job, at the time that it was estimated that but $14,000 would be required to complete the painting. It is argued that this and other items were reckless expenditures because the total amount so expended was so vastly in excess of early estimates.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake View Trust & Savings Bank v. Filmore Construction Co.
393 N.E.2d 714 (Appellate Court of Illinois, 1979)
In re Prudence Co.
21 F. Supp. 316 (E.D. New York, 1937)
Prudence Co. v. Fidelity & Deposit Co. of Md.
297 U.S. 198 (Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
7 F. Supp. 392, 1934 U.S. Dist. LEXIS 1623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prudence-co-v-fidelity-deposit-co-of-maryland-nysd-1934.