Rivenbark v. Finis P. Ernest, Inc.

346 N.E.2d 494, 37 Ill. App. 3d 536, 1976 Ill. App. LEXIS 2219
CourtAppellate Court of Illinois
DecidedApril 22, 1976
Docket75-316
StatusPublished
Cited by31 cases

This text of 346 N.E.2d 494 (Rivenbark v. Finis P. Ernest, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rivenbark v. Finis P. Ernest, Inc., 346 N.E.2d 494, 37 Ill. App. 3d 536, 1976 Ill. App. LEXIS 2219 (Ill. Ct. App. 1976).

Opinion

Mr. JUSTICE CARTER

delivered the opinion of the court:

This appeal arises out of a bench trial of the present contract action and consolidated cases involving mechanics’ liens concerning material and for labor supplied to defendant-appellant, a general contractor, or his subcontractors on a St. Clair County Housing Authority construction project. Defendant herein entered into a written contract on May 11, 1971, with plaintiff, a drywall contractor, wherein plaintiff agreed to furnish labor and materials for construction of buildings of various types in the housing project. The total contract price was *218,632.59, which was computed by first multiplying the unit price per building type by the number of buildings of that type to be completed and then taking the sum of these products plus extras. On November 9,1972, plaintiff filed a two-count complaint against defendant, alleging that defendant owed plaintiff *31,828.44 for labor and materials supplied pursuant to the contract and *25,000 for loss of anticipated profits. Plaintiff asserted that defendant wrongfully refused to permit plaintiff to complete the contract. A trial resulted in a verdict of *52,595.24 (*31,210.24 for labor and materials already supplied by plaintiff under the contract and *22,385 for lost profits) plus interest from November 9, 1972, and interest of *530 on plaintiff’s note payable to Belleville National Savings Bank. It is from the judgment entered on the verdict and the denial of post-trial motions that this appeal is taken.

The record indicates that the plaintiff has received *16,040.56 in partial satisfaction of the judgment. This amount has been used to recompense several lienholders for materials supplied to plaintiff on the project. These lienholders were parties in the portion of the consolidated cause not the subject of this appeal.

The defendant-appellant presents the following questions for review: (1) whether the trial court erred in awarding damages for lost profits that plaintiff would have realized had he completed his contract; (2) whether plaintiff’s failure to produce certain documents requested in a discovery motion was prejudicial to defendant; (3) whether the amount awarded plaintiff as damages on past due interest was excessive; (4) whether the amount awarded for labor and material was excessive.

Contrary to his position in the trial court, defendant on appeal concedes that he materially breached the contract in question. Plaintiff, who was forced to stop work because of defendant’s breach before substantial performance of the instant contract, thus properly elected to seek recovery based upon protection of the present value of his expected profits as well as upon expenses already incurred. By the term “profits” we mean the net amount that would have been made by the plaintiff had there been full performance. We do not define “profits” to mean the contract price less the cost of completion, for under the instant circumstances the allowance of expenditures in addition thereto would result in a double recovery for plaintiff. See Izzo v. City of Loves Park, 20 Ill. App. 2d 117; 22 Am. Jur. 2d Damages §160, at 229-30 (1965).

Defendant initially contends that the trial court erroneously awarded lost profits.

There are three general principles which courts apply to determine when lost profits will be allowed as compensation in contract cases. Lost profits will be allowed only if (1) their loss is proved with a reasonable degree of certainty (United States v. Penn Foundry & Manufacturing Co., 337 U.S. 198, 93 L. Ed. 1308, 69 S. Ct. 1009 (1949); Billeter v. Halsam Products Co., 313 Ill. App. 145; (2) the court is satisfied that the wrongful act of the defendant caused the loss of profits (Garden City Sand Co. v. Southern Fire Brick & Clay Co., 260 Ill. 231; and (3) the profits were reasonably within the contemplation of the defaulting party at the time the contract was entered into (Flug v. Craft Manufacturing Co., 3 Ill. App. 2d 56). (22 Am. Jur. 2d Damages §§ 171, 174, at 242, 246-48 (1965).) When the profits which are sought are those arising out of the breached contract, those profits are considered one of the elements of the contract, and are presumed to have been within the contemplation of the defaulting party at the time he entered into the contract; they are recoverable if proved with reasonable certainty. However, when the profits sought are those which would have arisen only out of a coUateral transaction, not only must these profits be proved with reasonable certainty, but also it must be shown that they were reasonably made within the contemplation of the defaulting party when the contract was made. (H.G. Holloway & Bro. v. White-Dunham Shoe Co., 151 F. 216 (7th Cir. 1906).) Notice of the possible existence of collateral profits, given after execution of the contract, will not satisfy this requirement. Cramer v. Grand Rapids Show Case Co., 223 N.Y. 63, 119 N.E.227 (1918); Macchia v. Megow, 355 Pa. 265, 50 A.2d 314 (1947).

