Price v. City of New York

104 A.D. 198
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 15, 1905
StatusPublished
Cited by4 cases

This text of 104 A.D. 198 (Price v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Price v. City of New York, 104 A.D. 198 (N.Y. Ct. App. 1905).

Opinion

Bartlett, Woodward, Jenks, Rich and Miller, JJ., concurred.

The following is the opinion of Hon. William J. Carr, Referee:

Carr, Referee:

In December, 1901, the parties to this action entered into a written contract providing for the delivery by the plaintiff to the defendant of coal in an approximately estimated quantity of 17,900 tons, to be delivered at various specified pumping stations of the defendant from time to time, throughout the year 1902. For the coal so delivered the defendant agreed to pay at the rate of three dollars and eighty-seven cents a ton. Clause J of the contract and paragraph 2 of the specifications, forming a part of the contract, provided that the delivery of coal should be “ as directed by the Commissioner,” and the plaintiff should “ carry on such contract with such force and in such manner and order, and at such times and seasons' as may from time to time be directed by the Engineer, it being understood that the rate of delivery as outlined in this contract is only approximate, and may be varied by the Engineer as he may deem necessary,” etc.

Clause O of the contract provided in terms partly as follows: That in order to enable the Contractor to prosecute the work advantageously, the Engineer shall, from time to time, as the work progresses, but not oftener than once a month, make an estimate of the amount of coal delivered under this contract since the last preceding estimate was made and of the value thereof, according to the [200]*200terms of this contract. Upon such estimate being' made ninety per cent'of such estimated value shall be paid to the Contractor.” This clause.contained likewise a provision as to the. certificate to be made by the engineer on complete performance of the contractor. The ' plaintiff entered upon the delivery of coal in January or February, 1902, and "the engineer' on February 28, 1902, gave an estimate and certificate as "to the amount and value of coal delivered and "ninety per cent of such value was paid to the plaintiff. A like estimate and certificate was given and a like payment made for coal ' delivered in March, April and May of the same year, less ten per cent retained payments. ^ .

Under this scheme of payment, the sum of $462.22 was retained ' under the February estimate; the sum of $379.'52 under the March estimate; the sum of. $547.28 under-the April estimate, and the sum of $630.72 under the May estimate. On June thirtieth the engineer made an estimate and certificate showing deliveries in June of coal at the contract price-of $3,284.12, andmn July thirtieth ■ a like estimate and certificate was made showing a delivery in July of coal at the contract price of $4,127.15. This was followed by a like estimate for August in the sum of $3,239.90;

The amount estimated for June was not paid in the whole or in part until August thirtieth, when ninety per cent was paid on account. The amount estimated for July and August has n’ot been paid at .all. On August twenty-eighth the plaintiff notified the defendant in writing that she claimed a breach of contract on the part of the defendant ip failing to make payments on the June and July estimates, and that, becausé of "said alleged breach, she elected to terminate the contract and would sue for the ten per cent retained on the previous payments and the value of the coal delivered in June, July and August. .This action has been brought accordingly, the plaintiff. making an "allowance, against her claim, of the ninety per cent part payment-on August 3,1902, made on account of the June estimate. She asks judgmen t,f or the sum of $9,679.20, with interest-from-August 31, 1902. I am of opinion that the foregoing facts, -alleged -in the complaint and established- by the evidence, con- " st-itute-at least a. prima facie cause of action for the plaintiff.

If the plaintiff was entitled to payment on the .June and July estimates ..the delay and refusal on the 'part of the defendant con[201]*201stituted such a breach of performance by the defendant as entitled her to terminate the contract and recover, for her past performance as evidencéd by the estimates and certificates of the engineers. (Snyder v. City of New York, 74 App. Div. 428 ; Thomas v. Stewart, 132 N. Y. 580; Graf v. Cunningham, 109 id. 369; Wharton & Co. v. Winch, 140 id. 287.)

The defendant claims, however, that the plaintiff was not entitled to any payment on account of the June, July or August estimates, because of alleged anterior breaches of performance on her account. There is no allegation in the answer that the estimates of the engineer were fraudulent and collusive. No claim is made that coal certified as delivered was not actually delivered, or that there was any mistake as to quantity or value in the estimates and certificates. Such being the ease, the estimates and certificates maybe said to be conclusive on the parties. (Brady v. Mayor, etc., of New York, 132 N. Y. 416 ; Matter of Freel, 148 id. 168 ; Snyder v. City of New York, 74 App. Div. 428 ; O'Keeffe v. City of New York, 173 N. Y. 478.)

The answer sets up affirmatively a specific breach on the part of the plaintiff upon which it bases a counterclaim for $13,964.19, with interest. x

Assuming that the defendant is not bound on this point by the certificates and estimates of its engineers, it is not apparent that it has established any facts upon which the counterclaim is allowable^ A general claim is made of breaches by the plaintiff anterior to the estimates of June, July and August, but no satisfactory evidence thereof has been offered except as to an alleged breach subsequent to July 16, 1902. At Iqast substantial performance prior to that time is indisputable upon the evidence, and no claim of damage or material injury to the defendant has been proved or asserted as to anything occurring or omitted prior to July sixteenth. The specifications forming a part of the contract provide in part as follows : “ That,in case of failure on the part of the Contractor to deliver coal at the proper wharf, railroad station or switch in the quantities ordered and at the rate herein specified within fourteen (14) days (Sundays and holidays excluded) after the date of written notice mailed to him by the Engineer directing him that shipments of coal are desired, then and in that case the Commissioner shall have the [202]*202right to purchase such quantity of coal in the open market as may tie required, and to deduct, from any estimate that may be -due.'the Contractor the- additional co^t of the said coal delivered at the rail- ' road station, switch or pumping station Where it maybe required, o'ver and above the prices stipulated in ¡the contract for coal at the said station.” ' , .

On July sixteenth-a letter from" the engineer, dated July 16, 1902, addressed to “Mr. E. Y. Price, 13-21 Park Row,‘N. Y.,”was deposited in the Brooklyn post office as a “ registered letter.” This . letter required ¡the delivery of specified quantities of coal at specific pumping stations, and gave notice* that in case of. non-delivery within, fourteen days of its-daté the engineer would certify the fact to tlie commissioner in order that coal might be purchased in open" market on tlie. plaintiff’s account, under the .provisions of the certifi- ' cate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford v. Regal Shoe Store No. 162, Inc.
20 Misc. 2d 1055 (City of New York Municipal Court, 1959)
Fields v. Western Millers Mutual Fire Insurance
182 Misc. 895 (New York Supreme Court, 1944)
Saffold v. Fellows
128 Misc. 422 (New York Surrogate's Court, 1926)
Freund v. A. Shapiro & Son
4 F.2d 383 (Third Circuit, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
104 A.D. 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/price-v-city-of-new-york-nyappdiv-1905.