United States v. Penn Foundry & Manufacturing Co.

337 U.S. 198, 69 S. Ct. 1009, 93 L. Ed. 2d 1308, 1949 U.S. LEXIS 2941
CourtSupreme Court of the United States
DecidedJune 6, 1949
Docket253
StatusPublished
Cited by51 cases

This text of 337 U.S. 198 (United States v. Penn Foundry & Manufacturing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Penn Foundry & Manufacturing Co., 337 U.S. 198, 69 S. Ct. 1009, 93 L. Ed. 2d 1308, 1949 U.S. LEXIS 2941 (1949).

Opinions

Mr. Justice Burton

delivered the opinion of the Court.

This is an action which was brought in the Court of Claims by the respondent, Penn Foundry and Manufacturing Company, Inc., against the United States for loss of anticipated profits alleged to have been caused by the latter’s cancellation of a contract for gun mounts for the Navy. The cancellation occurred a few days after the contract had been awarded by the United States to the respondent on February 23, 1942. The question presented is whether the findings of fact made by the Court of Claims are sufficient to sustain its judgment requiring the United States to pay for such loss. 110 Ct. Cl. 374, 75 F. Supp. 319. We hold that they are not. We so hold because of (1) the absence of any finding of the readiness and capacity of the respondent to perform certain of its contractual obligations upon which its profits were contingent and (2) the presence of certain affirmative findings which preclude the drawing of any sufficient inference of such readiness and capacity from the other findings. ,

The record includes only the pleadings and accompanying exhibits filed in the Court of Claims,and that court’s special findings of fact, conclusion of law, opinion, judgment and refusal to grant a new trial. We do not have before us the report which its Commissioner made to the [200]*200Court of Claims or: the testimony upon which he or that court relied. While, additional claims were made .by the respondent in its original petition to the Court of Claims and-while the United States originally contested the binding force of the contract, the errors specified in the present proceeding question only the right of the respondent to recover $80,000; as damages for its alleged loss of anticipated profits. We_gr anted certiorari because of the .possible relation of the result in this case to claims finder many war contracts cancelled by the JJnited States. 335 U. S. 857.

The findings of fact show the following:

In 1911, the respondent bought a manufacturing plant consisting of six buildings in Waynesboro, Virginiá. The main buildings, each 57 x .100 feet, ¿ad been built in 1890 and were referred to respectively as the machine shop, the foundry and the blacksmith shop. .At one time the respondent manufactured circular saws and, at another, did work on brake shoes. Since 1931, the plant had been used only for minor engagements, requiring not more than four .or five .employe'es. It had been idle for some, years when, la,te in 1940''or early in 1941, the respondent’s of-, ficers became desirous of engaging in the National Defense Program. -.Most of those officers were then in other businesses at or .near Pittsburgh, Pennsylvania. One stockholder and .director was in . the real estate business in Waynesboro. Be had been the local manager, of the plant when it was in operation and had continued thereafter as such and as thq statfitory agent of the company.

. In !January, 1941, the respondent engaged an additional man as assistant to the president and, on February 24,1942, an engineer as general manager. In April, 1941, it submitted a proposal to the Navy for the manufacture' of 500 3-inch 50,-caliber gun mounts. In July, a representative of the Gun Mount Section of the Navy Department inspected the plant. Following a conference in [201]*201September, the respondent was asked by the Government to furnish information as to financial ability, commit-' ments of subcontractors, and a detailed study of the machine tool operations, predicated upon a possible award of 150 3-inch 50-caliber mounts. In October and December, the respondent submitted additional information and slightly modified its proposals. December 22, the respondent’s proposal as to prices, quantities, delivery schedule, payments and options for additional mounts was accepted as satisfactory and the respondent agreed to secure a letter from a surety company indicating that a bond of the nature required by the Navy’s Bureau of Supplies and Accounts would be furnished'.

