Shackelford Plumbing v. Siebe Govt Contr Div

Court of Appeals for the Fifth Circuit·Decided November 8, 2000·No. 99-60747·Unpublished

Opinion

UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT

No. 99-60747

SHACKELFORD PLUMBING CORPORATION, Plaintiff-Appellee,

versus

SIEBE GOVERNMENT CONTRACTS DIVISION, A SIEBE ENVIRONMENTAL CONTROLS GROUP, DIVISION OF BARBER-COLMAN COMPANY,

Defendant-Appellant.

Appeal from the United States District Court for the Southern District of Mississippi (3:98-CV-463(B)(N))

November 7, 2000

Before WOOD,1 DAVIS, and BARKSDALE, Circuit Judges. PER CURIAM:2 At issue is waiver vel non of contractual requirements for written change orders and timely claim submittals. Shackelford Plumbing Corporation filed this diversity action against Siebe Government Contracts Division of the Barber-Colman Company for 14 claims arising at eight military facilities in the United States. The district court granted Siebe summary judgment on one claim. A jury found for Siebe on two claims and for Shackelford on the

1 Harlington Wood, Jr., Circuit Judge of the Seventh Circuit, sitting by designation.

2 Pursuant to 5TH CIR. R. 47.5, the Court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4.

remaining 11. Siebe contests the denial of judgment as a matter of law as to five claims involving four sites. Alternatively, it challenges a jury instruction and requests a new trial for all but one of those five claims. We AFFIRM in PART, REVERSE and RENDER in PART, and REMAND FOR ENTRY OF AN AMENDED JUDGMENT.

I.

Siebe contracted with the Government to perform work at military installations (FORSCOM contracts) and hospitals (MEDCOM contracts). Shackelford was a subcontractor for those contracts. The contracts were “indefinite quantity contracts”, meaning the master subcontracts had zero dollars value. As the Government and Siebe agreed on delivery orders, Siebe issued delivery orders, complete with pricing, to Shackelford. Shackelford completed over $4 million in work for Siebe on 11 delivery orders.

The two master subcontracts between Siebe and Shackelford contained identical provisions regarding changes in the work required by the delivery orders. Prior to the beginning of such changed work, Siebe was required to give Shackelford written notice of the change; Shackelford, to submit a written estimate to Siebe. Paragraph 5.2 provided:

The Subcontractor [Shackelford] may be ordered in writing by the Contractor [Siebe] without invalidating this Subcontract, to make changes in the Work within the general scope of this Subcontract consisting of additions, deletions, or other revisions,....

[Shackelford], prior to the commencement of such changed or revised Work, shall submit promptly to [Siebe] written copies of an estimate for adjustment to the Subcontract Sum and Subcontract Time for such revised Work in a manner consistent with requirements of the Subcontract Documents.

(Emphasis added; footnotes omitted.) Testimony at trial focused not on Shackelford’s failure to submit a prior estimate but on work done without a prior written change order.

Shackelford’s contracts with Siebe incorporated provisions of Siebe’s contracts with the Government. Under them, Siebe had specified times within which to submit a claim to the Government after the cost was incurred. Along this line, Shackelford was required to provide timely claim submittal to Siebe for additional costs, including claims for delay damages. Paragraph 5.3 provided:

The Subcontractor [Shackelford] shall make claims promptly to the Contractor [Siebe] for additional cost, extensions of time and damages for delays or other causes in accordance with the Subcontract Documents. A claim which will affect or become part of a claim which [Siebe] is required to make under the Prime Contract within a specified time period or in a specified manner shall be made in sufficient time to permit [Siebe] to satisfy the requirements of the Prime Contract. Such claims shall be received by [Siebe] not less than two working days preceding the time by which [Siebe’s] claims must be made. Failure of [Shackelford] to make such a timely claim shall bind [Shackelford] to the same consequences as those to which [Siebe] is bound.

(Emphasis added.) The parties do not dispute that the post-work claim submittal had to be in writing.

II.

In defense of its refusal to pay Shackelford’s claims, Siebe points to the absence of prior written change orders and to Shackelford’s failure to submit several claims in the time and manner required. Shackelford counters that Siebe waived those requirements.

