Wilmette Partners v. Hamel

594 N.E.2d 1177, 230 Ill. App. 3d 248, 171 Ill. Dec. 657
CourtAppellate Court of Illinois
DecidedMay 4, 1992
Docket1-90-2449
StatusPublished
Cited by52 cases

This text of 594 N.E.2d 1177 (Wilmette Partners v. Hamel) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilmette Partners v. Hamel, 594 N.E.2d 1177, 230 Ill. App. 3d 248, 171 Ill. Dec. 657 (Ill. Ct. App. 1992).

Opinion

PRESIDING JUSTICE BUCKLEY

delivered the opinion of the court:

In August and September 1987, plaintiff Wilmette Partners, Ltd. (Wilmette), contracted with Russ Hamel, d/b/a Russ’s Construction and Excavating (Hamel), for Hamel to perform demolition and excavation services on improved property which Wilmette owned in the Village of Wilmette. A dispute arose regarding Hamel’s performance of the demolition contract, which Hamel never completed. Another contractor subsequently completed the remaining demolition work and excavated the property.

Wilmette instituted this action against Hamel for breach of the demolition contract. Hamel counterclaimed against Wilmette and others (defendants) seeking foreclosure of his mechanic’s lien, damages, contractual interest and attorney fees for defendants’ breach of the demolition contract, and damages for defendants’ anticipatory repudiation of the excavation contract.

After a bench trial, the circuit court of Cook County found that Wilmette had breached the demolition contract and anticipatorily repudiated the excavation contract. The court thereafter entered judgment against Wilmette on its complaint; awarded a mechanic’s lien in favor of Hamel in the amount of $18,400 plus costs and interest from the date of contract; entered judgment in favor of Hamel in the amount of $34,300 for Wilmette’s breach of the excavation contract; and entered judgment in favor of Hamel in the amount of $7,500 for attorney fees incurred by Hamel through June 21,1990.

Wilmette appeals alleging numerous contentions, all of which turn on the issue of whether the manifest weight of the evidence supports the court’s findings of fact on whose conduct amounted to breach of contract. Hamel cross-appeals, alleging: (1) the circuit court erred when it failed to enter judgment on Hamel's count II, which sought in personam damages and contractual interest for breach of the demolition contract; and (2) this court must remand to the circuit court for an award of additional attorney fees to Hamel for having to respond to Wilmette’s appeal.

Wilmette is a general partnership with Richard Keefe as general partner and James Allen, among others, as limited partners. Wilmette is the sole beneficiary of a land trust with the La Salle National Bank. The corpus of the trust is three 50-foot lots at 724-726 12th Street in the Village of Wilmette. Hamel is an excavation contractor with seven years’ experience in the demolition and excavation field.

Wilmette planned to build a 39-unit condominium building on the property. On August 28, 1987, Hamel and Wilmette entered a written contract in which Hamel agreed to excavate the foundation for the new building and Wilmette agreed to pay $105,000.

On September 8, 1987, Hamel and Wilmette entered a second contract in which Hamel agreed to demolish two existing structures on the property and remove their foundations. The demolition contract required Wilmette to pay Hamel a total of $35,000, with $17,500 payable upon “demolition of [the] structure^] and removal of substantial amount of brick.” Significantly, the demolition contract contained no provisions regarding a commencement or completion date and the contract did not contain any clause stating that “time was of the essence.” Other relevant provisions of the demolition contract included the following: (1) an allowance of attorney fees to Hamel for having to enforce the contract; (2) a 2% monthly service charge in favor of Hamel for “past due amounts” owed by Wilmette to Hamel; (3) completion dates being contingent upon events that were beyond Hamel’s control (a “force majeure” clause); and (4) the allowance of additional labor charges if “area to be excavated is beyond normal conditions.”

On September 9, 1987, Hamel began work under the demolition contract. Hamel testified that he pulled the outside brick from the buildings and assisted a brick company in salvaging the bricks. He next pulled the two structures down and hauled the material away. The record reflects that, in accordance with the demolition contract’s divisibility provision, Hamel received $17,500 at or about this stage of Hamel’s performance.

Both parties’ witnesses testified that Hamel next removed the existing structures’ concrete floors or slabs. The witnesses also agree that Hamel removed two subterranean walls totaling 145 feet in length. The parties are in dispute as to what demolition work Hamel performed beyond this.

