United States Surety Co. v. United States

83 Fed. Cl. 306, 2008 U.S. Claims LEXIS 244, 2008 WL 4061064
CourtUnited States Court of Federal Claims
DecidedAugust 28, 2008
DocketNo. 07-638 C
StatusPublished
Cited by17 cases

This text of 83 Fed. Cl. 306 (United States Surety Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Surety Co. v. United States, 83 Fed. Cl. 306, 2008 U.S. Claims LEXIS 244, 2008 WL 4061064 (uscfc 2008).

Opinion

Opinion and Order

BLOCK, Judge.

I. INTRODUCTION

Plaintiffs, United States Surety Company and American Contractors Indemnity Company, are Miller Act1 co-sureties that provided performance and payment bonds for Woodside Construction, Inc. (‘Woodside”) on its dredging contract with defendant, the United States. When Woodside was terminated for default, plaintiffs entered into a formal takeover agreement with the government and performed the remainder of the dredging contract. At issue in this case is whether plaintiffs, having completed the contract pursuant to the takeover agreement, possess a superior right to earned but withheld funds, as compared to the government’s entitlement to liquidated damages from these same funds.

Defendant has moved to dismiss the case for failure to state a claim pursuant to Rules Court of Federal Claims (“RCFC”) 12(b)(6) and, in response, plaintiffs moved for summary judgment under RCFC 56. For the reasons set forth below, this Court does not reach the merits of the defendant’s 12(b)(6) motion, but instead sua sponte grants summary judgment in favor of the government.

II. FACTUAL BACKGROUND2

The following facts for this summary judgment motion are undisputed. On April 22, [308]*3082005, the U.S. Army Corps of Engineers (“Corps”) entered into a dredging contract with Woodside. Compl. ¶ 5; PPFUF ¶ 1; DRPFUF ¶ 1. As required in the contract, Woodside obtained performance and payment bonds in the amount of $1,435,300.00 from plaintiffs. Compl. ¶ 6; PPFUF ¶ 2; DRPFUF ¶ 2.

On December 22, 2005, the government terminated the contract with Woodside for default and called upon plaintiffs to complete performance of the contract pursuant to the obligations of their performance bond. Compl. ¶ 7; PPFUF ¶ 3; DRPFUF ¶ 3. At the time, Woodside had earned, but the government had not paid, $88,879.48 on the contract.3 PPFUF ¶ 7; DRPFUF ¶ 7.

On or about December 30, 2005, the government and plaintiffs entered into a takeover agreement, which provides in part:

2. The Government agrees to pay the Surety in the manner provided by the Contract, the unearned balance of $800,362.80, earned retainage of $8,085.00 and earned but unpaid contract funds of $80,394.48, subject to the following conditions:
A. All unpaid earnings of the Principal, including retained percentages and progress estimates for work accomplished prior to termination, shall be subject to claims by the Government against the Principal arising from the project, except to the extent that such unpaid earnings may be required to permit payment to the Surety of its actual costs and expenses incurred in the performance of or payment for the work called for in the Contract.
C. Except as expressly provided herein, nothing in this Takeover Agreement shall be construed as a waiver or release of any rights of the Government against the Principal or the Surety, including but not limited to liquidated damages for delays in completion of the work, except to the extent that such delays may be excused under the provisions of the Contract.

Compl. Ex. A. at 2.

The government assessed and withheld from plaintiffs $122,800.00 in liquidated damages, $32,000.00 of which it withheld for the period of time prior to the termination of Woodside. Compl. ¶¶ 15-16; PPFUF ¶¶ 8-9; DRPFUF ¶¶ 8-9.

On January 11, 2007, plaintiffs filed a claim with the Contracting Officer (“CO”) for $32,000.00, stating that “the $32,000.00 ... assessed as [liquidated [djamages ... qualifies under the exclusion set forth in Paragraph 2[A] of the Takeover Agreement and should be paid to the Surety.” Compl. Ex. B ¶ 9. The CO denied plaintiffs’ claim in a final decision dated July 18, 2007. Compl. Ex. C. Subsequently, on August 28, 2007, plaintiffs brought suit in this Court seeking relief in the amount of $32,000.00. Compl. 5.

