Snyder v. City of New York

74 A.D. 421, 77 N.Y.S. 637
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 15, 1902
StatusPublished
Cited by9 cases

This text of 74 A.D. 421 (Snyder v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snyder v. City of New York, 74 A.D. 421, 77 N.Y.S. 637 (N.Y. Ct. App. 1902).

Opinion

Hatch, J.:

It is claimed by the appellant, as a first ground upon which to defeat a recovery in this action, that by the provisions of the contract there could be no assignment of the same without the previous written consent of the commissioner of public works, or his successor, indorsed thereon, and as such consent was never given no cause of action vested in the plaintiff as against the defendant. In Fortunato v. Patten (147 N. Y. 277) it was held that such a provision of the contract was for the protection of the city and to secure for it the skíII and intelligence of the person with whom the city contracted. It was recognized in that case, however, that there [426]*426was a wide distinction between the assignment of a contract and the assignment of moneys falling due. thereunder after performance. For the purpose of disposition of this question, we assume that there was a breach of the contract upon the part of the city, and, if so, the contractor became entitled to have and receive the sums of money which had been earned thereunder and for such damages as might have been occasioned by the breach. An assignment, therefore, of these claims would not be an assignment of the contract but of a cause of action against the city for the recovery of moneys which it was obligated to pay, and in this view of the question there would be no violation of that clause of the contract which prohibited its assignment without the consent of the commissioner of public works. The clause in question is a restriction solely upon the assignment of the contract as such and not of the moneys earned thereunder which the city is bound to pay. (Mellen v. Hamilton Fire Ins. Co., 17 N. Y. 609 ; Brichta v. N. Y. Lafayette Ins. Co., 2 N. Y. Super. Ct. 372.) Such an assignment is not an assignment of the contract. (Brace v. City of Gloversville, 167 N. Y. 452.) If, therefore, the evidence authorized a finding that the city has been guilty of a breach of the contract, and that there was money due and payable according to its terms, the plaintiff in this action acquired title thereto and was authorized to maintain this action for its recovery. It also appeared that the assignment was not made until the work had been completed by another contractor, so that at the time when this assignment was made there was no contract ' in existence to assign; consequently, the city could not be deprived of the services of the particular contractor in the performance of the contract, nor could it be vexed by being compelled to deal' with other parties with whom it had entered into no contractual relation. There was nothing, therefore, in existence which could be assigned at the time when this assignment was made, except the claim which was held by the contractor against the city, predicated upon its breach of the contract.

By the terms of the contract it is insisted that the commissioner of public works was justified in declaring the contract abandoned. Upon this subject the contract provides that the commissioner may at any time, if lie shall be of opinion and shall so certify in writing that the work, or any part thereof, is unnecessarily or unreasonably [427]*427delayed, or the contract is being willfully violated, or for other cause of bad faith on the part of the contractor, direct the contractor to discontinue all work by written notice to that effect, and thereupon the contractor is required to discontinue. Under that clause of the contract relating to payments by which thirty per cent is authorized to be retained, the payment of the seventy per cent is to be based upon the determination of the commissioner of public works, as he shall deem advisable. It is evident that this authority,. which is vested in the commissioner of public works, both as to performance of the contract and payment thereunder, is not to be exercised arbitrarily at the mere will of the commissioner. There must exist some basis therefor, and the commissioner must fairly exercise his judgment and discretion thereon, and, in the absence of any ground, the commissioner would not be justified in directing the contractor to cease performance of the contract or withhold the payment of the seventy per cent when the contractor was clearly entitled thereto by the terms of the contract. It is evident that if the contract had been performed by the contractor so as to entitle him to the payment under the ninth certificate, then it became the duty of the commissioner of public works to authorize a payment, and if there was a breach upon the part of the city by refusing payment of the ninth certificate, and also in withholding the delivery of the tenth, then the commissioner of public works was not justified in declaring the contract abandoned. Such declaration was of a time considerably subsequent to the date when the contractor became entitled to these payments, and if he should have received them at that time the city could not, through the commissioner of public works, by subsequent declaration, declare the contract canceled, nor could the contractor be placed in default by any such declaration, if he had been guilty of no breach himself, To permit the city so to do would authorize it to take advantage of its own wrong. (Graf v. Cunningham, 109 N. Y. 369 ; Wright v. Reusens, 133 id. 298.)

The contract was comparatively large, took a considerable time for its completion, and necessarily involved a large expenditure of money in performing the work. It is necessarily to be presumed, therefore, that the seventy per cent payment was necessary from time to time as the work progressed, to enable the contractor to receive sufficient money therefrom to properly carry on the work. [428]*428The payment of this sum, therefore, was evidently necessary and ■essential to enable the contractor to properly perform the contract. It is evident that in these' respects, as well as in all others, good faith and fair dealing were required at the hands of both contracting parties. The question, therefore, comes ultimately to rest upon the question as to whether the contractor became entitled to payment under the ninth certificate. By the terms of the Contract his right was to be' evidenced by the certificate of the surveyor appointed by the city, subject thereafter to the proper scrutiny of the commissioner of public works. In the absence of fraud or mistake the certificate thus given was binding and conclusive upon both parties and entitled' the contractor to payment according to its terms. (Sweet v. Morrison, 216 N. Y. 19; Wyckoff v. Meyers, 44 id. 143 ; Smith v. Mayor, 12 App. Div. 391; New York Building Co. v. Springfield El. Co., 56 id. 294.)

It is undisputed that the surveyor, acting for the city, gave to the contractor the certificate contemplated thereby under and by virtue Of which the contractor became entitled to have and receive, as a seventy per cent payment, the sum of $1,980. To this certificate the commissioner of public works made no objection. On the contrary, after consultation with the comptroller, the commissioner of public works examined the work, and recommended to the comp-’ troller that the certificate be paid'as certified and returned the samé to the comptroller for payment. So far as the terms of the written contract are concerned, there is nothing therein which authorized the comptroller either to suspend the work under the contract or refuse payment when properly certified by the surveyor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allhusen v. Caristo Construction Corp.
278 A.D. 817 (Appellate Division of the Supreme Court of New York, 1951)
Bandes v. Triborough Bridge Authority
165 Misc. 698 (City of New York Municipal Court, 1936)
Sacks v. Neptune Meter Co.
144 Misc. 70 (Appellate Terms of the Supreme Court of New York, 1932)
Sperry & Hutchinson Co. v. Siegel, Cooper & Co.
225 Ill. App. 540 (Appellate Court of Illinois, 1922)
Atlantic City v. Warren Bros.
226 F. 372 (Third Circuit, 1915)
City of New York v. Third Nat. Bank
221 F. 175 (Second Circuit, 1915)
Hart v. . City of New York
94 N.E. 219 (New York Court of Appeals, 1911)
Kinzer Construction Co. v. State
125 N.Y.S. 46 (New York State Court of Claims, 1910)
Price v. City of New York
104 A.D. 198 (Appellate Division of the Supreme Court of New York, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
74 A.D. 421, 77 N.Y.S. 637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snyder-v-city-of-new-york-nyappdiv-1902.