Beaconwear Clothing Co. v. United States

355 F.2d 583, 174 Ct. Cl. 40, 1966 U.S. Ct. Cl. LEXIS 145
CourtUnited States Court of Claims
DecidedJanuary 21, 1966
DocketNo. 226-59
StatusPublished
Cited by26 cases

This text of 355 F.2d 583 (Beaconwear Clothing Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beaconwear Clothing Co. v. United States, 355 F.2d 583, 174 Ct. Cl. 40, 1966 U.S. Ct. Cl. LEXIS 145 (cc 1966).

Opinion

CoweN, Ohief Judge,

delivered the opinion of the court:

This is a suit on a Government contract brought by Beaconwear Clothing Company, a nominal plaintiff which is no longer in business, to the use and benefit of The Amal[43]*43gamated Bank of New York, which disavows any financial interest in the action. The Bank has filed a third-party petition by reason of the fact that it is the record assignee from Beaconwear, the contractor, of all proceeds on the contract in question. Joseph Spiotta, trading as Spiotta & Company, a subcontractor which performed all the work on the contract, has also filed a third-party petition, claiming recovery by virtue of its alleged status: (a) as beneficiary of Beaconwear’s assignment to the Bank, and (b) as transferee on a second assignment of the proceeds from Beaconwear. Defendant has entered a counterclaim against Beaconwear arising out of an earlier and separate contract.

Beaconwear Clothing Company (hereinafter referred to as Beaconwear), a partnership composed of Lawrence B. Nasher and Joseph S. Nasher, was awarded contract no. DA30-352-TAP-2020 on May 29,1953, for the manufacture of 64,000 cotton overcoats for the Army. 32,000 coats were to be delivered by October 31,1953, and the remaining 32,000 by November 31 of the same year, with materials to be furnished by defendant. Beaconwear had. arranged for performance of the contract by a subcontractor, General Coat, Inc. of Brooklyn, New York, but this firm never performed any work on the project, and production did not effectively begin until the end of the year. No deliveries having been made as of November 10, 1953, Beaconwear requested permission to subcontract the entire contract, quantity to Joseph Spiotta, trading as Spiotta & Company, (referred to throughout as Spiotta). A copy of the proposed subcontract agreement was forwarded to the contracting officer, and approval was granted “within the terms and conditions of the contract,” upon the understanding that Beaconwear would remain liable for any loss or damage to Government furnished property. On November 21, 1953, pursuant to the terms of the subcontract agreement with Spiotta, Beacon-wear assigned all right and title to the proceeds of the contract to a financial institution of Spiotta’s designation — The Amalgamated Bank of New York, third-party plaintiff herein (to be referred to as the Bank). This assignment from Beaconwear to the Bank conformed in all respects to the Assignment of Claims Act of 1940 (31 U.S.C. §203 [44]*44(1952)). Hence, at this stage Spiotta was the approved subcontractor under Beaconwear, charged with the manufacture and delivery of all the overcoats described in the contract, and the Bank was the authorized assignee of the proceeds of the contract. Although subsequent events and transactions have tended to complicate and confuse the factual pattern of the case, this essential relationship of Beaconwear as prime contractor, Spiotta as subcontractor, and the Bank as sole legal assignee, remained unaltered throughout the duration of the contract performance.

On January 18,1954, Beaconwear attempted a second assignment of all rights and title to the moneys receivable under the contract to “Joseph Spiotta, Charles Silverman, or Joseph Freda.” The document evidencing this transfer was phrased in the same language as, and made subject to, the prior assignment to the Bank. The three men (Silverman and Freda were employees of Spiotta at the time) were then given power of attorney to act for Beaconwear, to demand and receive all proceeds from the United States or the Bank, and to open a special account in the Bank in Beaconwear’s name. The practical result of this arrangement was that when deliveries of overcoats were ultimately received by defendant from Spiotta, payments on the contract were made to the assignee Bank, where they were deposited in the special Beaconwear account and subsequently withdrawn by Spiotta.

Because performance of the contract had been delayed and no deliveries tendered as of February 16, 1954, the contracting officer terminated Beaconwear’s right to manufacture and deliver 30,000 of the 64,000 overcoats called for. The remaining 34,000 units were eventually delivered 'by subcontractor Spiotta as of June 7, 1954, and accepted by defendant. Contract performance has thus been completed and the only matter outstanding concerns the question of compensation. Proper adjudication of this subject necessarily entails a determination: (1) as to what theory and facts form the basis of the cause of action; (2) as to what amount of recovery is allowable; and (3) as to which party, if any, is entitled to recover the said amount.

