Prudence Co. v. Fidelity & Deposit Co. of Md.

297 U.S. 198, 56 S. Ct. 387, 80 L. Ed. 581, 1936 U.S. LEXIS 523
CourtSupreme Court of the United States
DecidedFebruary 3, 1936
Docket270
StatusPublished
Cited by20 cases

This text of 297 U.S. 198 (Prudence Co. v. Fidelity & Deposit Co. of Md.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prudence Co. v. Fidelity & Deposit Co. of Md., 297 U.S. 198, 56 S. Ct. 387, 80 L. Ed. 581, 1936 U.S. LEXIS 523 (1936).

Opinion

*203 Me. Justice Caedozo

delivered the opinion of the Court.

We are to. determine the measure of damages upon a bond conditioned against loss through the failure to complete a building at the time and in the manner called for by the building contract.

*204 In September, 1929, petitioner, the Prudence Company, Inc., undertook to make a mortgage loan of $6,-650,000 in aid of the construction of Essex House, an apartment hotel in the City of New York. The borrower covenanted that the building would conform to plans and specifications, and would be completed not later than December 16, 1930. As part of the same transaction, two surety companies, - the respondents in this court, signed a bond in the sum of $3,000,000, indemnifying the lender against loss through the failure of the borrower to construct' and pay for a building conforming to the contract, and complete it by the stated time. The bond also provided that in the event of the borrower’s default, the lender, if it so elected, should be at liberty to go forward with the work, and charge the cost against the sureties. Other conditions are believed to be immaterial to any-question now before us.

On December 16, 1930, the borrower made default under the mortgage, abandoning the work with the building then unfinished. At that time the petitioner’s advances under the building loan agreement were $6,575,-000, the full amount promised, less $75,000 retained by agreement. On December 18, 1930, petitioner through its nominee brought suit in the state court for the foreclosure of the mortgage. On January 6, 1931, it went into possession with the mortgagor’s consent. On January 19, 1931, there was a judgment of foreclosure, followed by a sale on March 17, 1931, at which the mortgagee was the buyer, the bid of $6,000,000 being applied upon the mortgage.- A-deficiency judgment of $716,215.02 was entered the next month.

Petitioner in' possession of the building went on with the unfinished work, bringing it to completion in October, 1931. An action on the bond was. then begun against the sureties. The trial court gave judgment for damages in the sum of $798,416.81, made up of three classes of items: *205 the cost of completion; the loss from omissions and inferior substitutions; and the interest on investment, together with taxes and insurance charges, while the building was idle because unready for its occupants. 7 F. Supp. 392. The Circuit Court of Appeals for the Second Circuit found this award to be excessive. In the view of that court no award should have been made for interest, taxes or insurance during the period of idleness. Payments necessary to complete the building were properly allowed, for they were evidence of the difference in value between an incomplete and a completed structure. Re-' paration was also to be made for omissions and substitutions to the extent that they diminished value, unless strict compliance had been waived by the lender or its agents. However, the extent of the recovery was not susceptible of ascertainment without the aid of a new trial. This was so because evidence of waiver had been offered by the surety and erroneously excluded. A remand was thus necessary to elicit all the facts. 77 F. (2d) 834. Before a second trial was had, a writ of certiorari issued at the instance of petitioner to resolve a claim of conflict between the decision to be reviewed and a decision of this court. Trainor Co. v. Aetna Casualty & Surety Co., 290 U. S. 47. The writ states that it is “limited to the question of the measure of damages,” thus excluding from our consideration the ruling of the court below as to- the effect of waiver of performance.

Limiting our review accordingly, we think the extent of the recovery upon the new trial that will be necessary has been too narrowly confined.

