Chain Belt Co. v. United States

115 F. Supp. 701, 127 Ct. Cl. 38
CourtUnited States Court of Claims
DecidedSeptember 30, 1953
Docket49292
StatusPublished
Cited by78 cases

This text of 115 F. Supp. 701 (Chain Belt Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chain Belt Co. v. United States, 115 F. Supp. 701, 127 Ct. Cl. 38 (cc 1953).

Opinions

LITTLETON, Judge.

In this suit the plaintiff seeks to recover damages in the amount of $267,-223.74, for breach of contract arising out of defendant’s failure to move its machinery out of a portion of the premises purchased by plaintiff from defendant oh the date agreed to in the contract of sale, and defendant’s failure to repair damage caused to the floors as a result of the moving operation when it was performed. The damages alleged and claimed by plaintiff to have resulted from such breach consist of the cost of $42,098.68 to plaintiff of repairing the floors damaged by the machinery removal methods employed by defendant’s moving contractor; the cost of utilities and services in the sum of $34,888.30 for the period following the agreed removal date during which time the Government-owned machinery remained in plaintiff’s plant; the cost of $2,191.52 to plaintiff of removing some of the Government-owned machinery when .it became apparent that the Government was not going to be able to complete the moving by the agreed date; and plaintiff’s losses in the sum of $178,045.24 resulting from its inability to make profitable use of that area of the plant containing the Government-owned machinery for the above period.

Plaintiff is a Wisconsin corporation with its principal office located at 1600 West Bruce Street, Milwaukee. For many years plaintiff has been one of the country’s leading manufacturers of construction and conveying machinery employing chain transmission, and owning plants in Massachusetts and in Wisconsin. Plaintiff had five plants in the Milwaukee area including Plant No. 1, located at 1600 West Bruce Street, where its chain manufacturing -operations were carried on.

In December 1941, the United States, through the Defense Plant Corporation, constructed in the Village of West Milwaukee, on land previously purchased from plaintiff, a large factory-type building designed for use in the production of gun barrels and related military equipment. During the war these premises were leased to plaintiff corporation which thereafter manufactured military materials therein under contracts with the defendant until the lease was terminated on October 18, 1945. From that time until September 10, 1946, plaintiff continued in possession of the plant pursuant to an informal understanding with defendant, whereby plaintiff, provided protection and maintenance services for the whole building and utilized some of the plant space for storage of its own materials.1

Plaintiff did not exercise a three-months’ option contained in the lease to purchase defendant’s plant, because it planned instead to construct a new and large plant in which to expand its chain manufacturing business to meet a strong post-war demand for its products. However, because of the availability, good condition and extensive floor space of defendant’s plant, plaintiff, in December 1945, commenced negotiations with defendant for the purchase of the gun plant. Plaintiff was also influenced by the fact that defendant’s plant could be made ready for use in a much shorter time than would be required to build a new plant. During the course of the negotiations defendant was advised of [705]*705plaintiff’s intended use of the plant, of its urgent need of the floor space and its desire to occupy the building in sound, usable condition at the earliest practicable date. On February 20, 1946, plaintiff offered to purchase the property for $1,041,599.97, including certain mechanical equipment and cranes present in the building. In April 1946, plaintiff increased its offer to $1,422,000 and this offer was accepted by defendant in July 1946.

On September 10, 1946, plaintiff and defendant, through War Assets Administration, entered into a contract of sale which provided for the sale to plaintiff of the land, buildings and installations, as listed on attached schedules, for $1,-422,000 to be paid in cash upon delivery to plaintiff of a quitclaim deed, which deed defendant agreed to deliver to plaintiff within thirty days. Paragraph Three provided that plaintiff had examined the premises and was satisfied as to their existence and condition. Paragraph Six provided that plaintiff understood that there was located on the premises a great number of items of production equipment, machinery and tools, automotive equipment, laboratory and testing equipment, and furniture and office equipment, which were owned by the Reconstruction Finance Corporation and were not included in the sale of the premises. The parties agreed that such items of machinery, etc., even though affixed to the realty, should be considered to be personal property of the seller and would not pass with the quitclaim deed to be later delivered. Defendant agreed that it would remove the items of machinery in question within 90 days from the date of the delivery of the quitclaim deed. Plaintiff agreed that defendant, its vendees, contractors and other authorized persons should have access to the premises at all reasonable hours “to the end that said property may be exhibited, sold, prepared for shipment, and removed in an orderly manner within said ninety-day period,” and that the property might remain on the premises during that period as part of the consideration for the transaction without cost or charge against defendant. Plaintiff further agreed to provide without cost to defendant such facilities and utilities as were on the premises and might be reasonably required to accomplish the purposes mentioned.

