Applied Companies v. United States

144 F.3d 1470, 42 Cont. Cas. Fed. 77,303, 41 Fed. Cl. 1470, 1998 U.S. App. LEXIS 10488, 1998 WL 265529
CourtCourt of Appeals for the Federal Circuit
DecidedMay 27, 1998
Docket97-5085
StatusPublished
Cited by71 cases

This text of 144 F.3d 1470 (Applied Companies v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Applied Companies v. United States, 144 F.3d 1470, 42 Cont. Cas. Fed. 77,303, 41 Fed. Cl. 1470, 1998 U.S. App. LEXIS 10488, 1998 WL 265529 (Fed. Cir. 1998).

Opinion

BRYSON, Circuit Judge.

This case concerns the law of setoffs. The dispute began when the government made two overpayments to Applied Companies, a government contractor. Applied agreed that it was obligated to repay the money, but instead of repaying it directly, Applied sought to set off the debt against obligations the government owed to it on other contracts. The government rejected Applied’s proposals and instead discharged Applied’s debt by setting it off against the amount the government had agreed to pay Applied pursuant to a termination settlement agreement on another contract. Applied objected to the setoff and sued in the Court of Federal Claims to recover the funds that were withheld from the proceeds of the termination settlement agreement. The Court of Federal Claims rejected Applied’s challenge to the government’s setoff. Applied Cos. v. United States, 37 Fed. Cl. 749 (1997). We affirm.

I

This case has a complicated factual background, the details of which are set forth in *1473 the thorough opinion prepared by the trial judge. See Applied Cos., 37 Fed. Cl. at 751-55. Applied entered into several contracts with the government to supply air conditioning units. One of those contracts, Contract No. 0058, was terminated for default by the government. The Armed Services Board of Contract Appeals converted the default termination into a termination for the convenience of the government, and the parties negotiated a termination settlement agreement. Under the terms of the settlement, the government agreed to pay Applied $2,818,931.34 to resolve all claims from the terminated contract.

The government, however, did not pay Applied that sum, but instead paid only $911,-604.11. That sum was paid to Comeriea Bank, to which Applied had assigned the proceeds of Contract No. 0058 as partial collateral for a loan. The government used the remainder to offset two overpayments that the government had previously made to Applied on another contract, Contract No. C072, three years earlier.

The overpayments on Contract No. C072, which were apparently the product of a computer error, resulted in a total excess payment to Applied of $1,399,005.19. Applied promptly notified the government of the overpayments, but instead of returning the money, Applied proposed several arrangements to discharge the debt by crediting the overpayments against other outstanding government obligations to Applied. The government did not accept any of Applied’s proposals, but insisted on direct repayment. Applied did not return the overpayments, and the government ultimately chose to recoup the overpayments by offsetting them against the sum the government agreed to pay Applied in connection with the settlement of Contract No. 0058. Applied protested the setoff, but the contracting officer denied the protest.

Applied sought review of the government’s actions in the Court of Federal Claims, arguing that the setoff violated the terms of the settlement agreement on Contract No. 0058 and was improper for other reasons as well. The Court of Federal Claims rejected each of Applied’s arguments and granted summary judgment in favor of the government. First, the court held that the termination settlement agreement did not bar the setoff, because nothing in the agreement deprived the government of its common law setoff right. Second, the court rejected Applied’s argument that it had previously retired its debt to the government by setting it off against obligations the government owed Applied on other contracts. The court found that Applied had “not established that at the time the government properly exercised its setoff rights [Applied] had previously exercised a valid setoff.” Third, the court held that the government’s setoff did not have to be predicated on the final decision of a contracting officer, because the government’s right to recover the overpayment was not subject to the Contract Disputes Act. Finally, the court rejected Applied’s argument that the Assignment of Claims Act of 1940, 31 U.S.C. § 3727 and 41 U.S.C. § 15, barred the government from taking a setoff against the funds in the termination settlement agreement. The “nosetoff’ provision of the Assignment of Claims Act, the court explained, was intended to protect assignees and therefore was not enforceable by an assignor such as Applied.

