North Star Aviation Corp. v. United States

458 F.2d 64, 198 Ct. Cl. 178, 1972 U.S. Ct. Cl. LEXIS 65
CourtUnited States Court of Claims
DecidedApril 14, 1972
DocketNo. 264-69
StatusPublished
Cited by3 cases

This text of 458 F.2d 64 (North Star Aviation Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Star Aviation Corp. v. United States, 458 F.2d 64, 198 Ct. Cl. 178, 1972 U.S. Ct. Cl. LEXIS 65 (cc 1972).

Opinion

Per Curiam;

This case was referred to Trial Commissioner William E. Day with directions to make findings of fact and recommendation for conclusions of law under the [180]*180order of reference and Eule 134(h). The commissioner has done so in an opinion and report filed on December 10,1971. Defendant timely filed a notice of intention to except to the commissioner’s report which, defendant subsequently withdrew. Both parties have now (by plaintiff’s motion of February 24, 1972, and supplemental motion of March. 3, 1972, and defendant’s response of February 28, 1972) stated their request or consent that the court adopt the trial commissioner’s opinion as the 'basis for its judgment in this case.

Since the court agrees with the commissioner’s opinion, findings of fact and recommended conclusion of law, as hereinafter set forth, it 'hereby grants plaintiff’s motion (as supplemented) for judgment and adopts the opinion, findings of fact and recommended conclusion of law as the basis for its judgment in this case without oral argument. Therefore, plaintiff is entitled to recover and judgment is entered for plaintiff in the sum of $16,780.

OPINION OP COMMISSIONER

Day, Commissioner: This is a contract case in which only the amount of damages is in issue, the government having admitted that it wrongfully terminated a contract made with the plaintiff. Since the pertinent facts are fully stated in the attached findings, it is enough to say here that the government’s action was based on its mistaken belief that plaintiff had defaulted by not furnishing a proper performance bond within the allowed time period. In fact, however, the termination was premature, coming before the period expired, and plaintiff eventually furnished a timely and proper bond. Both parties now agree that plaintiff was not in default.

The contract did not contain a clause allowing termination for the convenience of the government and none was required to be inserted under any applicable federal regulation. [Transcript at 6.] See G. L. Christian & Assoc. v. United States, 160 Ct. Cl. 1, 312 F. 2d 418 (1963), cert. denied 375 U.S. 954 (1963). There was only one reference to a convenience termination (see finding 3), and it was limited to [181]*181cases in which the contractor’s default might be excusable due to causes beyond his control. Consequently, the termination constituted a common law breach of contract. See Nolan Bros. v. United States, 186 Ct. Cl. 602, 609, 405 F. 2d 1250, 1254 (1969), in which this court said:

* * * In John Reiner & Co. v. United States [citation omitted], the Government canceled the contract outright (without any payment at all) because the General Accounting Office had said the award was improper; we held the award legal and the cancellation baseless but that the termination-clause measure-of-recovery applied ; if that article were absent or inapplicable, the defendant's action would have been treated exactly as a common law breach. * * * [Emphasis added.]

Accordingly, plaintiff’s recovery is to be measured by its anticipated profits from the contract. Cf. David J. Joseph Co. v. United States, 113 Ct. Cl. 3, 82 F. Supp. 345 (1949); Brown & Son Electric Co. v. United States, 163 Ct. Cl. 465, 325 F. 2d 446 (1963); Albano Cleaners, Inc. v. United States, 197 Ct. Cl. 450, 455 F. 2d 556 (1972).

Prior to trial, defendant asserted that no recovery should be allowed because plaintiff was not ready, willing and able to perform the contract on May 22, 1967, citing United States v. Penn Fowndry & Mfg. Co., 337 U.S. 198 (1949). Now, however, the government admits, and I have so found, that plaintiff would have been ready on time but for the government’s breach. Therefore, the only remaining task is to determine the amount of plaintiff’s anticipated profit.

In this regard, I have considered (1) plaintiff’s actual expenditures for 1969, the first year in which its books attributed expenses to individual aircraft, (2) the estimated costs of operating plaintiff’s business in 1967, (3) the performances of plaintiff’s competitors who had similar contracts with the Bureau of Land Management in 1967, and (4) the testimony of both parties’ expert witnesses. Based on these factors and the evidence presented, I have concluded that plaintiff’s reasonably anticipated profit on the terminated contract would have been $16,780.

[182]*182FINDINGS op Fact

1. Plaintiff, North Star Aviation Corporation, is and was at all times relevant hereto, a corporation organized under the laws of the State of Alaska, with its principal office in Fairbanks, Alaska. It was organized in 1966 by Eobert Schact and William Witmer for the purpose of obtaining and performing contracts with the Bureau of Land Management of the Department of the Interior to provide fire fighting services in Alaska.

2. Pursuant to an invitation to negotiate, plaintiff entered hito contract No. 14-11-0001-3555 (Neg.) with the Bureau of Land Management (BLM) to provide a tanker aircraft and pilot to be used for dropping fire retardants on forest and range fires in Alaska, from May 22 through August 19, 1967. Plaintiff was notified that this contract was accepted on December 9,1966.

3. The only provisions of the contract dealing with termination were contained in Article XX (Default and Termination), as follows:

ARTICLE XX. DEFAULT AND TERMINATION :

(a) The Government may, subject to the provision of Paragraph (c) below, by written notice of default to the contractor, terminate the whole or any part of this contract in any one of the following circumstances:
(1) If the contractor fails to perform the provisions of this contract within the time specified, or
(2) If the contractor fails to perform any of the provisions of this contract in accordance with its specifications, terms, and conditions, and does not cure such failure within the time specified by the Contracting Officer by written notice specifying such failure.
(b) In the event the Government terminates this contract in whole or in part as provided in (a) above, the Government may procure, upon such terms and in such manner as the Contracting Officer may deem appropriate, services, or any other requirements of the contract, similar to those terminated, and may take possession of and utilize in completing the work such materials, appliances and plant as may be on the site of the work and necessary therefor, and the contractor shall be liable to the Government for excess costs and any other damages [183]*183occasioned by the default of the contractor. If the Government does not terminate the contractor’s right to proceed, he shall continue the work and shall be liable to the Government for any actual damages occasioned by his failure to perform except to the extent that liquidated damages are stipulated in lieu thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marketing & Management Information, Inc. v. United States
57 Fed. Cl. 665 (Federal Claims, 2003)
IBI Security Service, Inc. v. United States
35 Cont. Cas. Fed. 75,740 (Court of Claims, 1989)
Peck Iron & Metal Co. v. United States
603 F.2d 171 (Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
458 F.2d 64, 198 Ct. Cl. 178, 1972 U.S. Ct. Cl. LEXIS 65, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-star-aviation-corp-v-united-states-cc-1972.