Shackelford Plumbing v. Siebe Govt Contr Div

Court of Appeals for the Fifth Circuit·Decided November 8, 2000·No. 99-60747·Unpublished

Opinion

UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT

No. 99-60747

SHACKELFORD PLUMBING CORPORATION,

Plaintiff-Appellee,

versus

SIEBE GOVERNMENT CONTRACTS DIVISION, A SIEBE ENVIRONMENTAL CONTROLS GROUP, DIVISION OF BARBER-COLMAN COMPANY,

Defendant-Appellant.

Appeal from the United States District Court for the Southern District of Mississippi (3:98-CV-463(B)(N))

November 7, 2000

Before WOOD,1 DAVIS, and BARKSDALE, Circuit Judges.

PER CURIAM:2

At issue is waiver vel non of contractual requirements for

written change orders and timely claim submittals. Shackelford

Plumbing Corporation filed this diversity action against Siebe

Government Contracts Division of the Barber-Colman Company for 14

claims arising at eight military facilities in the United States.

The district court granted Siebe summary judgment on one claim. A

jury found for Siebe on two claims and for Shackelford on the

1 Harlington Wood, Jr., Circuit Judge of the Seventh Circuit, sitting by designation. 2 Pursuant to 5TH CIR. R. 47.5, the Court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4. remaining 11. Siebe contests the denial of judgment as a matter of

law as to five claims involving four sites. Alternatively, it

challenges a jury instruction and requests a new trial for all but

one of those five claims. We AFFIRM in PART, REVERSE and RENDER in

PART, and REMAND FOR ENTRY OF AN AMENDED JUDGMENT.

I.

Siebe contracted with the Government to perform work at

military installations (FORSCOM contracts) and hospitals (MEDCOM

contracts). Shackelford was a subcontractor for those contracts.

The contracts were “indefinite quantity contracts”, meaning the

master subcontracts had zero dollars value. As the Government and

Siebe agreed on delivery orders, Siebe issued delivery orders,

complete with pricing, to Shackelford. Shackelford completed over

$4 million in work for Siebe on 11 delivery orders.

The two master subcontracts between Siebe and Shackelford

contained identical provisions regarding changes in the work

required by the delivery orders. Prior to the beginning of such

changed work, Siebe was required to give Shackelford written notice

of the change; Shackelford, to submit a written estimate to Siebe.

Paragraph 5.2 provided:

The Subcontractor [Shackelford] may be ordered in writing by the Contractor [Siebe] without invalidating this Subcontract, to make changes in the Work within the general scope of this Subcontract consisting of additions, deletions, or other revisions,.... [Shackelford], prior to the commencement of such changed or revised Work, shall submit promptly to [Siebe] written copies of an estimate for adjustment to the Subcontract Sum and Subcontract Time for such revised Work in a manner consistent with requirements of the Subcontract Documents.

2 (Emphasis added; footnotes omitted.) Testimony at trial focused

not on Shackelford’s failure to submit a prior estimate but on work

done without a prior written change order.

Shackelford’s contracts with Siebe incorporated provisions of

Siebe’s contracts with the Government. Under them, Siebe had

specified times within which to submit a claim to the Government

after the cost was incurred. Along this line, Shackelford was

required to provide timely claim submittal to Siebe for additional

costs, including claims for delay damages. Paragraph 5.3 provided:

The Subcontractor [Shackelford] shall make claims promptly to the Contractor [Siebe] for additional cost, extensions of time and damages for delays or other causes in accordance with the Subcontract Documents. A claim which will affect or become part of a claim which [Siebe] is required to make under the Prime Contract within a specified time period or in a specified manner shall be made in sufficient time to permit [Siebe] to satisfy the requirements of the Prime Contract. Such claims shall be received by [Siebe] not less than two working days preceding the time by which [Siebe’s] claims must be made. Failure of [Shackelford] to make such a timely claim shall bind [Shackelford] to the same consequences as those to which [Siebe] is bound.

