C. W. Hunt Co. v. Boston Elevated Railway Co.

85 N.E. 446, 199 Mass. 220, 1908 Mass. LEXIS 809
CourtMassachusetts Supreme Judicial Court
DecidedJune 9, 1908
StatusPublished
Cited by53 cases

This text of 85 N.E. 446 (C. W. Hunt Co. v. Boston Elevated Railway Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. W. Hunt Co. v. Boston Elevated Railway Co., 85 N.E. 446, 199 Mass. 220, 1908 Mass. LEXIS 809 (Mass. 1908).

Opinion

Loring, J.

1. We are of opinion that the auditor was right in proceeding on the footing that the Hunt Company was entitled to recover if “ the towers did conform to the contract and specifications, as modified by the parties in March, 1903, and that if they were not satisfactory to the vice-president of the railway company they ought to have satisfied a reasonable man.”

This is not a contract “ into which considerations of taste or personal preference may enter,” as was said by Knowlton, C. J., in Noyes v. Eastern Accident Association, 190 Mass. 171, 172. That is to say, it is not a case within McCarren v. McNulty, 7 Gray, 139; Brown v. Foster, 113 Mass. 136; White v. Randall, 153 Mass. 394; Webber v. Cambridgeport Savings Bank, 186 Mass. 314, 315. The case at bar is for work of a business character and comes within Hawkins v. Graham, 149 Mass. 284, if as matter of construction it was to be done to the satisfaction of the defendant and not to that of a third person as arbitrator.

The provision of the contract is: The contractor agrees that all material furnished and work done hereunder shall be subject to acceptance by the railway company and its vice president; that all apparatus furnished and work done shall be subject at all times to the inspection of said vice president or his authorized agents, and that any work performed or material furnished which may be deemed by said vice president to be not in accordance with the terms of this contract and accompanying specifications shall be immediately replaced by the contractor at its own expense.” There are also these provisions in the specifications : “ The work shall be executed under the direction and supervision of the vice-president of the Boston Elevated Railway Company or his authorized representative. . . . The vice-president of the Boston Elevated Railway Company, without relieving the contractor from any responsibility therein, reserves the right to direct the manner and order in which the work shall be executed.”

Had Mr. Sergeant been a third person and not an officer of the defendant corporation, the provisions of the specifications would have been enough to make him a quasi arbitrator within the rule applied in Atkins v. Barnstable, 97 Mass. 428; Palmer v. Clark, 106 Mass. 373; Flint v. Gibson, 106 Mass. 391; [228]*228Robbins v. Clark, 129 Mass. 145; National Contracting Co. v. Commonwealth, 183 Mass. 89; Norcross v. Wyman, 187 Mass. 25.

But Mr. Sergeant represented the railway company in this transaction, and was not a third person. That being so, the provision that the work was to be done “ subject to acceptance by the railway company and its vice president ” would have brought this case within Hawkins v. Graham without a doubt had that been the only provision of the contract on this point. In such a case Mr. Sergeant in accepting or not accepting the work would have acted for and represented the railway company, and would not have been a third person acting as arbitrator.

Although, as we have said, the provisions in the specifications look the other way, we are of opinion on the whole that Mr. Sergeant must he taken to have been the representative of the defendant and not a third person in this matter. This conclusion is enforced by the fact that all the correspondence set forth in the report which took place under the contract was carried on by Mr. Sergeant in behalf of the railway company.

2. The railway company urges that the auditor is wrong in his conclusion from the correspondence set out in the report “that if the changes specified were made, and if they accomplished the results which they might fairly be expected. to accomplish, the railway company would be satisfied with the towers and would accept them.”

This contention of the railway company is based on these words in the closing letter of April 3: “We have no desire whatever to interrupt the work, but we waive none of our rights under the contract to reject any or all of it if it proves unsatisfactory when completed.” This statement is to be taken in connection with what went before.