Hamel testified that after removing the existing structures’ slabs, he encountered two previously unknown, subterranean concrete floors or slabs. One slab measured 90 by 50 feet, the second measured 75 by 50 feet, and both were about five inches thick. Upon removal of these slabs, Hamel discovered two previously unknown, subterranean concrete walls totaling 125 feet in length. Hamel also discovered that one of the known foundational walls, which ran between two of the lots for their entire length (about 200 feet), was an oversized wall in that it was four to five feet thick and deep.

Hamel testified that he brought his discoveries to the attention of Allen. Hamel and Allen discussed the structures and agreed that they had to be removed. Hamel could not give Allen a price for their removal at the time because he did not know how much effort their removal would take. Hamel did state to Allen that he would be reasonable about price. Hamel claimed that he removed these structures and that $3,500 represented a fair, reasonable and customary charge for all the extras he performed. Hamel provided no breakdown for this figure other than stating in general how he reached it.

Regarding what extra walls and slabs Hamel discovered, Wilmette’s position is not entirely clear from the evidence. It admits Hamel discovered at least one slab and the extra thick wall. It also admits Hamel discovered yet another, entirely different subterranean wall, approximately 100 feet in length. Wilmette apparently disputes any discovery beyond this although Keefe acknowledges that a dairy previously existed on the property.

Regarding an agreement to perform extras, Wilmette denies that any agreement was reached at the property for Hamel to perform removal of the previously unknown walls and slabs. In this regard, Allen testified that, while he was present at the site on a daily basis, he could not recollect any conversation with Hamel regarding “extras.” Keefe, who visited the site on a daily basis, generally denies that an agreement at the site was reached between Hamel and Allen regarding extras.

On October 14, 1987, a meeting occurred between Hamel, Keefe, Phillip DiMaso, 1 the project’s general contractor, and James Williams, the job superintendent, regarding Hamel’s performance under the demolition contract. The parties’ testimony again conflicts as to what transpired during this meeting.

The testimony of Keefe, DiMaso and Williams regarding what transpired during this meeting can be viewed as paralleling a “confirmatory” letter which Keefe sent to Hamel following the meeting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pinkert v. Boardwalk Birch Companies, LLC.
2023 IL App (1st) 221953-U (Appellate Court of Illinois, 2023)
Health Care Service Corp. v. Walgreen Co.
2023 IL App (1st) 230547 (Appellate Court of Illinois, 2023)
Vista North Condominium Assoc. v. Hispanic Housing Development Corp.
2023 IL App (1st) 211161-U (Appellate Court of Illinois, 2023)
A+ Home Improvement Co. v. Ramos
2022 IL App (2d) 210770-U (Appellate Court of Illinois, 2022)
John Franklin & Dorothy Bickmore Living Trust v. Nanavati
2020 IL App (2d) 190710 (Appellate Court of Illinois, 2020)
Performance Food Group, Inc. v. Ariva Hospitality, Inc.
2020 IL App (3d) 190409 (Appellate Court of Illinois, 2020)
Northwestern Memorial Hospital v. Sharif
2014 IL App (1st) 133008 (Appellate Court of Illinois, 2014)
In re: F.P.
2014 IL App (4th) 140360 (Appellate Court of Illinois, 2014)
Doornbos Heating & Air Conditioning, Inc. v. Schlenker
932 N.E.2d 1073 (Appellate Court of Illinois, 2010)
Moede v. POCHTER
701 F. Supp. 2d 997 (N.D. Illinois, 2009)
O'Connor Construction Co. v. Belmont Harbor Home Development, LLC
909 N.E.2d 294 (Appellate Court of Illinois, 2009)
In Re Marriage of Tabassum and Younis
881 N.E.2d 396 (Appellate Court of Illinois, 2007)
In re Marriage of Tabassum
Appellate Court of Illinois, 2007
In Re Arlington Hospitality, Inc.
368 B.R. 702 (N.D. Illinois, 2007)
Erlenbush v. Largent
Appellate Court of Illinois, 2004
Busse v. Paul Revere Life Insurance
793 N.E.2d 779 (Appellate Court of Illinois, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
594 N.E.2d 1177, 230 Ill. App. 3d 248, 171 Ill. Dec. 657, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilmette-partners-v-hamel-illappct-1992.