In Paragraph Ten plaintiff “certified” and agreed that it was acquiring the premises for its own use and not for the purpose of reselling or leasing it; and that in no case would plaintiff resell or lease the premises within three years from the date of the contract without first obtaining written authorization from the War Assets Administrator.

Although the contract of sale allowed defendant 30 days in which to deliver the quitclaim deed, the deed was delivered to plaintiff on September 11, 1946 (the day following the execution of the contract of sale), at which time plaintiff paid the full purchase price in cash.

Because of the large number of Government-owned machines located on the premises and the manner in which they were installed, it was reasonably to be anticipated that the better part of the stipulated 90 days would be required to effect an orderly removal of such machines. When, by October 1, 1946, defendant had done nothing to prepare for removal of the machinery, plaintiff commenced writing to defendant calling attention to the magnitude of the removal task and to the fact that unless defendant commenced removal operations at once, the plant would not be cleared within the 90-day contract period. Somewhat later, plaintiff pointed out to defendant that further delay in effecting the removal would aggravate the already inevitable damages that would accrue to plaintiff because of plaintiff’s inability to fully occupy and use the plant on the promised date, and plaintiff offered, to cooperate with defendant in any manner possible to help bring about the timely removal of defendant’s property.

On November 25, 1946, defendant finally entered into a contract with the [706]*706Shea-Matson Trucking Company for the removal of defendant’s machines. On December 4, 1946, War Assets Administration representatives held an on-site sale of some of defendant’s machinery, but defendant’s removal work did not commence until after that date.

On November 29, 1946, War Assets Administration wrote to plaintiff asking for an- extension of the time within which it might remove its property from plaintiff’s plant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clean Fuel Llc v. United States
110 Fed. Cl. 415 (Federal Claims, 2013)
Stovall v. United States
94 Fed. Cl. 336 (Federal Claims, 2010)
Dobyns v. United States
91 Fed. Cl. 412 (Federal Claims, 2010)
Hicks v. United States
89 Fed. Cl. 243 (Federal Claims, 2009)
SGS-92-X003 v. United States
85 Fed. Cl. 678 (Federal Claims, 2009)
Oswalt v. United States
85 Fed. Cl. 153 (Federal Claims, 2008)
Agredano v. United States
82 Fed. Cl. 416 (Federal Claims, 2008)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
Yankee Atomic Electric Co. v. United States
73 Fed. Cl. 249 (Federal Claims, 2006)
American Federal Bank, FSB v. United States
72 Fed. Cl. 586 (Federal Claims, 2006)
Rivera Agredano v. United States
70 Fed. Cl. 564 (Federal Claims, 2006)
Rodriguez v. United States
69 Fed. Cl. 487 (Federal Claims, 2006)
Carabetta Enterprises, Inc. v. United States
68 Fed. Cl. 410 (Federal Claims, 2005)
Precision Pine & Timber, Inc. v. United States
63 Fed. Cl. 122 (Federal Claims, 2004)
Standard Federal Bank v. United States
62 Fed. Cl. 265 (Federal Claims, 2004)
Franconia Associates v. United States
61 Fed. Cl. 718 (Federal Claims, 2004)
Indiana Michigan Power Co. v. United States
60 Fed. Cl. 639 (Federal Claims, 2004)
Whyte v. United States
59 Fed. Cl. 493 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
115 F. Supp. 701, 127 Ct. Cl. 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chain-belt-co-v-united-states-cc-1953.