Board of Education v. Maryland Casualty Co. of Baltimore

27 F.2d 20, 1928 U.S. App. LEXIS 3318
CourtCourt of Appeals for the Third Circuit
DecidedJune 21, 1928
DocketNo. 3767
StatusPublished
Cited by7 cases

This text of 27 F.2d 20 (Board of Education v. Maryland Casualty Co. of Baltimore) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Education v. Maryland Casualty Co. of Baltimore, 27 F.2d 20, 1928 U.S. App. LEXIS 3318 (3d Cir. 1928).

Opinion

WOOLLEY, Circuit Judge.

The judgment which is brought here for review by this writ of error is perhaps the last step in protracted litigation which the Board of Education of the City of Asbury Park began by an action against the Maryland Casualty Company, surety on a building contract, to recover for the contractor’s default. The main facts were stated in the opinion of this court when it disposed of another phase of the controversy. Maryland Casualty Company v. Board of Education (C. C. A.) 20 F.(2d) 799.

A jury was waived and the ease tried to the judge. As his findings on questions of fact are conclusive (though of course open to inquiry as to whether there was evidence that sustains them, Ward v. Joslin, 186 U. S. 142, 147, 22 S. Ct. 807, 46 L. Ed. 1093), we shall confine our review to questions of law of which the thirty assignments of error, when compressed, raise three.

The first question concerns the measure of damages. This turns on another, namely, whether the measure is that prescribed by general law or by the terms of the contract itself.

We first look to general law applicable to the facts of the case which, on this point, are these: Burke Brothers Construction Company entered into a contract with- the plaintiff municipal corporation for the erection of a school building and gave bond for performance with the defendant as surety. Burke Brothers Company defaulted rather promptly. The plaintiff took possession and after advertising for bids let the completion of the work to the MeClary Corporation under a contract in terms identical with that of Burke Brothers Company except at an increased cost of about $30,000. Looking upon this difference in cost as its main damage the plaintiff brought this suit against the surety on the first contract before the building had been completed under the second, asserting the difference in cost between the two contracts as the proper measure of damages. The defendant, however, regarding the suit as prematurely brought, maintained at the trial, and still maintains, that the proper measure of damages is the difference between the price of construction under the Burke Brothers’ contract and the actual cost of the building when completed under the MeClary contract. Whether the building has in fact been completed is a subsidiary question between the plaintiff and the second contractor, still open and having a bearing on the matter under discussion only in the event the defendant should prevail on the law.

Burke Brothers Company engaged to erect for the plaintiff a building of a certain kind at a named cost. By that contract, the duty of the company to erect and the right of the plaintiff to obtain a building of that kind at that cost became fixed. The bond which the defendant gave to assure performance was tied to the contract and its condition was as broad as its terms. Breach of the contract faithfully to perform was likewise a breach of the bond and on that breach the rights of the plaintiff municipal corporation and the liability of the defendant surety company became fixed. United States v. U. S. Fidelity Company, 236 U. S. 512, 524, 35 S. Ct. 298, 59 L. Ed. 696. Failing, because of the breach, to obtain the building contracted for, the plaintiff next had a right to damages. When and in what amount? Clearly the plaintiff was entitled to the damages it had sustained at the time of the breach. Such being its right, when could the plaintiff assert it by suit? That depends^ on the character of the defendant’s bond. If it is a bond of indemnity, suit of course must await the completion of the building, for until then no one can determine its cost and the consequent loss in order to determine the amount of indemnity. But the bond in suit is not one of indemnity. National Surety Co. v. City of Huntsville, 192 Ala. 82, 68 So. 373. It is a bond to assure performance of a contract or else respond in damages. As the contractor failed to perform, its surety may be called upon at once to pay the damages without waiting for the completion of the budding by the owner or another party. Indeed the building may never be completed, for, unless otherwise provided by the contract, the owner is not required to complete [22]*22the work abandoned by the contractor as a condition precedent to recovery on a bond of assurance, Wills v. Peace Creek Drainage District (C. C. A.) 4 F.(2d) 519; National Surety Co. v. City of Huntsville, 192 Ala. 82, 68 So. 373; Newton v. Consolidated Constr. Co., 184 Mich. 63, 150 N. W. 348; King v. Nichols, 53 Minn. 453, 55 N. W. 604; Simons v. Wittmann, 113 Mo. App. 357, 88 S. W. 791; Cinn. Ry. v. Carthage, 36 Ohio St. 631, yet the surety will be liable for damages occasioned, by the breach.

In what amount? That depends on the plaintiff’s ability to prove damages — a matter of proofs. If the owner does not go on with the building, either by himself or through another, proof of what its completion would reasonably cost has been accepted as a factor in estimating damages. But where after breach a contract for completion has been let on terms identical with those of the first contract except as to price, as in this case, eourts have pronounced that the measure of damages is the difference between the defaulter’s price and the price of the subsequent letting. City of Goldsboro v. Moffett (C. C.) 49 F. 213, 216; Schuyler County v. Missouri Bridge & Iron Co., 173 Ill. App, 435, Id., 256 Ill. 348, 100 N. E. 239. This rule is applied in such eases because ,of the positive proof of damages made available by the cost price named in the second contract into which the owner had been forced to enter by the breach of the first contract, and this proof of damages being at hand may at once be used in a suit to recover.

Against this rule of measure of damages the defendant cites and earnestly relies on the decision in American Surety Company v. Woods (C. C. A.) 105 F. 741, which on its face is seemingly opposed to the rule, yet the court which rendered that decision later distinguished it in Wills v. Peace Creek Drainage District, supra, by pointing out (first holding to the general rule that the right of an owner to sue for breach of a building contract is not dependent on his completing the abandoned work) that the contract in that ease contained a provision that on default by the contractor the owner should complete the work and that as a matter oi fact the work had been abandoned by both parties.

Finding that the true measure of damages is the difference between the defaulter’s price and- the cost price of re-letting when the contract contains no provision which requires the owner to complete the work upon breach by the contractor, the rule applies in this ease if the contract contains no such provision. But the defendant says, and on this it mainly rests its case, that the' contract does contain just such a provision. Its relevant parts are as follows:

“Should the contractor * * * fail to comply with the terms of the contract, the owner * * * may and shall have the right and power to enter upon and taire possession of the premises and all materials thereon, and * * * to employ workmen by day’s work or otherwise, and to provide materials sufficient to finish the work, * * *. The finishing of the various works will be deducted from the amount of- the contract, or from any payments due or to be due said contractor. In such an event the payments herein agreed upon shall not he due until the entire work shall be completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake View Trust & Savings Bank v. Filmore Construction Co.
393 N.E.2d 714 (Appellate Court of Illinois, 1979)
Continental Casualty Co. v. United States
113 F.2d 284 (Fifth Circuit, 1940)
United States v. Continental Casualty Co.
29 F. Supp. 598 (E.D. Louisiana, 1939)
City of Reading v. United States Fidelity & Guaranty Co.
19 F. Supp. 350 (E.D. Pennsylvania, 1937)
Prudence Co. v. Fidelity & Deposit Co. of Maryland
77 F.2d 834 (Second Circuit, 1935)
Prudence Co. v. Fidelity & Deposit Co. of Maryland
7 F. Supp. 392 (S.D. New York, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
27 F.2d 20, 1928 U.S. App. LEXIS 3318, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-education-v-maryland-casualty-co-of-baltimore-ca3-1928.