The claims asserted here'by plaintiffs arise out of certain deductions which it is alleged were improperly made by de[45]*45fendant on the pertinent contract. These deductions fall into four general categories: (1) savings to the contractor on the substitution of an aluminum buckle for the originally specified phenolic one; (2) savings to the contractor for deviations in Operations 33C, 41C, 41L, and IOC of the contract; (3) loss of Government furnished property; and (4) the taking by defendant of unwarranted prompt payment discounts. Each of these subjects (to be referred to respectively as the Buckle, Deviations, Government Furnished Property, and Discount claims) will later be accorded separate and more specific treatment.

As to the matter of the amount of recovery, there has been Substantial uncertainty and confusion. Plaintiffs have claimed various sums on essentially the same items at different stages of the litigation. In the petition, amended petitions, and motion for summary judgment, the sums of $2,617.65, $3,638.61, $5,784.06, $4,595.18, $2,040.46, and $2,306.20 appear in the respective prayers for relief. Plaintiffs’ requested findings of fact claim entitlement in the amount of $2,028.04, and it was on the basis of this claim that findings of fact were made by our trial commissioner.'

Assuming for the moment that the cause of action is meritorious, there next arises the question of which party is entitled to recovery on the contract. The court has before it as parties-plaintiff the contractor, the subcontractor, and the assignee. This, of course, is not a singular occurrence. What complicates matters, however, is the fact that Beacon-wear, the contractor and normal plaintiff in such a case, is not suing in its own name, but for the benefit of the Bank. The Bank in turn has stated that it has no interest in the case. Spiotta is the real party in interest, having performed all the work on the contract and being the only party with a financial stake in the outcome of the action. It bases its primary claim to recovery here on either, or both, of the two assignments of the contract proceeds made by Beacon-wear, alluded to above. Spiotta argues secondarily that it acquired the status of de facto prime contractor by reason of: (a) its having assumed responsibility for manufacture and delivery of all the overcoats called for, and (b). its having received from Beaconwear a general power of attorney [46]*46to perform the entire contract and collect tlie proceeds thereon.

The trial commissioner to whom this case was referred has made findings of fact on each of the four claims which form the basis of plaintiffs’ cause of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northrop Grumman Computing Systems, Inc. v. United States
99 Fed. Cl. 651 (Federal Claims, 2011)
Applied Companies v. United States
144 F.3d 1470 (Federal Circuit, 1998)
Capital Nat. Bank of New York v. McDonald's Corp.
625 F. Supp. 874 (S.D. New York, 1986)
Pan Arctic Corp. v. United States
33 Cont. Cas. Fed. 73,742 (Court of Claims, 1985)
Diamond Manufacturing Co. v. United States
31 Cont. Cas. Fed. 71,579 (Court of Claims, 1983)
Walker v. United States
30 Cont. Cas. Fed. 70,000 (Court of Claims, 1982)
Mitsui & Co. v. Puerto Rico Water Resources Authority
528 F. Supp. 768 (D. Puerto Rico, 1981)
Unihealth Services Corp.
650 F.2d 288 (Court of Claims, 1980)
Rel-Reeves, Inc. v. United States
606 F.2d 949 (Court of Claims, 1979)
First National City Bank v. United States
537 F.2d 426 (Court of Claims, 1976)
Sampson v. United States
529 F.2d 1299 (Court of Claims, 1976)
Brown v. United States
524 F.2d 693 (Court of Claims, 1975)
United States v. Perry Lynch
499 F.2d 1011 (D.C. Circuit, 1974)
Talisman Associates, Ltd.
202 Ct. Cl. 1119 (Court of Claims, 1973)
Gardiner Manufacturing Co. v. United States
479 F.2d 39 (Ninth Circuit, 1973)
Uniroyal, Inc. v. United States
454 F.2d 1394 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
355 F.2d 583, 174 Ct. Cl. 40, 1966 U.S. Ct. Cl. LEXIS 145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beaconwear-clothing-co-v-united-states-cc-1966.