(Emphasis added.) The parties do not dispute that the post-work

claim submittal had to be in writing.

II.

In defense of its refusal to pay Shackelford’s claims, Siebe

points to the absence of prior written change orders and to

Shackelford’s failure to submit several claims in the time and

manner required. Shackelford counters that Siebe waived those

requirements.

3 Pursuant to the choice of law clauses in the contracts,

Illinois law governs. Under it, and regarding paragraph 5.2

(changes in the work), a provision in a construction contract that

requires change orders to be in writing is valid. Watson Lumber

Co. v. Guennewig, 226 N.E.2d 270, 276 (Ill. 1967). To prove a

waiver of a writing requirement for such changes, Shackelford must

demonstrate by clear and convincing evidence: “(a) the work was

outside the scope of [the] contract promises; (b) the extra items

were ordered by [Siebe], (c) [Siebe] agreed to pay extra, either by

[] words or conduct, (d) the extras were not furnished by

[Shackelford] as [a] voluntary act, and (e) the extra items were

not rendered necessary by any fault of [Shackelford]”. Id.

(emphasis added and citations omitted); id. (“Where the contract

provides that there shall be no charge for extra work unless a

written agreement is made therefor, the builder cannot recover

compensation as for extra work on account of alterations made at

the oral request or consent of the owner but for which no agreement

to pay additional compensation is made.” (emphasis added; internal

quotation marks and citation omitted)).

“Clear and convincing evidence is that quantum of proof that

leaves no reasonable doubt in the mind of the fact finder as to the

truth of the proposition [stated].” City of Chicago v. Boulevard

Bank Nat’l Assoc., 688 N.E.2d 844, 852 (Ill. App. Ct. 1997)

(emphasis added; internal quotation marks and citation omitted).

The Watson court also stated:

Illinois cases allow recovery for extra compensation only when the contractor has made his claim for an extra, clear and certain,

4 before furnishing the item, not after.... If he does expressly contend that work demanded is extra, the owner certainly cannot be said to be taken unawares, and if orders are given to go ahead it is with full knowledge of the possible consequences.

226 N.E.2d at 279 (emphasis added; internal quotation marks and

citation omitted).

Although Watson stated the claim must be “clear and certain”,

the contract at issue in Watson simply required that, pre-work, the

fact of the change be in writing, not addressing whether the amount

likewise must be in writing. Id. at 274. In Bulley & Andrews,

Inc. v. Symons Corp., 323 N.E.2d 806 (Ill. App. Ct. 1975), an

Illinois court applied Watson to a contract with a clause similar

to paragraph 5.2, which required written notice of the value of the

Free access — add to your briefcase to read the full text and ask questions with AI

Shackelford Plumbing v. Siebe Govt Contr Div, (5th Cir. 2000).

Shackelford Plumbing v. Siebe Govt Contr Div (Shackelford Plumbing v. Siebe Govt Contr Div) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Omnitech International, Inc. v. Clorox Co.
11 F.3d 1316 (Fifth Circuit, 1994)
Johnson v. Sawyer,et al
120 F.3d 1307 (Fifth Circuit, 1997)
Williams v. Wal-Mart Stores Inc
188 F.3d 278 (Fifth Circuit, 1999)
City of Chicago v. Boulevard Bank National Ass'n
688 N.E.2d 844 (Appellate Court of Illinois, 1997)
Watson Lumber Co. v. Guennewig
226 N.E.2d 270 (Appellate Court of Illinois, 1967)
A.W. Wendell & Sons, Inc. v. Qazi
626 N.E.2d 280 (Appellate Court of Illinois, 1993)
Bulley & Andrews, Inc. v. Symons Corp.
323 N.E.2d 806 (Appellate Court of Illinois, 1975)
Duncan v. Cannon
561 N.E.2d 1147 (Appellate Court of Illinois, 1990)
Hill v. International Paper Co.
121 F.3d 168 (Fifth Circuit, 1997)