On February 19,1903, (that is to say, six months after the first tower and five and a half months after the second tower should have been completed and in working order,) Mr. Sergeant wrote to the Hunt Company a letter stating that “ up to this time there is no indication that these towers are likely to prove in any degree adequate or satisfactory,” complaining that the Hunt Company’s men had left the work, and ending with this threat: “ Unless you proceed without further delay to com[229]*229píete your contract we shall be compelled to install an efficient apparatus at your expense.” In answer the president of the Hunt Company wrote a letter of explanation ending with this request: “ If you will kindly point out any feature of the contract which has not been carried out by us, I would be pleased to have you advise me of the same, and it will be given immediate and careful attention, and meanwhile we say, courteously but emphatically, that we deny your right6 to install an efficient apparatus at your (our) expense ’ or any apparatus at our expense, and in the same way we repudiate the suggestion’ contained in your letter, that the machinery is not in accordance with our contract, or in any wise inefficient through any fault of ours.” Thereupon a personal interview took place on March 3, 4 and 5, in which Mr. Sergeant undertook to tell the representative of the Hunt Company “ in what respects the towers failed to meet the requirements of the railway company.” These were embodied in a letter from Mr. Hunt, dated March 17, under six heads, and stated that “ Each of the other points noted in the conference we are now in the process of making such changes in, as we have no doubt will meet your approval.” Another conference took place on March 19 and 20, and the points discussed were embodied in a letter of Mr. Hunt dated March 23, under fourteen heads. In this letter Mr. Hunt states what he proposes to do in respect to each of the fourteen matters. On the 24th Mr. Sergeant discusses each of the fourteen heads and what the Hunt Company proposes as to each, and on the 27th Mr. Hunt answers, dealing with the fourteen items in a similar way. Then follows a correspondence not set out in the report but which is characterized by the auditor as “ some rather lively correspondence ... as to who was now causing delay ” ; and on April 3 this is closed by á letter from Mr. Sergeant in which he states that he is “pleased to note that you now wish to immediately proceed with the completion of the towers in accordance with my letter of the 24th ult. We supposed you would do so immediately on receipt of that letter, nor was there anything in your subsequent letter of the 27th ult. which appeared to be in conflict with the work proposed to be done. We were therefore at a loss to understand your telegram of 1st inst. So.far from holding up the work, we have de[230]*230manded and do demand that you proceed forthwith to complete your contract.” Then follows the paragraph here relied on by the railway company, which we repeat in full: “You mention a desire that we should, in acknowledging your letter, state that the work can proceed to completion without interruption.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rodriguez v. Massachusetts Bay Transportation Authority
33 Mass. L. Rptr. 418 (Massachusetts Superior Court, 2016)
Piemonte v. New Boston Garden Corp.
387 N.E.2d 1145 (Massachusetts Supreme Judicial Court, 1979)
Salem Glass Co. v. Joseph Rugo, Inc.
176 N.E.2d 30 (Massachusetts Supreme Judicial Court, 1961)
P. A. Dolan Co. v. P. S. Thorsen Co.
86 N.E.2d 652 (Massachusetts Supreme Judicial Court, 1949)
Morgan-National Woodworking Co. v. Cline
84 N.E.2d 460 (Massachusetts Supreme Judicial Court, 1949)
Manhattan Clothing Co. v. Goldberg
12 Mass. App. Div. 99 (Mass. Dist. Ct., App. Div., 1947)
Brown v. General Trading Co.
37 N.E.2d 987 (Massachusetts Supreme Judicial Court, 1941)
Assessors of Quincy v. Boston Consolidated Gas Co.
34 N.E.2d 623 (Massachusetts Supreme Judicial Court, 1941)
Kurland v. Massachusetts Amusement Corp.
29 N.E.2d 749 (Massachusetts Supreme Judicial Court, 1940)
Gechijian v. Richmond Insurance
25 N.E.2d 191 (Massachusetts Supreme Judicial Court, 1940)
Pearson v. Fraser
4 Mass. App. Div. 345 (Mass. Dist. Ct., App. Div., 1939)
Ryder v. Town of Lexington
21 N.E.2d 382 (Massachusetts Supreme Judicial Court, 1939)
Sarhanis v. Young
17 N.E.2d 878 (Massachusetts Supreme Judicial Court, 1938)
Prudence Co. v. Fidelity & Deposit Co. of Md.
297 U.S. 198 (Supreme Court, 1936)
Graustein v. H. P. Hood & Sons, Inc.
200 N.E. 14 (Massachusetts Supreme Judicial Court, 1936)
Piper v. Childs
195 N.E. 763 (Massachusetts Supreme Judicial Court, 1935)
Rooney v. Weeks
194 N.E. 666 (Massachusetts Supreme Judicial Court, 1935)
Potier v. A. W. Perry, Inc.
190 N.E. 822 (Massachusetts Supreme Judicial Court, 1934)
Brooklyn Eastern District Terminal v. United States
287 U.S. 170 (Supreme Court, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
85 N.E. 446, 199 Mass. 220, 1908 Mass. LEXIS 809, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-w-hunt-co-v-boston-elevated-railway-co-mass-1908.