The respondent received a “letter of intent,” dated December 29, 1941, signed by the Paymaster General of the Navy as contracting officer and approved by the Under Secretary of the Navy. It stated that it was anticipated that the Navy Department would place an order with the respondent for the manufacture of 150 gun mounts. It specified the delivery of two complete mounts in May, 1942, three in June, five in July, and thereafter at a minimum rate of ten mounts per month. The letter also authorized the respondent to purchase materials and spare parts, subject to confirmation by the Government’s purchasing officer, and to proceed with the production of the mounts in anticipation of the placing of the order for their production. However, under date of January 7, 1942, the Government held up this authorization of expenditures until such time as the respondent furnished the Government with the firm commitment of an approved surety company to act as surety on a performance bond. January 10, the respondent accepted the letter of intent. January 29, the Navy Department stated that the necessary letter from a surety company had not beeñ received and that failure promptly to submit such a letter might result, in the termination of the [202]*202letter of intent. February 3, the respondent’s representatives submitted a letter from a surety company indicating that that company thought that a bond in connection with a contract of this size would have to be, reinsured and that, unless some change were made in the financial setup, reinsurance would be declined. It added, however, that, if either of two suggested plans relative to refinancing were accomplished and if the respondent furnished certain information as to new key personnel to be engaged by the respondent, then the reinsurance could be obtained and the surety company could execute a bond. The findings of fact disclose a difference in the testimony as. to. the reaction of the Government's, representative to this-letter. -There is no finding that the Government’s requirement in this regard ever was met.

Much in the following findings of fact Nos. 5-8 is vital to the issue before us:

“5. On January 16 and 17, 1942, plaintiff’s plant,, was visited by inspectors of the Philadelphia Inspection District of the Navy Department to instruct plaintiff’s personnel as to the Navy inspection requirements. At the time there was no one at the plant except the watchman and the local manager. No work at dll was being performed at the time. On February 19, 1942, á production specialist from the War Production Board visited the plant. His duties were to assist production in factories in the production of naval ordnance. At that time only the watchman was at jt%e plant. The production specialist inspected the plant with the local manager, who was called from his, real estate office, and also talked with Mr: Johnson [the new assistant to the president], who was called to Waynesboro for that purpose. Reports of these visits were given to the Navy Department. At that time the comyany was [203]*203not prepared to undertake work of the character proposed by the contract, and would not for ah indefinite time be prepared successfully to complete a contract for 150 gun mounts. Plaintiff’s foundry was incapable of production of the cast steel forgings required for the gun mounts. It was plaintiff’s plan, as shown by its proposal to the Government, to subcontract for these eastings, as well as for other parts of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anchor Savings Bank, FSB v. United States
121 Fed. Cl. 296 (Federal Claims, 2015)
Biosig Instruments, Inc. v. Nautilus, Inc.
783 F.3d 1374 (Federal Circuit, 2015)
SWR, Inc.
Armed Services Board of Contract Appeals, 2014
United States v. Knauer
635 F. Supp. 2d 203 (E.D. New York, 2009)
Sarei v. Rio Tinto PLC.
221 F. Supp. 2d 1116 (C.D. California, 2002)
California Federal Bank v. United States
43 Fed. Cl. 445 (Federal Claims, 1999)
Gleave v. Graham
954 F. Supp. 599 (W.D. New York, 1997)
Daybreak Construction Specialties, Inc. v. Saghatoleslami
712 P.2d 1028 (Colorado Court of Appeals, 1985)
American Science & Engineering, Inc. v. United States
8 Cl. Ct. 129 (Court of Claims, 1985)
McDonnell Douglas Corp. v. Islamic Republic of Iran
758 F.2d 341 (Eighth Circuit, 1985)
Reprosystem, BV v. SCM Corp.
522 F. Supp. 1257 (S.D. New York, 1981)
Dairy Sales Corp. v. United States
593 F.2d 1002 (Court of Claims, 1979)
Marder v. Conwed Corp.
75 F.R.D. 48 (E.D. Pennsylvania, 1977)
Rivenbark v. Finis P. Ernest, Inc.
346 N.E.2d 494 (Appellate Court of Illinois, 1976)
North Star Aviation Corp. v. United States
458 F.2d 64 (Court of Claims, 1972)
Nolan Brothers, Incorporated v. The United States
405 F.2d 1250 (Court of Claims, 1969)
Low v. Honolulu Rapid Transit Co.
445 P.2d 372 (Hawaii Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
337 U.S. 198, 69 S. Ct. 1009, 93 L. Ed. 2d 1308, 1949 U.S. LEXIS 2941, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-penn-foundry-manufacturing-co-scotus-1949.