Thomas v. Stewart

4 Silv. Ct. App. 139, 43 N.Y. St. Rep. 881
CourtNew York Court of Appeals
DecidedMarch 22, 1892
StatusPublished

This text of 4 Silv. Ct. App. 139 (Thomas v. Stewart) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas v. Stewart, 4 Silv. Ct. App. 139, 43 N.Y. St. Rep. 881 (N.Y. 1892).

Opinion

Vann, J.

—If the second instalment was due when the demand of payment was made by the contractors, they could lawfully decline to go on with the contract, because the owner had refused performance on his part. Graf v. Cunningham, 109 N. Y. 369 ; Schwartz v. Saunders, 46 Ill. 18. If the second instalment was not then due, the contractors were in default, and the lienors, who claim under them, are entitled to a recovery only to the extent conceded by the owner, or to the difference between the amount unpaid at the date of such default and the sum required to complete the contract. Van Clief v. Van Vechten, 130 N. Y. 571; 42 St. Rep. 736 ; Malbon v. Birney, 11 Wis. 108.

By the terms of the agreement the second payment was to become due when the floors were laid, “ partitions set and ready for mason.” The owner claims that the contractors failed in performance, to the extent, necessary to entitle [142]*142them to the second payment, by omitting several things required by the plans and specifications. The lienors claim that the features omitted were waived by the architect, prevented hy the owner or not required to be done as a condition precedent to the second -payment, and evidence was given in support of the claim, but the court made no specific finding upon the subject. The use of cottonwood in certain window frames, required to be made of pine, was not denied, but one of the contractors testified that on hearing that the architect objected, he went to see him and said that cottonwood could be used as well as pine; that they were merely skeletons, and were covered over with pine casings on the outside and inside. After hearing this explanation the architect said: “ You may use those frames, but bring no more cottonwood on the job. The witness further testified that no cottonwood was used after that, except that some balusters were turned for use on the rear piazza, but they were no part of the work required to be done prior to the second payment. According to the evidence of another witness no cottonwood whatever was brought on the premises after the architect objected. The architect testified that he allowed certain window frames made of cottonwood to be put in, provided the contractors would use no more cottonwood in the building, but he claimed that after that more window frames of the same kind were put in against his protest. When, however, he was asked to certify that the second payment was due, he did not mention this as an objection, but based his refusal upon other grounds.

There was other testimony tending to corroborate the theory of either side upon the question of consent to the change, which thus became a question of fact • for the trial court to determine, and it will be presumed, in support of the finding that the second payment was due, that the court found in favor of the lienors upon this issue. Ostrander v. Hart, 130 N. Y. 406; Thomson v. Bank of British North America, 82 N. Y. 1; Burnap v. Nat. Bank of [143]*143Potsdam, 96 Id. 125. But the appellant insists that the architect had no right to substitute an inferior article without the consent of the owner, and the authorities support that position. Glacius v. Black, 50 N. Y. 145; Bigler v. The Mayor, 9 Hun, 253.

The court, however, found upon. evidence that is not printed in. the case, but which it is expressly stipulated proved the fact, “ that said Sahagian employed the said George Rayner as his architect and servant to superintend the work of erecting said house and the doing of the work thereof, and the said Rayner did so superintend such work and the erecting of such house.” The contract provided that all work was to be done to the satisfaction of the architect, and the owner told one of the contractors that everything was left with the architect. Inasmuch as Mr. Rayner was not only the architect, but was also the agent of the owner and represented him in the erection of the building, we think that he had authority to consent to the substitution complained of. The fact that the change was made without the knowledge or consent of the owner, as found by the court, evidently means, when the context is considered, without his personal knowledge or consent.

It is further insisted that injustice was done the owner because the contractors failed to put two locust posts in the cellar beneath the girders, as required by the specifications.^ The. object of those posts were to support the girders, which in turn support the partitions that were to be set and ready for the mason before the second instalment became payable. While there was nothing in the specifications to indicate when the posts were to be put in, as the object in putting them in was to support the partitions, it is reasonable to conclude that it was contemplated by the parties that they were to be placed in position before the partitions were built. The contractors, however, were only to do the carpenter work. They had nothing to do with the mason work, which the owner was to do himself. Evidence was [144]*144given tending to show that the locust posts could not be put in because the cellar was not sufficiently excavated to permit it, and the stone foundations upon which they were to rest were not built, all of which was mason work. The contractors, therefore, put in temporary posts so that they could go on with their work, and, according to the evidence, this was the only practicable course. The architect did not include the omission to put in permanent posts among his reasons for declining to give a certificate. We do not think that the owner can take advantage of his own omission, nor justly complain because work was not done, when the failure to do it was owing to himself. Smith v. Norris, 120 Mass. 58; Welch v. Sherer, 93 Ill. 64; Charnley v. Honig, 74 Wis. 163.

The specifications required the contractors “ to make and set in partition back of each water closet a four by ten inch ventilator.” The trial judge found that these were not put in, but he refused to find that the partitions were not properly set and ready for the mason on that account. The specifications do not provide when the ventilators were to be put in, nor whether they were to be behind lath and plaster, or behind wood. They were not a part of the partition, but were to be “ set in ” it, presumptively after the partition was erected. Some witnesses testified that if •they were put in and plastered over, the plaster, having no “ clinch,” would not adhere thoroughly, and that the proper way was to put them behind wood, so that they would be accessible for repairs and other purposes, without tearing away the lath and plaster. Evidence was also given, without objection, to the effect that they should be put in after the masons had done their work of plastering the partitions. Other witnesses testified that they should be lathed and plastered over, so that they could not be seen, and that this was the usual way. The architect was of this opinion, but he gave no such direction to the contractors, and did not say so when he refused the certificate, nor allude to the ven[145]*145tilators in any way. TMs conflict in the evidence justified the finding of the trial court in favor of the lienors upon this subject and its refusal to find as requested by the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ostrander v. . Hart
29 N.E. 744 (New York Court of Appeals, 1892)
Thomas v. . Fleury
26 N.Y. 26 (New York Court of Appeals, 1862)
Graf v. . Cunningham
16 N.E. 551 (New York Court of Appeals, 1888)
Van Clief v. . Van Vechten
29 N.E. 1017 (New York Court of Appeals, 1892)
Thomson v. . Bank of British North America
82 N.Y. 1 (New York Court of Appeals, 1880)
Glacius v. . Black
50 N.Y. 145 (New York Court of Appeals, 1872)
Smith v. Norris
120 Mass. 58 (Massachusetts Supreme Judicial Court, 1876)
Schwartz v. Saunders
46 Ill. 18 (Illinois Supreme Court, 1867)
Welch v. Sherer
93 Ill. 64 (Illinois Supreme Court, 1879)
Charnley v. Honig
42 N.W. 220 (Wisconsin Supreme Court, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
4 Silv. Ct. App. 139, 43 N.Y. St. Rep. 881, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-v-stewart-ny-1892.