The petitioner should be placed in the same position it would have occupied if the building had been completed on December 16, 1930. Trainor Co. v. Aetna Casualty & Surety Co., supra, at pp. 54, 55; Kidd v. McCormick, 83 N. Y. 391, 398; Province Securities Corp. v. Maryland Casualty Co., 269 Mass, 75, 94; 168 N. E. 252. To give *206 it nothing but the cost of doing the unfinished work, plus the loss resulting from omissions and substitutions, would be a scant measure of reparation, allowing nothing for delay. Ruff v. Rinaldo, 55 N. Y. 664; C. W. Hunt Co. v. Boston Elevated Ry. Co., 199 Mass. 220, 233, 235; 85 N. E. 446; Sedgwick, Damages, 9th ed., § 645. If performance had been prompt, the mortgagee would have had the security of a finished structure, which a buyer at a foreclosure sale could have utilized at once. During the pendency of the suit, the rents might have been impounded at the hands of a receiver and applied upon the deficiency resulting from the sale. Freedman’s Saving & Trust Co. v. Shepherd, 127 U. S. 494, 503; Worthen Co. v. Kavanaugh, 295 U. S. 56, 62. With the building still unfinished there were no rents to be collected and hence none to be applied in. reduction of the debt. More important still, the amount of any bid was certain to be reduced by notice to the bidders that the building would be unproductive until ready to be occupied. From the point of view of bidders the reduction in value as the consequence of delay would be made up of two factors: the estimated cost of finishing the work, and the estimated carrying charges, not to exceed the rental value, during the period of idleness. Cf. Trainor Co. v. Aetna Casualty & Surety Co., supra, at p. 55; Kidd v. McCormick, supra, at p. 398. So &t least an assessor of the damages might find as a fair inference of fact, even if the finding does not follow as an inference of law. The effect of the decision is to hold down the recovery to the first of these factors and to eliminate the second.

The petitioner might have relied upon the testimony of experts as to the total depreciation and as to the weight of the component factors. It chose a different method. To show the loss sustained from finishing the work, it proved the actual cost, as by the express provisions of the bond it was at liberty to do. Cf. Comey v. *207 United Surety Co., 217 N. Y. 268, 276; 111 N. E. 832; Appleton v. Marx, 191 N. Y. 81, 85, 86; 86 N. E. 563. One of the factors of diminished value it has thus established with precision. To fix the weight of the other factor, it would have done better to give evidence by experts of the rental value of such a building at. the date of the default and later. Griffin v. Colver, 16 N. Y. 489, 496; Cassidy v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Surety Co. v. United States
83 Fed. Cl. 306 (Federal Claims, 2008)
BMY-Combat Systems Division of Harsco Corp. v. United States
38 Cont. Cas. Fed. 76,380 (Court of Claims, 1992)
Mcgrath v. Zenith Radio Corporation
651 F.2d 458 (Seventh Circuit, 1981)
McGrath v. Zenith Radio Corp.
651 F.2d 458 (Seventh Circuit, 1981)
1633 Associates v. Uris Buildings Corp.
66 A.D.2d 237 (Appellate Division of the Supreme Court of New York, 1979)
Glendale Federal Savings & Loan Ass'n v. Marina View Heights Development Co.
66 Cal. App. 3d 101 (California Court of Appeal, 1977)
New Amsterdam Casualty Co. v. Bettes
407 S.W.2d 307 (Court of Appeals of Texas, 1966)
Jh Ellen, Jr. v. King
88 S.E.2d 598 (Supreme Court of South Carolina, 1955)
Zipkin v. Investors Syndicate
152 F.2d 678 (D.C. Circuit, 1945)
Modern Industrial Bank v. United States
101 Ct. Cl. 808 (Court of Claims, 1944)
Gulf States Creosoting Co. v. Loving
120 F.2d 195 (Fourth Circuit, 1941)
In Re Prudence Co.
96 F.2d 157 (Second Circuit, 1938)
In re Prudence Co.
21 F. Supp. 316 (E.D. New York, 1937)
City of Reading v. United States Fidelity & Guaranty Co.
19 F. Supp. 350 (E.D. Pennsylvania, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
297 U.S. 198, 56 S. Ct. 387, 80 L. Ed. 581, 1936 U.S. LEXIS 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prudence-co-v-fidelity-deposit-co-of-md-scotus-1936.