Prospective profits recoverable are limited to those which might have been made pursuant to the performance of the particular contract sued on and during the period for which it was to run. The net profits lost by breach of contract are ascertained by deducting from the contract price those expenses necessary for full compliance on the plaintiffs part. (Sokoloff v. Highway Steel Products Co., 335 Ill. App. 573, 82 N.E.2d 509 (abstract opinion).) Problems with this calculation arise in relation to the cost of performance. Since plaintiffs direct cost of performance is often, as here, avoided by the defendant’s breach, the general rule is that direct costs (such as labor and materials) are to be deducted from the contract price, these costs being determined by what the plaintiff would have had to pay and not what they would have cost someone else. Annot., 50 A.L.R. 1397 (1927); 22 Am. Jur. 2d Damages §178, at 254-55 (1965).

The problem of plaintiff’s indirect costs appears to be one of first impression in Illinois. Courts of other jurisdictions have had difficulty with this problem.

“Some cases take the position that indirect costs — such as rent, salary of office employees, salary of administrative personnel, utilities, and other “overhead” items — are a part of the cost of production, and deduct them from the contract price to determine the net profit recovery. This result is often reached without discussion on the court’s part, indicating that counsel did not press the problem during trial. To the extent that the breach of contract allows the plaintiff an opportunity to enter into other contracts which now bear the same portion of the indirect costs as were to be borne by the breached contract, these cases are simply an expression of the doctrine of avoidable consequences. However, if the indirect costs are of the type which cannot be reduced following the breach, and if the plaintiff could have entered into further contracts even though the defendant had not breached the contract, then the fact that the plaintiff did not enter into contracts after the defendant’s breach does not lessen or eliminate the plaintiff’s indirect costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Otto Baum Co. v. Süd Family Ltd. Partnership
2020 IL App (3d) 190054 (Appellate Court of Illinois, 2021)
Lake in Hills Aviation Group, Inc. v. Village of Lake in Hills
698 N.E.2d 163 (Appellate Court of Illinois, 1998)
Roboserve, Inc. v. Kato Kagaku Co., Ltd.
873 F. Supp. 1124 (N.D. Illinois, 1995)
Carlson v. City Construction Co.
606 N.E.2d 400 (Appellate Court of Illinois, 1992)
Milex Products, Inc. v. Alra Laboratories, Inc.
603 N.E.2d 1226 (Appellate Court of Illinois, 1992)
Wilmette Partners v. Hamel
594 N.E.2d 1177 (Appellate Court of Illinois, 1992)
Stanley Gudyka Sales Co. v. Lacy Forest Products Co.
915 F.2d 273 (Seventh Circuit, 1990)
Madigan Bros. v. Melrose Shopping Center Co.
556 N.E.2d 730 (Appellate Court of Illinois, 1990)
Cencula v. Keller
536 N.E.2d 93 (Appellate Court of Illinois, 1989)
Gordon v. Bauer
532 N.E.2d 855 (Appellate Court of Illinois, 1988)
Panno v. Nicolau
529 N.E.2d 95 (Appellate Court of Illinois, 1988)
Madison Associates v. Bass
511 N.E.2d 690 (Appellate Court of Illinois, 1987)
Vranas & Associates, Inc. v. Family Pride Finer Foods, Inc.
498 N.E.2d 333 (Appellate Court of Illinois, 1986)
Midland Hotel Corp. v. Reuben H. Donnelley Corp.
501 N.E.2d 1280 (Appellate Court of Illinois, 1986)
Mohr v. Dix Mutual County Fire Insurance
493 N.E.2d 638 (Appellate Court of Illinois, 1986)
Central Information Financial Services, Ltd. v. First National Bank
471 N.E.2d 992 (Appellate Court of Illinois, 1984)
Cen. Info. Fin. Serv. v. First Nat'l Bk
471 N.E.2d 992 (Appellate Court of Illinois, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
346 N.E.2d 494, 37 Ill. App. 3d 536, 1976 Ill. App. LEXIS 2219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rivenbark-v-finis-p-ernest-inc-illappct-1976.