Prudence Co. v. Fidelity & Deposit Co. of Maryland

77 F.2d 834, 1935 U.S. App. LEXIS 4724
CourtCourt of Appeals for the Second Circuit
DecidedJune 10, 1935
DocketNo. 293
StatusPublished
Cited by6 cases

This text of 77 F.2d 834 (Prudence Co. v. Fidelity & Deposit Co. of Maryland) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prudence Co. v. Fidelity & Deposit Co. of Maryland, 77 F.2d 834, 1935 U.S. App. LEXIS 4724 (2d Cir. 1935).

Opinion

MANTON, Circuit Judge.

The judgment appealed from was entered upon a directed verdict after a trial by a jury of one, pursuant to a stipulation of the parties. The action is upon a surety bond guaranteeing to appellee, holder of a first mortgage lien, the completion of the apartment hotel, Essex House, in New York City. Central Park Properties, Inc., the mortgagor, was the principal on the bond given by the appellants.

Central Park Properties Inc., had contracted for a building loan with the appellee, of $6,650,000; the building to be erected as provided by certain plans and specifications. Half the amount of the loan was advanced at the time of the closing of the loan, and the balance as the work progressed. Completion of the building was fixed for December 16, 1930.

Appellants’ guaranty was for the completion of the building, not for the payment of the loan. On December 5, 1930, a certificate of occupancy having been granted theretofore, the appellee made the final payment under the building loan of $300,000, but by agreement retained $75,000, which amount was then thought sufficient to complete the building. December 16, 1930, the principal of the mortgage was due, and the principal defaulted; all interest had been paid. December 18, 1930, appellee commenced foreclosure proceedings; January 19, 1931, judgment of foreclosure was entered. On the sale, March 17, 1931, appellee became the buyer for $6,000,000; August 30, 1931, a deficiency judgment was entered against the principal. Claiming that the building was not completed on December 16, 1930, the appellee has recovered a judgment based on the claim that it has suffered damages because of such in-completion.

The owner furnished a surety bond of $3,000,000, wherein appellants guaranteed the construction and completion of the building by the principal in accordance with the building loan agreement and the approved plans and specifications, by the 16th of December, 1930. They promised to make good any and all defaults of the principal. Appellee sued for breach, claiming a default in the obligation to complete the building, and, as damages, claimed (1) items necessarily spent to complete the building; (2) items of omission and substitution by the principal whereby the value of the building had been lessened; and (3) that by reason of the failure to complete the building it was deprived of interest on the principal of the loan from December 16, 1930, to October 1, 1931, together with taxes and insurance paid during part of that period.

Before final payment was made, December 5, 1930, the appellee’s employees inspected the building thoroughly, and its own report showed that there was only $42,350 worth of work unfinished; a later report of December 16, 1930, fixed the amount at $23,500. When the final payment was made, the amount of work remaining to be done was disputed, but the principal and the appellee agreed upon the retention of $75,000 by the appellee for completion. The $75,000, however, was used by the appellee to reduce the mortgage principal, as was permissible under the terms of the agreement. It was not until February 14, 1931, that claims of in-completion were presented to appellants, by the appellee, in anything near the presently claimed sums. In April, 1931, the listed items of incompletion amounted to $254,177.29, and submitted items of omissions and substitutions amounting to $125,-495.34.

As a complete defense, the appellants argue that when, on December 5, 1930, the owner and the appellee agreed upon the final payment of the building loan, and the appellee retained $75,000, appellants were discharged. The building loan agreement provided that “the final advance shall not be due and payable until the borrower shall obtain and deliver to the lender the usual certificate of completion issued by the building Department * * A certificate of occupancy was issued October 3, 1930, but this was not a certificate of completion. Thus, the final advance was not due by reason of the issuance of the certificate of occupancy. The principal, however, made claims to the final payment when the certificate of occupancy was granted; the appellee refused, but made some further advances on several occasions, and later did make the final payment as stated. The appellant’s contention is that before this payment a controversy arose between the [836]*836principal and the appellee as to completion, and the consequent fight to final payment; that an agreement withholding some of the principal for completion having been reached, this settled the controversy, and so far as completion of the building is concerned, it took the place of the building loan agreement, and that thereafter any recourse which the appellee might have for failure to complete the building was against the principal pursuant to this compromise agreement, and that by virtue of such agreement, the appellants were discharged. The basis of this contention is that the agreement altered and changed the terms of the instruments by which the appellants were bound. ,

But making an advance of payment did not, by the terms of the building loan agreement, constitute acceptance or approval of the work done. When the final payment was made, there was no release from the obligation to complete and no agreement was made upon any sum for completion. No compromise agreement took the place of the building loan agreement. The intent to substitute a new executory contract for an existing one must be clearly established. City Nat. Bank v. Fuller, 52 F.(2d) 870, 79 A. L. R. 71 (C. C. A. 8). The trial court found that the agreement of December 5, 1930, was in no way an accord and satisfaction. Upon disputed evidence, whether or not the transaction or agreement arrived at was a compromise, novation, or an accord and satisfaction, was a question of fact found against the appellants. Union Indemnity Co. v. United States, 74 F.(2d) 645 (C. C. A. 6).

Moreover, the surety bond provided: “Any waiver or release by the Obligee * * * of any default or omission by the Principal and/or Surety in complying with said building loan agreement or plans and specifications or with the provisions of this bond, must be in writing and signed by the duly authorized officers of the Obligee in order to be binding upon the Obligee and any such waiver or release shall apply only to the item or items specifically so released.” Thus the appellants agreed that appellee would not be affected by releases or waivers unless in writing, and signed by duly authorized officers, specifying the items released. The appellee had a right to rely upon this provision. This defense therefore must fail.

In the opinion below, the court held that the measure of damages which the appellee could recover is the cost of completion according to the plans and specifications. The appellee was entitled to a completed building for security only. The cost of completion may well be considered as the amount and the measure of damages sustained. In Kidd v. McCormick, 83 N. Y. 391, there was an agreement to erect houses on certain lots on which the plaintiff held a bond and mortgage. Plaintiff later agreed to permit subsequent mortgages to have priority over his if the defendants deposited a certain sum of money in a trust company to insure the completion, of the houses, which was done. The houses were not completed. The plaintiff completed them, foreclosed his mortgages, bid in the premises, and entered a deficiency judgment. Plaintiff sued to reach the moneys deposited in trust. The trial court found that the houses in their incompleted state were worth less than if finished as agreed, and a judgment was entered for the difference.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fournigault v. Independence One Mortgage Corp.
242 F.R.D. 486 (N.D. Illinois, 2007)
New Amsterdam Casualty Co. v. Bettes
407 S.W.2d 307 (Court of Appeals of Texas, 1966)
Hammond Ford, Inc. v. Ford Motor Co.
204 F. Supp. 772 (S.D. New York, 1962)
In Re Prudence Co.
96 F.2d 157 (Second Circuit, 1938)
In re Prudence Co.
21 F. Supp. 316 (E.D. New York, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
77 F.2d 834, 1935 U.S. App. LEXIS 4724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prudence-co-v-fidelity-deposit-co-of-maryland-ca2-1935.