Hartford Fire Insurance v. United States

108 Fed. Cl. 525, 2012 U.S. Claims LEXIS 1255, 2012 WL 5194055
CourtUnited States Court of Federal Claims
DecidedOctober 22, 2012
DocketNo. 11-499C
StatusPublished
Cited by6 cases

This text of 108 Fed. Cl. 525 (Hartford Fire Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Fire Insurance v. United States, 108 Fed. Cl. 525, 2012 U.S. Claims LEXIS 1255, 2012 WL 5194055 (uscfc 2012).

Opinion

[528]*528 OPINION AND ORDER

BOHDAN A. FUTEY, Judge.

This case comes before the Court on defendant’s Motion to Dismiss.

On August 2, 2011, plaintiff Hartford Fire Insurance Company (“Hartford”), a Connecticut corporation with its principal place of business in Hartford, Connecticut, filed a complaint in the Court of Federal Claims against the United States, acting specifically through the United States Army Corps of Engineers (“the Corps”). The complaint alleged the Corps wrongfully disbursed funds to Overstreet Electric Co. (“Overstreet”), a contractor for whom Hartford had acted as a Miller Act surety on two federal contracts with the Corps. Hartford seeks to exercise its right of equitable subrogation, and seeks damages of $700,000, which it claims the Corps wrongfully paid to Overstreet in violation of the government’s stakeholder duty to the surety. The government filed a motion to dismiss under United States Court of Federal Claims Rules (“RCFC”) 12(b)(1) and 12(b)(6), citing the Court’s jurisdictional statute of limitations, and a failure to state a claim upon which relief may be granted. On April 11, 2012, the Court granted Hartford’s unopposed motion to amend its complaint, clarifying Hartford’s position on its accrual of its claim, damages, and settlement negotiations concerning the payment at issue. In its response, defendant withdrew its statute of limitations argument, but reiterated its arguments for dismissal under RCFC 12(b)(6).

This is a case which plaintiff seeks to fit within the holding in Transamerica, in which the Court of Appeals for the Federal Circuit held that a performance bond surety stated a cause of action against the government for equitable subrogation when it sought funds payable by the government to the contractor on an equitable adjustment to a separate contract. Transamerica Ins. Co. v. United States, 989 F.2d 1188, 1195 (Fed.Cir.1993). This “two-contract” theory of recovery allowed the surety as equitable subrogee, to offset its loss on one contract with an amount due to the contractor on a second contract. Id. Transamerica distinguished a line of pri- or cases, and limited its holding to cases in which the balancing of the equities favored recovery. Id. at 1192-95.

I. Background1

This ease involves two federal contracts, both procured through the Army Corps of Engineers and awarded to Over-street Electric Co. As required by the Miller Act for all construction contracts over $100,000, a surety—here, Hartford Fire Insurance Company—posted performance and payment bonds for the projects.2 See Miller Act, 40 U.S.C. § 3131(b) (2011). Upon the prime contractor’s default, the performance bond surety has the option of either completing the project itself, or of assuming liability for the government’s excess costs in completing the contract. Ins. Co. of the West, 243 F.3d 1367, 1370 (Fed.Cir.2001); Aetna Cas. & Sur. Co. v. United States, 845 F.2d 971, 975 (Fed.Cir.1988). A third alternative is to provide the funds to an insolvent contractor to complete performance. Ins. Co. of the West, 243 F.3d at 1370.

On October 5, 2000, the Corps awarded Contract No. DACW27-01-C-0001 to Over-street for the rehabilitation of pumping stations along the Little Calumet River in Lake County, Indiana (“Little Calumet Project”). Substantial completion was to occur by October 24, 2004. In accordance with the Miller Act, Hartford issued payment and performance bonds on the project in the amount of $4 million. On September 13, 2001, the Corps awarded Contract No. DACW21-01-C-001 to Overstreet for disposal area improvements and weir replacement in an area of the Savannah Harbor near Savannah, [529]*529Georgia (“Savannah Project”). Hartford also issued payment and performance bonds for this project in the amount of $4,306,035.86.

Problems arose and on July 29, 2003, the Corps terminated Overstreet for default on the Savannah Project. Overstreet submitted a claim pursuant to the Contract Disputes Act (“CDA”) on January 30, 2004, seeking a conversion to a termination for convenience based on its arguments of defective specifications, differing site conditions, and delay in performance due to the defective specifications. The Corps denied Overstreet’s request, and on June 30, 2004, Overstreet filed suit against the Corps in the Court of Federal Claims. Fed. Cl. Docket No. 04-1067C. The government filed a counterclaim in the suit for $1.48 million.3

While the dispute over the Savannah Project was unfolding in late 2004 and early 2005, problems on the Little Calumet Project also developed. On February 7, 2005, the Corps issued a “Show Cause Notice” to Overstreet and Hartford, based upon Over-street’s failure to complete work within the schedule, and indicating it was considering a termination for default on the Little Calumet Project. The Corps directed Overstreet to respond in three days, and provide any information which would show the failure to perform was due to causes beyond its control. Overstreet did not respond within the three days. The contracting officer for the Little Calumet Project, Regina Blair, next sent a letter to Hartford, indicating its concern and lack of confidence in Overstreet’s ability to complete the project. The Corps had been awaiting the delivery of a complete work plan since October 2004, which Overstreet never submitted, and failed again to submit by its guaranteed February 16, 2005 deadline. On March 9, 2005, Overstreet sent a letter to Hartford, indicating that it was “up against the wall on th[e] [Little Calumet] project” and without involvement by Hartford, the Contracting Officer would be “likely left with no viable option but to terminate the contract for default.” On March 30, 2005, Blair sent a letter to Overstreet indi-eating default was imminent unless Over-street commenced work on all “punch list” and incomplete on-site efforts that could be done without a pump rebuilding subcontractor.

Three weeks later, on April 19, 2005, there was a settlement conference regarding Over-street’s suit against the Corps for the Savannah Project. Following two days of negotiations, the Corps and Overstreet agreed to a complete settlement of claims. By its terms, the termination for default would be changed to a termination for convenience, and the United States would pay Overstreet $700,000. The settlement was contingent upon the Department of Justice’s approval. Hartford states that although its attorney attended the settlement conference, “he did so as an observer to obtain information concerning the government’s claim against Overstreet” and “did not actively participate in the settlement negotiations.”

On June 20, 2005, Gary Judd of Hartford sent an email to Blair, regarding the Little Calumet Project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
108 Fed. Cl. 525, 2012 U.S. Claims LEXIS 1255, 2012 WL 5194055, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-fire-insurance-v-united-states-uscfc-2012.