Pan Arctic Corp. v. United States

33 Cont. Cas. Fed. 73,742, 8 Cl. Ct. 546, 1985 U.S. Claims LEXIS 942
CourtUnited States Court of Claims
DecidedJuly 29, 1985
DocketNo. 412-84C
StatusPublished
Cited by7 cases

This text of 33 Cont. Cas. Fed. 73,742 (Pan Arctic Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pan Arctic Corp. v. United States, 33 Cont. Cas. Fed. 73,742, 8 Cl. Ct. 546, 1985 U.S. Claims LEXIS 942 (cc 1985).

Opinion

OPINION

SETO, Judge.

In this government contract case, a subcontractor has attempted to sue the United States directly, claiming it has been assigned all of the prime contractor’s claims against the government. The underlying issues raised by defendant’s motion to dismiss are: (1) whether the Assignment of Claims Act precludes a subcontractor from suing the government as an assignee; (2) whether the Severin Doctrine precludes the prime contractor from assuming the subcontractor’s role as plaintiff in this action; and (3) whether certain counts of the complaint must be dismissed as sounding in tort. For the reasons stated below, defendant’s motion is denied.

FACTS

In April 1972, Worthington Service Corporation (“Worthington”) entered into a negotiated contract with the U.S. Army Corps of Engineers for the removal of an engine-generator from Stewart Air Force Base in New York and its subsequent installation at Shemya Air Force Base in Alaska. Worthington then entered into a subcontract with Pan Arctic Corporation (“Pan Arctic”) to perform all of the construction work necessary for installation of the engine-generator at the Shemya facility.

Following the denial of certain claims presented to a contracting officer for the Department of the Army, Pan Arctic filed this action pursuant to 41 U.S.C. § 609(a). Prior to the commencement of this action, however, and as a result of other litigation between them, Worthington and Pan Arctic entered into a settlement agreement wherein Worthington purported to assign all of its claims against the government to Pan Arctic, its subcontractor. Although the agreement barred each party from asserting any claim arising out of the subject contracts against the others, it outlined each party’s role in the adjudication of the claims and delineated the distribution scheme for any potential recovery. On the basis of this agreement, and as Worthing-ton’s assignee, Pan Arctic sued the United States.

DISCUSSION

Assignment of Claims Act

It is a fundamental tenet of Claims Court jurisprudence that a subcontractor may not sue the government absent privity of contract. See Erickson Air Crane Co. v. United States, 731 F.2d 810, 813 (Fed.Cir.1984); United States v. Johnson Controls, Inc., 713 F.2d 1541, 1550-52 (Fed.Cir.1983). Therefore, a subcontractor without an independent basis for establishing privity with the government can seek redress only through the prime contractor. See Erickson Air Crane, 731 F.2d at 813-14.

In the instant case, Pan Arctic cannot sue the government in its own right because it lacks the requisite privity. Pan Arctic attempts to circumvent this jurisdictional limitation, however, by asserting it was assigned “all rights, title and interest in the claims which are the subject of this action” by its prime contractor, Worthington. Complaint at 2. Defendant argues that the Assignment of Claims Act, 31 U.S.C. § 3727 (1982), renders such an assignment null and void as against the Unit[548]*548ed States inasmuch as Pan Arctic is not a qualifying financial institution. See Uniroyal, Inc. v. United States, 454 F.2d 1394, 197 Ct.Cl. 258, 261 (1972). We agree. Because the assignment was not within the terms of the Assignmént of Claims Act, Pan Arctic is precluded from directly asserting its claim against the government as the assignee of its prime contractor. See also Beaconwear Clothing Co. v. United States, 355 F.2d 583, 174 Ct.Cl. 40, 49-50 (1966); Royal Indemnity Co. v. United States, 93 F.Supp. 891, 117 Ct.Cl. 736 (1950).

The Severin Doctrine

Because Worthington is the only party that can bring this action against the government, we must determine whether Worthington may be substituted as the party plaintiff. In its opposition to defendant’s motion to dismiss, Pan Arctic seeks leave of court to so amend the complaint. Defendant objects on the basis that the settlement agreement between Worthington and Pan Arctic completely releases Worthington from any liability to Pan Arctic, thereby eliminating the foundation for a suit by Worthington against the government. See Severin v. United States, 99 Ct.Cl. 435 (1943), cert. denied, 322 U.S. 733, 64 S.Ct. 1045, 88 L.Ed. 1567 (1944). Defendant’s invocation of the Severin Doctrine in the instant case, however, is inappropriate.

In Severin, the Court of Claims held that a contractor may sue the government for damages incurred by its subcontractor only if the contractor has suffered actual damages. Id. at 443. Therefore, such a suit may be brought “only when the prime contractor has reimbursed its subcontractor for the latter’s damages or remains liable for such reimbursement in the future.” J.L. Simmons Co. v. United States, 304 F.2d 886, 158 Ct.Cl. 393, 397 (1962). The doctrine thus provides that a contractor is precluded from maintaining a suit in behalf of its subcontractor when a contract clause or release completely exonerates the contractor from liability to its subcontractor. Id., 304 F.2d 886, 158 Ct.Cl. at 397-98. In such a case, the contractor has not suffered “actual damages.” See Severin, 99 Ct.Cl. at 443.

Defendant asserts that the settlement agreement of January 23, 1979 operates to invoke the proscription of the Severin Doctrine. In particular, defendant cites the language in paragraph 2 wherein Pan Arctic agrees to be “barred from asserting any other claim against any party in this matter for this project.” Plaintiff’s Appendix, Exhibit E at I.-. Defendant argues that this language completely releases Worthington from any liability to Pan Arctic, thereby precluding suit in this court. Defendant’s narrow reading of both the Severin Doctrine and the settlement agreement, however, cannot withstand judicial scrutiny.

In J.L. Simmons, the court was careful to emphasize that where the release from liability is not complete, the contractor will be permitted to sue the government in behalf of its subcontractor. J.L. Simmons, 304 F.2d 886, 158 Ct.Cl. at 398-400. Thus, the court has held on numerous occasions that a contractor may bring suit where the “contractor has agreed to reimburse its subcontractor for damages it has suffered at the hands of the Government, but only as and when the former receives payment for them from the Government.” Id., 304 F.2d 886,158 Ct.Cl. at 398. Accordingly, in cases where the contractor’s liability is conditioned on receiving payment from the government, the Severin Doctrine has been found not to apply.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northrop Grumman Computing Systems, Inc. v. United States
99 Fed. Cl. 651 (Federal Claims, 2011)
Lockheed Martin Corp. v. United States
50 Fed. Cl. 550 (Federal Claims, 2001)
Kentucky Bridge & Dam, Inc. v. United States
42 Cont. Cas. Fed. 77,404 (Federal Claims, 1998)
George Hyman Construction Co. v. United States
39 Cont. Cas. Fed. 76,601 (Federal Claims, 1993)
Eastern Trans-Waste of Maryland, Inc. v. United States
27 Fed. Cl. 146 (Federal Claims, 1992)
American National Bank & Trust Co. v. United States
36 Cont. Cas. Fed. 75,966 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 73,742, 8 Cl. Ct. 546, 1985 U.S. Claims LEXIS 942, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pan-arctic-corp-v-united-states-cc-1985.