UNITED STATES of America, Plaintiff-Appellee, v. NEW ORLEANS PUBLIC SERVICE, INC., Defendant-Appellant

553 F.2d 459, 14 Fair Empl. Prac. Cas. (BNA) 1734, 1977 U.S. App. LEXIS 13072, 14 Empl. Prac. Dec. (CCH) 7602
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 6, 1977
Docket75-1130
StatusPublished
Cited by61 cases

This text of 553 F.2d 459 (UNITED STATES of America, Plaintiff-Appellee, v. NEW ORLEANS PUBLIC SERVICE, INC., Defendant-Appellant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
UNITED STATES of America, Plaintiff-Appellee, v. NEW ORLEANS PUBLIC SERVICE, INC., Defendant-Appellant, 553 F.2d 459, 14 Fair Empl. Prac. Cas. (BNA) 1734, 1977 U.S. App. LEXIS 13072, 14 Empl. Prac. Dec. (CCH) 7602 (5th Cir. 1977).

Opinions

AINSWORTH, Circuit Judge:

Appellant, New Orleans Public Service, Inc. (hereinafter NOPSI), appeals from an adverse decision of the district court holding that NOPSI is a government contractor subject to Executive Order 11246,1 and permanently enjoining NOPSI from failing and refusing to comply with the Order, as amended, and the implementing rules and regulations. Questions as to the force, coverage and enforcement of the Executive Order are involved. The principal issue today before us is whether a public utility which, under a city permit, enjoys a local monopoly in the sale of electricity and a near-monopoly in the sale of natural gas and which sells such energy to the Government in substantial amount can be required by the Government to comply with the equal opportunity obligations of Executive Order 11246, even though the utility has not agreed to be so bound. We hold that the Government can compel such a utility to follow the Order; however, we disagree with the district court as to the appropriate remedy.

Executive Order 11246 prohibits employment discrimination by government contractors. The Order was issued by President Johnson in 1965, and requires that all covered government contracts contain a nondiscrimination clause, including an agreement to take affirmative action to achieve the equal opportunity goals of the Executive Order’s mandate. Id. § 202.

NOPSI is a public utility which produces, distributes and sells electric power to consumers located in that part of New Orleans, Louisiana, on the east bank of the Mississippi River, and "sells and distributes natural gas to consumers throughout the city. The company sells its gas and electricity pursuant to indeterminate permits,2 like franchises, issued by the City Council of New Orleans. NOPSI is the only company with indeterminate permits to supply New Orleans with gas, and the east bank of the city with electricity. If any New Orleans consumer (including the Federal Government) on the east bank wishes to buy electric service, the consumer must purchase from NOPSI. NOPSI also provides most of the natural gas service to consumers (including the Federal Government) throughout the city, [462]*462and in those cases where companies receive their gas from other sources, NOPSI has agreed to the arrangement and has built and maintained the transmission line connecting the company with the parish boundary. The federal agencies which buy electricity from NOPSI are on the east bank, and have no alternative source of electric power. NOPSI is regulated by the City Council, which in 1973 granted the company rate increases for its electric and natural gas services to customers.

A number of federal agencies and installations in New Orleans are major purchasers of electricity and natural gas from NOPSI. In 1973 NOPSI supplied such federal users with nearly $2 million worth of electric utility service, and with more than $2,680,000 worth of electric and natural gas utility services combined. There are nine federal agencies which at the present time and during the period 1965-1973 each have received over $10,000 annually in combined gas and electric services from NOPSI; some of those each have received more than $50,000 in such utility services annually. The biggest user, the Michoud Assembly Facility (hereinafter Michoud) of the National Aeronautics and Space Administration (hereinafter NASA), alone received approximately $1.4 million worth of electricity and natural gas in 1973. The agencies are billed monthly and pay for the services on a regular basis.

