De Laval Steam Turbine Co. v. United States

284 U.S. 61, 52 S. Ct. 78, 76 L. Ed. 168, 1931 U.S. LEXIS 838
Supreme Court of the United States·Decided November 23, 1931·No. 6·Published·Cited by 34 cases

Opinion

*68 Mr. Justice Sutherland

delivered the opinion of the Court.

Petitioner, a manufacturer of marine steam turbines, prior to January 12, 1918, had entered into thirteen written contracts with various firms and corporations for the manufacture of steam turbine propulsion units for ships. In the early part of 1918, after petitioner had. commenced work under the contracts, the United States, acting through the Emergency Fleet Corporation, requisitioned these contracts, and advised the parties that it would rriake just compensation for the turbine equipment which the petitioner was required .to complete, and that the Emergency Fleet Corporation would assúme the responsibility of the contracts and make payment to petitioner.

The present controversy concerns three of these contracts (the other ten having been fully performed), the first for the construction of four marine turbine sets at the contract .price of $150,000, the. second for the construction of ten marine turbine sets at the’ contract price of $735,000, and the third for the construction of four marine turbine sets at the contract price of $216,000. Petitioner, continued to perform its obligations under these contracts as directed by the Fleet Corporation, for about a year, at which time, following the signing of the Armistice, it became necessary in the public interest to suspend op *69 erations Under the contracts, and, upon the several orders of the Fleet Corporation, petitioner suspended operations, stored the materials on hand, which had been assembled for the performance of the contracts, until January 14, 1920, when, by agreement, .they were released from the effect of the requisition and were taken over by petitioner at an agreed salvage value.

The Fleet Corporation awarded compensation to petitioner, but the latter thought the award insufficient arid sought by this suit .in the Court of Claims to have the amount of just. compensation determined. The Court of Claims gave judgment in favor of petitioner for its actual costs and expenditures over the cash payments received, amounting to $116,231.66, together with' $30,000 damages for extraordinary expenses resulting from the' stopping of work, and $15,000 for.expenses and rental incident to the storing of materials during the period after the order to stop work. From the total of these items, certain deductions, including a payment by the Fleet Corporation of 75% of the amount which it had awarded, were made, resulting in an award of $84,074.34; with interest thereon'from August 17, 1920. To this award the. court added $8,500, with interest from March 17, 1919, as the value of the three contracts at the time of their cancellation, and the loss sustained by the petitioner by reason thereof. According to the findings, the petitioner, if it had been allowed to complete the performance of the three contracts, would have realized a profit of over three hundred thousand dollars. . But the court below declined to include any amount for anticipated profits. 70 Ct. Cls. 51.

The sole question presented for our determination is whether petitioner was entitled to an allowance of the amount, or any part of the amount, of these anticipated profits.as a part of the just compensation.

*70 In Russell Motor Car Co. v. United States, 261 U. S. 514, the contract involved had been made directly with the government for the manufacture of certain war supplies. Following the Armistice, and while the contract was in .process of being pérfórmed, the Secretary of the Navy directed its cancellation. Suit was brought in the Court of Claims to recover just compensation. That court found that if the manufacturer had been permitted to complete the contract , according to its terms, a very large amount would have been earned as profits, but refused to include in its award any part of these anticipated profits. We affirmed this determination and held that the statute* which empowered the President “(t>) to modify, suspend, cancel, or requisition any existing or future contract for the building, production, or purchase, of ships or material,” applied to the government’s own contracts as well as to private contracts, and that just compensation for the cancellation of such contracts should include “ the value of the contract at the timé of its cancellation, not what it would have produced by way of profits for the Car Company if it had been fully performed.”

A distinction is sought to be drawn between the Russell Company case and the present case on the ground that there the contract was made directly with the government, and here they were made between private parties. The question, therefore, is whether this circumstance alters the rule in respect of just compensation. In determining that question the cardinal point to be borne in mind is that whether the contract requisitioned or canceled be one with the government or one between private individuals, the person whose property rights are taken or destroyed is entitled to receive just compensation, not damages as for a breach. A sufficient ground for the distinction lies in the fact that in the one case the requisition or cancellation is a *71 lawful act under the power of eminent domain, while in the other the act constituting the breach is unlawful.

In the present case the government requisitioned the purchasers’ rights in the contracts, not for the purpose of putting an end to the contracts, but of keeping them alive for the benefit of the government. Its action being in pursuance of law, the government succeeded to all the rights of, the purchasers under the contracts. The effect was the same as though the contracts, had beeen assigned by the purchasers with the consent of the manufacturer. There resulted, by operation of law, a substitution of purchasers, and the government became possessed of the right to enforce the contracts as though it had been an original contracting party. In effect, the old contracts became new contracts between the government and the petitioner. See F. Haag & Bro. v. Reichert, 142 Ky. 298, 301; 134 S. W. 191. Compare Wiggins Ferry Co. v. Ohio & M. Ry. Co., 142 U. S. 396, 408; Chicago, R. I. & P. Ry. Co. v. Denver & R. G. R. Co., 143 U. S. 596, 608.

In this view, the government canceled its own contracts, and it is hard to see why the Russell Company case is not strictly applicable. Moreover, the Act of June 15, 1917, c 29, 40 Stat. 182, authorized the President to cancel “ any existing or future contract,” etc., and this language, as we have held, applies whether the contract is with the government or between private parties. In either case, cancellation is an exercise of the power of eminent domain, and the- liability of the government is for- just compensation.

Free access — add to your briefcase to read the full text and ask questions with AI

De Laval Steam Turbine Co. v. United States, 284 U.S. 61, 52 S. Ct. 78, 76 L. Ed. 168, 1931 U.S. LEXIS 838 (1931).

284 U.S. 61 (De Laval Steam Turbine Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Conoco, Inc. v. Tinklenberg
121 P.3d 893 (Colorado Court of Appeals, 2005)
S.J. Amoroso Construction Co. v. United States
38 Cont. Cas. Fed. 76,360 (Court of Claims, 1992)
Hedstrom Lumber Co. v. United States
32 Cont. Cas. Fed. 73,113 (Court of Claims, 1984)
Markoe v. Legislature of the Virgin Islands
15 V.I. 3 (Virgin Islands, 1978)
Van Nostrand v. Board of Supervisors
67 Misc. 2d 1096 (New York Supreme Court, 1971)
Sullivan v. United States
395 U.S. 169 (Supreme Court, 1969)
G. L. Christian and Associates v. The United States
312 F.2d 418 (Court of Claims, 1963)
G. L. Christian & Associates v. United States
160 Ct. Cl. 1 (Court of Claims, 1963)
Fabrica Uruguaya de Neumaticos, S. A. v. United States
84 F. Supp. 745 (Court of Claims, 1949)
United States v. Penn Foundry & Manufacturing Co.
337 U.S. 198 (Supreme Court, 1949)
Cudahy Bros. v. United States
155 F.2d 905 (Seventh Circuit, 1946)
Graves v. United States
62 F. Supp. 231 (W.D. New York, 1945)
North Dakota v. Szarkowski
142 F.2d 333 (Eighth Circuit, 1944)
International Arms & Fuze Co. v. United States
101 Ct. Cl. 297 (Court of Claims, 1944)
Huber v. Moran
140 F.2d 823 (Eighth Circuit, 1944)