Bulley & Andrews, Inc. v. Symons Corp.

323 N.E.2d 806, 25 Ill. App. 3d 696, 1975 Ill. App. LEXIS 3638
CourtAppellate Court of Illinois
DecidedJanuary 23, 1975
Docket59523
StatusPublished
Cited by26 cases

This text of 323 N.E.2d 806 (Bulley & Andrews, Inc. v. Symons Corp.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bulley & Andrews, Inc. v. Symons Corp., 323 N.E.2d 806, 25 Ill. App. 3d 696, 1975 Ill. App. LEXIS 3638 (Ill. Ct. App. 1975).

Opinion

Mr. PRESIDING JUSTICE McGLOON

delivered the opinion of the court:

Plaintiff, Bulley & Andrews, Inc., a general contractor, brought this action against defendant, Symons Corporation, to recover damages for contract extras, enforcement of its mechanic’s lien, and damages for defendant’s fraudulent misrepresentation. The circuit court of Cook County declared a mechanic’s lien and entered judgment in favor of plaintiff for some, but not all, of its claimed extras. Also, plaintiff’s fraudulent misrepresentation count was dismissed. On appeal, plaintiff alleges that the trial court erred by entering judgment in favor of defendant on plaintiff’s claim for extras resulting from owner ordered work, and on plaintiff’s fraudulent misrepresentation count. Defendant cross-appeals, alleging error in the judgment and mechanic’s lien entered against it.

We affirm.

The record reveals that the defendant, Symons Corporation, was in the business of designing and manufacturing concrete forming equipment. On August 8,1968, Symons contracted with Bulley & Andrews, Inc., a general contractor, for Bulley & Andrews to build an office and factory addition which provided for vast amounts of architectural concrete work to be done. The specifications incorporated into the contract stated that all forming equipment “will be furnished by Symons Manufacturing Company to the contractor from his standard catalog items, a copy of which is attached to this specification.” By way of explanation, forming equipment consists of those items which may be assembled together to form or create a mold into which wet concrete may be poured. This case is concerned with two particular types of forming equipment, form tie rods and rustication strips. The form rod is a metal rod inserted through holes in both forms and secured on the outside of each form so as to hold the forms together and give the resulting concrete a uniform thickness. The concrete is poured over the ties, allowed to set, and when the forms are removed the protruding ends of the ties are snapped off. The rustication strip is a piece of metal attached to the inside of the form to create a design on the' completed concrete wall.

Bulley & Andrews began work, and when it was ready to begin putting together the forms, its field superintendent, Richard Braun, asked Symons’ supervisor for the forming equipment to be used. Symons provided the forming equipment, and therein began the basis for this litigation. Bulley & Andrews’ position was that it thought the contract called for the use of the standard looped tie rods, a type of tie rod with loops at each end so the tie may be inserted through the forms and locked in place by simply slipping a wedge bolt into each loop. Accordingly, Bulley & Andrews’ personnel testified at trial that they prepared the contractor’s bid based upon the use of the easy-to-use looped ties Bulley & Andrews had been purchasing from Symons for the past 20 years. The tie rods supplied, however, were not the standard looped tie rods; Symons supplied threaded tie rods. Threaded tie rods serve the same function as the looped tie rods, but instead of having loops on both ends, one end of the rod is threaded to accept a securing nut. The threaded tie rod is pictured in Symons’ catalog as being appropriate for special uses, and the Symons’ supervisor explained to Braun that tihe threaded tie was to be used to enhance the final appearance of the concrete walls by reducing grout leakage. Also, Symons furnished a slightly different type of rustication strip than was pictured in its catalog.

Braun accepted the tendered threaded ties and the different rustication strips, and Bulley & Andrews began the forming. Braun neglected, however, to inform his office what type of forming equipment was received. The work took considerably longer to complete than was originally expected. Representatives from both Bulley & Andrews and Symons were at the site regularly to observe the progress, but there is no evidence in the record to indicate that Bulley & Andrews notified Symons either orally or in writing that it was experiencing difficulties and additional costs due to the use of the threaded tie rods and different rustication strips. Nine months after substantially all the forming was completed, Bulley & Andrews figured out that the additional expenses incurred in forming were due to the use of the threaded tie rod and the different rustication strip. Symons was then notified of a claim for extras for this work, but Symons refused to pay because it was not notified of the claim earlier. Also, Bulley & Andrews presented Symons with claims for extra work performed in another part of the job, the yard storage area, and for a delay in the work occasioned by Symons’ architect. Symons refused to recognize these claims, too. Bulley & Andrews filed the instant lawsuit.

