S.J. Amoroso Construction Co. v. United States

38 Cont. Cas. Fed. 76,360, 26 Cl. Ct. 759, 14 I.T.R.D. (BNA) 2083, 1992 U.S. Claims LEXIS 296, 1992 WL 153501
CourtUnited States Court of Claims
DecidedJuly 2, 1992
DocketNo. 91-943C
StatusPublished
Cited by7 cases

This text of 38 Cont. Cas. Fed. 76,360 (S.J. Amoroso Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.J. Amoroso Construction Co. v. United States, 38 Cont. Cas. Fed. 76,360, 26 Cl. Ct. 759, 14 I.T.R.D. (BNA) 2083, 1992 U.S. Claims LEXIS 296, 1992 WL 153501 (cc 1992).

Opinion

OPINION

LYDON, Senior Judge:

INTRODUCTION

The issue before the court involves the correct interpretation of the Buy American Act, 41 U.S.C. § 10a-§ 10d (1987) (amended 1988) (hereinafter “BAA”). Specifically, to resolve the cross motions for summary judgment, the court must decide whether, in a construction contract, the terms of the BAA apply in the aggregate to structural steel or to each individual piece of steel that is delivered to the construction site. In addition, the court must decide whether the contracting officer correctly excluded certain expenses when computing the domestic and foreign “costs” as that term is used in the BAA.

Plaintiff argues that the United States Army Corps of Engineers (hereinafter “Corps”) misinterpreted the BAA when it required plaintiff to calculate the domestic portion of each individual piece of structural steel delivered to the construction site. Plaintiff claims $363,250 in damages for the expense incurred calculating the domestic portion of each piece of steel and to replace approximately one-third of the structural steel which did not meet the BAA requirements under the Corps’ allegedly incorrect interpretation.

The court finds that the Corps interpreted the BAA requirements consistently with the numerous decisions of the various boards of contract appeals and the comptroller general. That interpretation is consistent with the language and purpose of the BAA. The interpretation urged by plaintiff, however, has the potential to undermine the purpose of the BAA. Therefore, the court grants defendant’s motion for summary judgment and denies plaintiff’s motion for partial summary judgment.

FACTS

On August 17, 1987, the Corps and S.J. Amoroso Construction Co., Inc. (hereinafter “Amoroso”), plaintiff, entered into an appropriated fund construction contract1 for construction of a commissary building at the Presidio, San Francisco, California, in the amount of $10,786,274.20. The contract provided a description of the work as follows:

Description of Work: 7283: Construction of reinforced concrete building (approx. 87,700SF) with concrete tilt up walls, steel roof deck, utilities, fire protection and alarm, paved parking, an [sic] landscaping: 7651A: Placement of approx. 10,600 LF of underground electrical pavement and installation of Government Furnished Equipment; 8140: Demolition of building which includes removal and disposal of asbestos siding and PCB fluorescent lighting ballast. Removal of Government salvage (gas meter, telephone booth, unit heaters, fire alarm box and sprinkler system shut off valve) which must be protected from damage during removal.

The contract was subject to the requirements of the BAA. 41 U.S.C. § 10a-§ lOd. The BAA provides, in relevant part:

Section 10a. American materials required for public use
[761]*761Notwithstanding any other provision of law, and unless the head of the department or independent establishment concerned shall determine it to be inconsistent with the public interest, or the cost to be unreasonable, only such unmanufactured articles, materials, and supplies as have been mined or produced in the United States, and only such manufactured articles, materials, and supplies as have been manufactured in the United States substantially all from articles, materials, or supplies mined, produced, or manufactured, as the case may be, in the United States, shall be acquired for public use. This section shall not apply with respect to articles, materials, or supplies for use outside the United States, or if articles, materials, or supplies of the class to be used or the articles, materials, or supplies from which they are manufactured are not mined, produced, or manufactured, as the case may be, in the United States in sufficient and reasonably available commercial quantities and of a satisfactory quality.
Section 10b. Contracts for public works; specification for use of American materials; blacklisting contractors violating requirements
(a) Every contract for the construction, alteration, or repair of any public building or public work in the United States growing out of an appropriation heretofore made or hereafter to be made shall contain a provision that in the performance of the work the contractor, subcontractors, material men, or suppliers, shall use only such unmanufactured articles, materials, and supplies as have been mined or produced in the United States, and only such manufactured articles, materials, and supplies as have been manufactured in the United States substantially all from articles, materials, or supplies mined, produced, or manufactured, as the case may be, in the United States except as provided in section 10a of this title: Provided, however, That if the head of the department or independent establishment making the contract shall find that in respect to some particular articles, materials, or supplies it is impracticable to make such requirement or that it would unreasonably increase the cost, an exception shall be noted in the specifications as to that particular article, material, or supply, and a public record made of the findings which justified the exception____

41 U.S.C. § 10a-§ 10b.2

The contract was assembled with the wrong BAA clause. The clause inserted in the contract was the BAA clause for supply contracts (clause no. 79), corresponding to 41 U.S.C. § 10a, instead of the clause utilized in construction contracts (clause no. 34) which corresponds to 41 U.S.C. § 10b. There is no dispute about the fact that the contract in question was a construction contract.

Plaintiff entered into a subcontract with Bostrom-Bergen (hereinafter “Bostrom”) on September 25, 1987, for structural steel, miscellaneous steel, structural welding, ultrasonic inspection of welds and steel joists. Bostrom was to fabricate, assemble and paint steel columns and beams to contract specifications from uncut steel beams. The finished pieces would consist of beams, columns, plates, struts, angles and other types of steel pieces. The process included (a) moving the raw material from the storage area to a saw for cutting to length, (b) taking the steel to an area for layout of holes, copes, shear plates, etc., (c) cutting the copes, (d) punching the holes, (e) taking the pieces to the painting area to prepare them for painting, (f) painting the pieces, (g) putting the pieces in sequence for erection, (h) loading the pieces for transportation to the construction site, and (i) erecting the pieces by crane then plumbing and bolting them.

By letter dated December 3, 1987, Bostrom informed Amoroso that it intended to purchase raw materials from a foreign source. This disclosure touched off a series of correspondence between Amoroso and Bostrom regarding compliance with [762]*762the BAA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glazer Const. Co., Inc. v. United States
50 F. Supp. 2d 85 (D. Massachusetts, 1999)
District of Columbia v. Organization for Environmental Growth, Inc.
700 A.2d 185 (District of Columbia Court of Appeals, 1997)
S.J. Amoroso Construction Co., Inc. v. United States
12 F.3d 1072 (Federal Circuit, 1993)
Department of General Services v. Harmans Associates Ltd. Partnership
633 A.2d 939 (Court of Special Appeals of Maryland, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,360, 26 Cl. Ct. 759, 14 I.T.R.D. (BNA) 2083, 1992 U.S. Claims LEXIS 296, 1992 WL 153501, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sj-amoroso-construction-co-v-united-states-cc-1992.