Pursuant to the choice of law clauses in the contracts, Illinois law governs. Under it, and regarding paragraph 5.2 (changes in the work), a provision in a construction contract that requires change orders to be in writing is valid. Watson Lumber Co. v. Guennewig, 226 N.E.2d 270, 276 (Ill. 1967). To prove a waiver of a writing requirement for such changes, Shackelford must demonstrate by clear and convincing evidence: “(a) the work was outside the scope of [the] contract promises; (b) the extra items were ordered by [Siebe], (c) [Siebe] agreed to pay extra, either by [] words or conduct, (d) the extras were not furnished by [Shackelford] as [a] voluntary act, and (e) the extra items were not rendered necessary by any fault of [Shackelford]”. Id. (emphasis added and citations omitted); id. (“Where the contract provides that there shall be no charge for extra work unless a written agreement is made therefor, the builder cannot recover compensation as for extra work on account of alterations made at the oral request or consent of the owner but for which no agreement to pay additional compensation is made.” (emphasis added; internal quotation marks and citation omitted)).

“Clear and convincing evidence is that quantum of proof that leaves no reasonable doubt in the mind of the fact finder as to the truth of the proposition [stated].” City of Chicago v. Boulevard Bank Nat’l Assoc., 688 N.E.2d 844, 852 (Ill. App. Ct. 1997) (emphasis added; internal quotation marks and citation omitted).

The Watson court also stated:

Illinois cases allow recovery for extra compensation only when the contractor has made his claim for an extra, clear and certain,

before furnishing the item, not after.... If he does expressly contend that work demanded is extra, the owner certainly cannot be said to be taken unawares, and if orders are given to go ahead it is with full knowledge of the possible consequences.

226 N.E.2d at 279 (emphasis added; internal quotation marks and citation omitted).

Although Watson stated the claim must be “clear and certain”, the contract at issue in Watson simply required that, pre-work, the fact of the change be in writing, not addressing whether the amount likewise must be in writing. Id. at 274. In Bulley & Andrews, Inc. v. Symons Corp., 323 N.E.2d 806 (Ill. App. Ct. 1975), an Illinois court applied Watson to a contract with a clause similar to paragraph 5.2, which required written notice of the value of the claim, not only of the change itself:

It is incumbent upon the owner to enforce the “extras” provision in his contract, or it is waived by him. By allowing work on extras to proceed before securing a memorandum signed by [the contractor, the owner] waived his right to enforce the provision. A contractual provision such as in this case prevents the contractor from proceeding with extra work on his own initiative, while allowing the owner to control his liabilities. When an owner orders work to proceed, he cannot claim to be taken unaware, nor can he require the contractor to bear the cost of the work he has so ordered.

Id. at 811-12 (internal quotation marks omitted); see id. (finding even though “[t]he estimate [for work ordered by the owner] was not submitted ... until three months after the ... work was completed”, because owner allowed work to proceed before securing necessary writing, it waived contractual provision (emphasis added)).

Free access — add to your briefcase to read the full text and ask questions with AI

Shackelford Plumbing v. Siebe Govt Contr Div, (5th Cir. 2000).

Shackelford Plumbing v. Siebe Govt Contr Div (Shackelford Plumbing v. Siebe Govt Contr Div) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Omnitech International, Inc. v. Clorox Co.
11 F.3d 1316 (Fifth Circuit, 1994)
Johnson v. Sawyer,et al
120 F.3d 1307 (Fifth Circuit, 1997)
Williams v. Wal-Mart Stores Inc
188 F.3d 278 (Fifth Circuit, 1999)
City of Chicago v. Boulevard Bank National Ass'n
688 N.E.2d 844 (Appellate Court of Illinois, 1997)
Watson Lumber Co. v. Guennewig
226 N.E.2d 270 (Appellate Court of Illinois, 1967)
A.W. Wendell & Sons, Inc. v. Qazi
626 N.E.2d 280 (Appellate Court of Illinois, 1993)
Bulley & Andrews, Inc. v. Symons Corp.
323 N.E.2d 806 (Appellate Court of Illinois, 1975)
Duncan v. Cannon
561 N.E.2d 1147 (Appellate Court of Illinois, 1990)
Hill v. International Paper Co.
121 F.3d 168 (Fifth Circuit, 1997)