The case was heard at a bench trial, and the trial court made an express finding that the plaintiff incurred substantial expenses by the use of the different forming equipment, but that plaintiff could not recover the additional expenses from such work because the claim was not submitted until after the work was completed. Accordingly, judgment was entered for defendant on plaintiff’s claim for extras resulting from the use of the threaded tie rod and different rustication strip. On the fraud count, the court entered judgment for defendant. As to plaintiff’s claims for extras resulting from the work performed in the yard storage area and for the delay occasioned by defendant’s architect, the trial court entered judgment for plaintiff and declared a mechanic’s lien. Plaintiff appeals from the judgments entered in favor of the defendant. Defendant cross appeals from the judgment and mechanic’s lien entered against it.

On appeal, plaintiff contends that the trial court erred by refusing to allow compensation for the extra work necessitated by the defendant’s modification of the forming equipment. Specifically, plaintiff alleges that such compensation was recoverable as extras under the contract, and also as damages for defendant’s fraudulent misrepresentation.

For a contractor to recover additional compensation from an owner for extra work, the contractor must prove the essential elements of his case as set forth in Watson Lumber Co. v. Guennewig (1967), 79 Ill. App.2d 377, 226 N.E.2d 270. The contract must establish that (a) the work was outside the scope of his contract promises, (b) the extra work items were ordered by the owner, (c) the owner agreed to pay extra, either by his words or conduct, (d) the extras were not furnished by the contract as his voluntary act, and (e) the extra items were not rendered necessary by any fault of the contractor.

The parties differ as to whether the work in question was outside the scope of the contract. The contract stated that:

“All * * * form ties, form hardware, steel adjustable shores and metal rustication strips will be furnished by Symons Manufacturing Company to the contractor from his standard catalog items, a copy of which is attached to this specification.”

As for the ties, the catalog pictured both the standard loop tie rod and the threaded tie rod that was actually furnished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trogub v. Robinson
Appellate Court of Illinois, 2006
DeSantis v. Brauvin Realty Partners, Inc.
618 N.E.2d 548 (Appellate Court of Illinois, 1993)
Wilmette Partners v. Hamel
594 N.E.2d 1177 (Appellate Court of Illinois, 1992)
Blue Cross and Blue Shield v. WR Grace & Co.
781 F. Supp. 420 (D. South Carolina, 1991)
Cleveland Wrecking Co. v. Central National Bank
576 N.E.2d 1055 (Appellate Court of Illinois, 1991)
Duncan v. Cannon
561 N.E.2d 1147 (Appellate Court of Illinois, 1990)
Schackleton v. Federal Signal Corp.
554 N.E.2d 244 (Appellate Court of Illinois, 1989)
Mitchell Buick & Oldsmobile Sales, Inc. v. National Dealer Services, Inc.
485 N.E.2d 1281 (Appellate Court of Illinois, 1985)
Havoco of America, Ltd. v. Hilco, Inc.
731 F.2d 1282 (Seventh Circuit, 1984)
Thread & Gage Co., Inc. v. Kucinski
451 N.E.2d 1292 (Appellate Court of Illinois, 1983)
Kaiser v. Olson
435 N.E.2d 113 (Appellate Court of Illinois, 1982)
Vance Pearson, Inc. v. Alexander
408 N.E.2d 782 (Appellate Court of Illinois, 1980)
Adams Laboratories, Inc. v. Jacobs Engineering Co.
486 F. Supp. 383 (N.D. Illinois, 1980)
Rao v. Parvathaneni
390 N.E.2d 496 (Appellate Court of Illinois, 1979)
Mother Earth, Ltd. v. Strawberry Camel, Ltd.
390 N.E.2d 393 (Appellate Court of Illinois, 1979)
Winn v. Turner
371 N.E.2d 170 (Appellate Court of Illinois, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
323 N.E.2d 806, 25 Ill. App. 3d 696, 1975 Ill. App. LEXIS 3638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bulley-andrews-inc-v-symons-corp-illappct-1975.