III. SUMMARY OF THE PARTIES’ POSITIONS

The thrust of plaintiffs’ argument is that the government’s claim to liquidated damages was extinguished by the terms of the takeover agreement recited above. Compl. ¶¶ 17-18. In addition, plaintiffs characterize the government’s withholding of liquidated damages as a set-off, and argue on the strength of Security Ins. Co. of Hartford v. United States, 192 Ct.Cl. 754, 428 F.2d 838 (1970) that once “a performance bond surety and the government enter into a formal takeover agreement, a setoff is not to be permitted against the retained funds claimed by the performance bond surety.” Pls.’ Opp’n to Def.’s Mot. to Dismiss 3-5. The government counters that it did not exercise its right of set-off, but that even if it were exercising such a right, plaintiffs’ reliance on Security is misplaced because Security dealt with a claim wholly unrelated to the performance of the bonded contract. Def.’s Reply to Pls.’ Opp’n 5-6. Lastly, the government argues that the terms of the takeover agreement could not have extinguished the government’s entitlement to liquidated damages be[309]*309cause the CO lacked the authority to make such a concession on behalf of the government. Def.’s Mot. to Dismiss 4-5.

IV. DISCUSSION

A. Jurisdiction

The Tucker Act grants this Court jurisdiction over “any claim against the United States founded either upon the Constitution, or any Act of Congress or any regulation of an executive department, or upon any express or implied contract with the United States, or for liquidated or unliquidated damages in cases not sounding in tort.” 28 U.S.C. § 1491(a)(1). However, the Tucker Act is “only a jurisdictional statute; it does not create any substantive right enforceable against the United States for money damages.” United States v. Mitchell, 445 U.S. 535, 538, 100 S.Ct. 1349, 63 L.Ed.2d 607 (1980) (quoting United States v. Testan, 424 U.S. 392, 398, 96 S.Ct. 948, 47 L.Ed.2d 114 (1976)). The plaintiff must also “assert a claim under a separate money-mandating constitutional provision, statute, or regulation, the violation of which supports a claim for damages against the United States.” Khan v. United States, 201 F.3d 1375, 1378 (Fed.Cir.2000) (quoting James v. Caldera, 159 F.3d 573, 580 (Fed.Cir.1998)).

The Contract Disputes Act of 1978 (“CDA”) is such a money-mandating statute. It authorizes this Court to adjudicate a claim for monetary damages arising from “any express or implied contract ... entered into by an executive agency for ... the procurement of construction, alteration, repair or maintenance of real property” filed within twelve months of a contracting officer’s final decision concerning the claim. 41 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alpha Energy v. GEC, LLC
Virgin Islands, 2024
Castillo v. United States
Federal Claims, 2023
Abu-Shawish v. United States
Federal Claims, 2022
In Re: LTC Holdings, Inc.
D. Delaware, 2020
Menendez v. United States
Federal Claims, 2018
Phila. Indem. Ins. Co. v. Ohana Control Sys., Inc.
289 F. Supp. 3d 1141 (D. Hawaii, 2018)
Zebel LLC v. United States
Federal Claims, 2017
Shaw v. United States
131 Fed. Cl. 181 (Federal Claims, 2017)
Tidewater Contractors, Inc. v. United States
131 Fed. Cl. 372 (Federal Claims, 2017)
Nesselrode v. United States
127 Fed. Cl. 421 (Federal Claims, 2016)
Kenneth Earman v. United States
114 Fed. Cl. 81 (Federal Claims, 2013)
Colonial Surety Co. v. United States
108 Fed. Cl. 622 (Federal Claims, 2013)
Hartford Fire Insurance v. United States
108 Fed. Cl. 525 (Federal Claims, 2012)
Lyons v. United States
99 Fed. Cl. 552 (Federal Claims, 2011)
Carahsoft Technology Corp. v. United States
86 Fed. Cl. 325 (Federal Claims, 2009)
West Bay Builders, Inc. v. United States
85 Fed. Cl. 1 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
83 Fed. Cl. 306, 2008 U.S. Claims LEXIS 244, 2008 WL 4061064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-surety-co-v-united-states-uscfc-2008.