According to the district court opinion, NOPSI supplies the Government with utility services pursuant to various contractual arrangements. The court found that NOP-SI is supplying 22 federal agencies under written agreements. Some of those contracts predated the Executive Order, but the court found that they were modified by, inter alia, the 1973 revised rate schedules which were approved by the City Council; were applied to the particular contract by NOPSI; and were accepted, through payment, by the agency. A few of those contracts contained nondiscrimination clauses required by earlier Executive Orders. In the case of two agencies in the group, the Government had sent NOPSI a proposed new contract, containing the nondiscrimination clause required by Executive Order 11246, but NOPSI rejected the proposed contract on the ground that the clause was unsatisfactory. Other contracts were signed in 1972 or on dates not specified by the district court opinion and were modified by the revised rate schedules in 1973.

In addition, the district court found that NOPSI is supplying six other federal agencies pursuant to contracts which were not formal, written agreements. Some of those contracts, for example, were based on letter requests from the federal agencies; another was based on an oral agreement.

Somewhat more complicated is the relationship between NOPSI and NASA’s Michoud facility. Disagreement in that relationship precipitated the instant litigation. NOPSI supplied Michoud with electricity and natural gas under a written contract between the utility and the space agency which was signed in 1965 and terminated according to its own terms in June 1970. That contract contained an equal opportunity clause which was required by Executive Order 10925, the predecessor of Executive Order 11246. The contract also contained a limitation clause restricting the scope of the contract to the Michoud operations. Because of the NASA-NOPSI relationship involving utilities service at Michoud, the Government has tried in the past to review NOPSI’s compliance with Executive Order 11246, but NOPSI has resisted on the ground that it was not covered by the Order. Attempts between the Government and NOPSI to negotiate a new utilities contract for Michoud broke down, with the Government unwilling to agree to a scope limitation like that in the 1965 contract, and NOPSI unwilling to agree to an equal opportunity clause without such a limitation. Nevertheless, NASA asked NOPSI to continue supplying Michoud, and NOPSI has continued to do so even though the formal contract has expired, subject to the rate schedules set out by NOPSI at the time of the termination of the written contract. The district court, after surveying the pre[463]*463ceding facts, held that a contract existed between NASA and NOPSI.3

The Government’s efforts to conduct a compliance review of NOPSI began in 1969, and further unsuccessful attempts were made through 1972. This action was initiated by the Government through the Justice Department in 1973 to compel NOPSI’s compliance with the Executive Order. After holding that NOPSI was covered by the Order, the district court permanently enjoined the utility from failing or refusing to comply with the Order and implementing regulations. The injunction reached NOP-SI’s refusal to allow the Government to conduct compliance reviews of NOPSI, and authorized the parties to begin discovery. In addition, the court retained continuing jurisdiction to effectuate NOPSI’s full compliance with the Executive Order.

I. The Validity and Applicability of the Executive Order

A. The Executive Order Program

The Executive Order requires that every nonexempt government contract contain a clause under which the employer agrees not to discriminate in employment on the basis of race, color, religion, sex or national origin, and further agrees to take affirmative action to achieve the equal opportunity objective. Exec. Order No. 11246, § 202(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Louisiana v. Biden
55 F.4th 1017 (Fifth Circuit, 2022)
State of Georgia v. President of the United States
46 F.4th 1283 (Eleventh Circuit, 2022)
Elzie Fuller, III v. Edwin B. Stimpson Co. Inc.
598 F. App'x 652 (Eleventh Circuit, 2015)
UPMC Braddock v. Harris
934 F. Supp. 2d 238 (District of Columbia, 2013)
United States v. Abu Marzook
412 F. Supp. 2d 913 (N.D. Illinois, 2006)
Shekoyan v. Sibley International Corp.
217 F. Supp. 2d 59 (District of Columbia, 2002)
Opinion Number
Louisiana Attorney General Reports, 1993
City of Waltham v. United States Postal Service
786 F. Supp. 105 (D. Massachusetts, 1992)
United States v. Whitney National Bank
671 F. Supp. 441 (E.D. Louisiana, 1987)
United States v. Thomas K. Bills, M.D.
822 F.2d 373 (Third Circuit, 1987)
Eatmon v. Bristol Steel & Iron Works, Inc.
769 F.2d 1503 (Eleventh Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
553 F.2d 459, 14 Fair Empl. Prac. Cas. (BNA) 1734, 1977 U.S. App. LEXIS 13072, 14 Empl. Prac. Dec. (CCH) 7602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-plaintiff-appellee-v-new-orleans-public-ca5-1977.