Bandes v. Triborough Bridge Authority

165 Misc. 698, 1 N.Y.S.2d 921, 1936 N.Y. Misc. LEXIS 865
CourtCity of New York Municipal Court
DecidedDecember 28, 1936
StatusPublished

This text of 165 Misc. 698 (Bandes v. Triborough Bridge Authority) is published on Counsel Stack Legal Research, covering City of New York Municipal Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bandes v. Triborough Bridge Authority, 165 Misc. 698, 1 N.Y.S.2d 921, 1936 N.Y. Misc. LEXIS 865 (N.Y. Super. Ct. 1936).

Opinion

Ryan, J.

Plaintiff sues as an assignee of moneys due under a public improvement contract, and trial was had before the court without a jury. The contract in question was known as No. 44, and was entered into by Triborough Bridge Authority on the one part and Max Hochman as the contractor on the other part, on April 8, 1935, for the demolition of additional buildings to the Manhattan approach of the Triborough Bridge. Remaining unpaid on the contract is a balance of $3,760, now in the possession of the comptroller of the city of New York. The assignment in question provided, among other things, that the contractor assigned to the plaintiff the sum of $2,000 out of payments now due or hereafter to become due to him from the Triborough Bridge Authority under and by virtue of said contract, and is dated October 25, 1935, and was filed in the comptroller’s office on November 4, 1935.

The defendant Zucker Water & Sewer Service Corp. in its answer interposes counterclaims, and demands judgment against the Triborough Bridge Authority in the sum of $1,169.14 by virtue of an instrument dated November 12, 1935, and filed in the comptroller’s office on November 21, 1935, addressed to the Triborough Bridge Authority and the finance department, New York city, requesting and requiring that out of the moneys due and to grow due under said contract that “ you pay unto Zucker Water & Sewer Service Corporation ” the sum of $1,169.14, and charge such payment against the moneys due or to grow due and owing to the contractor under said contract. Hochman, the contractor, testified he received from the plaintiff the sum of $2,000 on the execution of said assignment and used same in the work, labor and material for the completion of said contract; he further testified that the last day he worked on the job was October 26, 1935.

A concession was made by the corporation counsel, representing the Triborough Bridge Authority, that the testimony of Hochman as to the time of the completion of the job given with respect to plaintiff’s claim would be the same in reference to the claim of Zucker.

[700]*700Joseph Zucker, secretary of the Zucker Corporation, testified concerning a verbal agreement had with the contractor to do certain work consisting of disconnecting water and sewer lines from the buildings to be demolished, which work was done between April 29 and September 19,1935. Thus defendant asserts the claim for $1,169.14 on the ground that it performed the work for the contractor and received an order for the payment of that much of the contract moneys.

Item 22 of the contract in question, entitled “ Assignments and Sub-Contracts,” provides: “ Inasmuch as this Contract is made in reliance upon the Contractor’s personal qualifications and responsibility, and inasmuch as the payments to be made hereunder are intended to finance in part the Contractor’s performance, the Contractor shall not assign or otherwise transfer this contract or any part hereof, or any moneys due or to become due hereunder, without first obtaining the consent of the Resident Project Engineer and then without the express consent in writing of the Authority; provided, however, that the Contractor may sub-contract work to be performed hereunder to such persons as the Chief Engineer, subject to the approval of the Resident Project Engineer, may from time to time approve in writing.

“ No consent to any assignment or other transfer, and no approval of any sub-contractor shall under any circumstances operate to relieve the Contractor of any of his obligations under this contract; no Contract and no approval of any sub-contractor shall create or be deemed to create any rights in favor of such sub-contractor and against the Authority; and for all purposes hereunder, all assignees, sub-contractors, and other transferees shall be deemed to be the agents of the Contractor. Moreover, all sub-contracts and all approvals of sub-contractors, regardless of their form, shall be deemed to be conditioned upon performance by the sub-contractor in accordance with this contract; and if any sub-contractor shall fail to perform his Work to the satisfaction of the Engineer, the Chief Engineer shall have the absolute right to rescind his approval forthwith and to require the performance of such work by the Contractor personally, and /or through other approved subcontractors.

“ Nothing herein contained shall be construed to hinder, prevent or affect an assignment of any moneys due or to become due hereunder, made for the benefit of the Contractor’s creditors pursuant to law.”

Item 12 of the contract in question, entitled^ Time for Completion,” provides:

[701]*701“ The Contractor shall begin work within five (5) days after mailing of notice by the Chief Engineer so to do or if notice is delivered by messenger, within five (5) days after said delivery and shall complete all Work within 120 CONSECUTIVE CALENDAR DAYS from the date of said notice.

“ The Chief Engineer shall be the sole judge as to whether the Work hereunder has been completed within the time stipulated.”

Exhibit 5, introduced in evidence by the plaintiff, is a communication addressed to Col. Paul Loeser, director, and signed by Edward W. Stearns, acting chief engineer for the Triborough Bridge Authority, is dated January 3, 1936, and provides, among other things, as follows: “ The contract (No. 44) provides that the work should be completed within 120 consecutive calendar days from the date of notice to the Contractor to begin work. Such notice was given on April 19, 1935. The date for completion was, therefore, August 17, 1935. The contract was actually completed on November 15, 1935. * * * On July 30, 1935, the Contractor requested an extension of time to September 1, 1935, claiming that his delay was caused by the failure of the Authority to have all the parcels available for demolition. * * * In my opinion the Contractor suffered a delay of approximately three weeks because of the nonavailability of the parcels mentioned at the beginning of the work and the Contractor is, therefore, entitled to an extension of time to about September 7, 1935. The Work was practically completed prior to that date, the exceptions consisting of certain demolition below ground level, repairs to sidewalks and miscellaneous cleaning up which was finally completed November 15, 1935.”

In introducing that exhibit (5) the plaintiff became bound by its terms. (Jonasson v. Weir, 130 App. Div. 528; Curry v. American Railway Express Co., 214 id. 744.)

The date of the completion of the work is thus fixed as of November 15, 1935.

Plaintiff argues that it is wholly immaterial to her right of recovery whether the work under said contract was completed by the contractor on October 25, 1935, or on November 15, 1935.

The contract under consideration specifically prohibited the assignment or other transfer of the contract or any part thereof or any moneys due or to become due thereunder without the consent of the engineer and of the authority. That such consent was refused was not denied. That the contractor fully performed the contract is not denied; nor is the fact that the sum of $3,760 is still due as the balance thereon, which amount is in the possession of the comptroller.

[702]*702In the case of Episcopo v. Mayor of New York (35 Misc. 623) the assignment involved that of the contract itself, the previous consent to assign which had not been obtained.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arkansas Valley Smelting Co. v. Belden Mining Co.
127 U.S. 379 (Supreme Court, 1888)
State Bank v. Central Mercantile Bank
162 N.E. 475 (New York Court of Appeals, 1928)
Fortunato v. . Patten
41 N.E. 572 (New York Court of Appeals, 1895)
Snyder v. City of New York
74 A.D. 421 (Appellate Division of the Supreme Court of New York, 1902)
Jonasson v. Weir
130 A.D. 528 (Appellate Division of the Supreme Court of New York, 1909)
Episcopo v. Mayor of New York
35 Misc. 623 (New York Supreme Court, 1901)
Sacks v. Neptune Meter Co.
144 Misc. 70 (Appellate Terms of the Supreme Court of New York, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
165 Misc. 698, 1 N.Y.S.2d 921, 1936 N.Y. Misc. LEXIS 865, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bandes-v-triborough-bridge-authority-nynyccityct-1936.