Hart v. . City of New York

94 N.E. 219, 201 N.Y. 45, 1911 N.Y. LEXIS 1213
CourtNew York Court of Appeals
DecidedFebruary 7, 1911
StatusPublished
Cited by13 cases

This text of 94 N.E. 219 (Hart v. . City of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hart v. . City of New York, 94 N.E. 219, 201 N.Y. 45, 1911 N.Y. LEXIS 1213 (N.Y. 1911).

Opinion

Hiscock, J.

This action was brought to recover a balance alleged to be due to the appellant under a contract for the construction of a sewer and of a sewage disposal plant in the borough of Queens, and also several thousand dollars for extra labor and material which he alleges he was compelled to do and furnish in order to carry out and perform the terms of said contract, by reason of the wrongful acts, neglect, fault and omissions of the defendant, by changes of plans and in various other ways, and under the orders and directions of the defendant.” These last items of work and material are claimed to be “ in excess of that covered by the terms of the contract and necessary for the efficiency of the work required to be *49 done and in order to properly perform the same, all of which was done as directed by the defendant.”

In alleged competition with four others plaintiff bid upon and thereafter entered into a contract for the construction of the sewer and sewage disposal plant under discussion for the sum of $181,850, and of which amount the sum of $90,000 was to cover the disposal plant. As I understand it, the amounts were bid separately for the respective pieces of work. It is alleged, and in the case of the sewer is undisputed, that the plaintiff completed the sewer and disposal plant and thereafter received certificates from the proper officials of defendant to the effect that he had earned under the terms of his contract the sum of $191,550.59, and that he has received only the sum of $160,902.90. Outside of the items for extra services and materials above referred to and hereafter to be discussed by themselves, there seems to have been no dispute between the parties under the contract relating to the sewer, but the controversy arises concerning the sewage disposal plant, and it is assumed that if the plaintiff is not entitled to collect under the contract for work done and materials furnished in erecting the latter he has been paid all that he is entitled to for the construction of the sewer, and on that branch of the case would be entitled to no further recovery.

Two substantial reasons are urged why he is not entitled to collect under his contract for construction of the disposal plant. These are:

First, that the contract for the erection of said plant was illegal and void because the proposals for bids did not, sufficiently specify the work to be done and materials to be furnished so as to afford a basis for competitive bidding and thus comply with the provisions of defendant’s charter.

Second, that plaintiff did not so perform his contract, assuming it to be valid, as to entitle him to collect compensation.

I shall consider these two questions in the order stated.

Plaintiff entered into a contract for the construction of both sewer and the disposal plant. So far as his rights to compensation for the latter are concerned, I do not see that it makes *50 any difference whether the contract be treated as one entire one or as composed of two divisible and, separate parts. In either case, if the provisions relative to the construction of the disposal plant are illegal and invalid, plaintiff cannot recover for that whatever may be the case with reference to some of the items for extra work herein to be discussed.

The first instrument or notice issued in behalf of the defendant after it was determined to do the work in question was directed “ To contractors ” and headed “ Proposals for sewer,” and it commences as follows: Sewer in Broadway. * * * in the Borough of Queens, also the erection of a Disposal Plant in connection with the same. * * * Sealed bids or estimates for the above work * * * will be received at the office of the Department of Sewers * * * and the award of the contract, if awarded, will be made to the lowest bidder.”

This paper then further states: “ The following is a state-' ment based upon estimates of the Engineer, of the quantity and quality, and the nature and extent, as near as possible, of the work required ; and the several bids will be tested by the quantities and qualities mentioned in such statement.” Then follow several items relating to the sewer, which need not be quoted, and these are followed by the concluding item : “ One . Sewage Disposal Plant complete in every detail, as per accompanying specifications and those given in the proposal, including the operation of the Sewage Disposal Plant for M. H. W. (six) months, and the tests connected therewith.”

This proposal was followed by or contained what is entitled “ Data relating to the Disposal Plant to be Constructed in Connection with the Sewer in Broadway * * * in the Borough of Queens.” These data are the only specifications given by the municipal authorities of the work to be done and materials to be furnished in the construction of this plant. I do not Understand that there is any dispute that if they do not furnish the basis for the necessary competitive bids, considering the nature of the work to be done, which are required by the charter, then this branch of the contract is’ invalid.

*51 These so-called data are so extended that it is out of the question to quote from them in detail. I think, however, that they may be fairly summarized in the statement that the only substantial definite specifications which they contain for the proposed plant are as follows: The plant was to be erected on a given piece of land ; the building containing tanks, etc., was to be built of brick; there were to be a certain number of square yards of surface of filter beds, if used, for each one thousand gallons of sewage to be treated per day; the capacity of the plant was to be one million gallons of sewage in twenty-four hours and it was to be so subdivided as to be “ capable of treating fifty thousand (50,000) gallons of sewage in twenty-four (24) hours * * * independent of the rest of the plant” excepting boilers, etc.; the composition of the effluent discharged into the creek which was to be utilized in the operation of the plant was fixed. Outside of these specifications which were definite, the invited bidder was allowed in effect to select any method of sewage disposal, and construct, locate and arrange buildings, appurtenances, such as tanks for sedimentation, filtering pipes and valves, foundations, engines, boilers, etc., according to any system he desired and according to plans and specifications to be submitted by him with his bid.

It is apparent from this general statement how indefinite was the description of the work to be done, and how j>ractically impossible it was for bidders to compete with one another on a common basis of work to be done and materials furnished, and how open to the discretion and judgment of the municipal officers it was to determine which was the lowest bid. As stated, the question is whether the proposal and the specifications weie sufficiently definite to comply with the provisions of law and to make a bid and a contract entered into in response thereto legal. I do not think that they were.

Section 401 of the Greater New York charter, in force at the time, provided that “ Power and authority to construct and erect and maintain sewage disposal works and plants and *52

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L&M Bus Corp. v. New York City Department of Education
71 A.D.3d 127 (Appellate Division of the Supreme Court of New York, 2009)
Alderman v. Central New York Arterial Markets, Inc.
24 A.D.2d 1046 (Appellate Division of the Supreme Court of New York, 1965)
Webb v. Hillsborough County
175 So. 874 (Supreme Court of Florida, 1935)
Prudence Co. v. Fidelity & Deposit Co. of Maryland
7 F. Supp. 392 (S.D. New York, 1934)
Brooklyn Ash Removal Co. v. O'Brien
238 A.D. 647 (Appellate Division of the Supreme Court of New York, 1933)
Matter of McNutt Co. v. Eckert
177 N.E. 386 (New York Court of Appeals, 1931)
Matter of Shaddock v. Schwartz
158 N.E. 872 (New York Court of Appeals, 1927)
Yonkers Railroad v. City of Yonkers
218 A.D. 97 (Appellate Division of the Supreme Court of New York, 1926)
Yonkers Railroad v. City of Yonkers
128 Misc. 108 (New York Supreme Court, 1926)
City of New York v. Davis
7 F.2d 566 (Second Circuit, 1925)
Wade v. City of Tacoma
230 P. 99 (Washington Supreme Court, 1924)
Wadsworth v. . Bd. of Supervisors
112 N.E. 161 (New York Court of Appeals, 1916)
Miller v. Jackson Township
99 N.E. 102 (Indiana Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
94 N.E. 219, 201 N.Y. 45, 1911 N.Y. LEXIS 1213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hart-v-city-of-new-york-ny-1911.