II

Applied first argues that it retired the overpayment debt well before the government took its setoff, and that it did so by offsetting the overpayment debt against contract obligations the government owed to Applied under Contract No. B013, a separate contract for air conditioning units. The trial court rejected that argument, and we uphold the court’s ruling on that issue.

The record of correspondence between Applied and the government concerning the overpayment debt indicates that the matter remained unresolved until the government’s setoff of the settlement proceeds. Applied wrote four letters between April 1992 and July 1992 notifying the government of its *1474 intention to discharge the overpayment debt by crediting it against the government’s obligations on various contracts with Applied. In three of those letters, Applied proposed to credit the overpayments against its claim on Contract No. 0058 and asked for the government’s acquiescence in that arrangement. The government responded that it did not agree to Applied’s proposed crediting plan and demanded immediate repayment.

In May 1993 the government wrote a letter informing Applied that more than $96,000 in interest had accrued on the overpayments and offering Applied the alternative of entering into an installment plan to discharge the debt. Applied responded by requesting a “Deferred Payment Agreement,” which would have allowed the government to offset the ovei'payments against the settlement of various contract claims that Applied had filed against the government. Again, the government declined Applied’s proposal.

On August 28, 1993, Applied sent the government the x’esults of its “payment analysis” of two contracts, Contract No. C072 and Conti’act No. B013. Applied’s analysis showed that the government owed it a balance of $21,905.02 on the two contracts. Applied deiived that amount by crediting the government with the original overpayment on Contract No. C072, subtracting unpaid amounts on that contract, and subtracting an additional $1,280,349.19 that Applied claimed was the outstanding balance the government owed on Contract No. B013. In effect, Applied proposed that the overpayment be set off against amounts owed to Applied on the C072 and B013 contracts. In the Court of Federal Claims, Applied also submitted the declaration of its Chief Financial Officer, Kent Fortin, who averred that he had actually made the claimed setoff between Contract No. C072 and Contract No. B013 in July 1992, more than a year before the August 1993 letter.

On August 30, 1993, two days after the letter containing the payment analysis, Applied wrote the government and proposed to release the government from Applied’s claims on yet another contract, Contract No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Quinn v. City of New York
S.D. New York, 2025
Richardson v. United States
110 F.4th 1375 (Federal Circuit, 2024)
United Aeronautical Corp. v. Usaf
80 F.4th 1017 (Ninth Circuit, 2023)
Sana Kappouta v. Valiant Integrated Services
60 F.4th 1213 (Ninth Circuit, 2023)
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
Systems Application & Tech v. United States
26 F.4th 163 (Fourth Circuit, 2022)
Odyssey International, Inc.
Armed Services Board of Contract Appeals, 2021
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
CLC Construction Company
Armed Services Board of Contract Appeals, 2020
Conway v. United States
Federal Claims, 2019
Mirror Worlds Techs., LLC v. Facebook, Inc.
320 F. Supp. 3d 538 (S.D. Illinois, 2018)
3rd Eye Surveillance, LLC v. United States
133 Fed. Cl. 273 (Federal Claims, 2017)
Kansas City Power & Light Co. v. United States
131 Fed. Cl. 161 (Federal Claims, 2017)
Bruhn Newtech, Inc. v. United States
129 Fed. Cl. 656 (Federal Claims, 2016)
AeroVironment, Inc.
Armed Services Board of Contract Appeals, 2016
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Palafox Street Associates, L.P. v. United States
122 Fed. Cl. 18 (Federal Claims, 2015)
United States Enrichment Corporation v. United States
121 Fed. Cl. 532 (Federal Claims, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
144 F.3d 1470, 42 Cont. Cas. Fed. 77,303, 41 Fed. Cl. 1470, 1998 U.S. App. LEXIS 10488, 1998 WL 265529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/applied-companies-v-united-states-cafc-1998.