Duncan v. Cannon

561 N.E.2d 1147, 204 Ill. App. 3d 160, 149 Ill. Dec. 451, 1990 Ill. App. LEXIS 1455
CourtAppellate Court of Illinois
DecidedSeptember 24, 1990
Docket1-88-3007
StatusPublished
Cited by13 cases

This text of 561 N.E.2d 1147 (Duncan v. Cannon) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duncan v. Cannon, 561 N.E.2d 1147, 204 Ill. App. 3d 160, 149 Ill. Dec. 451, 1990 Ill. App. LEXIS 1455 (Ill. Ct. App. 1990).

Opinion

JUSTICE MANNING

delivered the opinion of the court:

Defendant and counterplaintiff Lauretta Cannon (Defendant) appeals from the judgment of the circuit court in favor of plaintiff and counterdefendant (Plaintiff) in the amount of $9,600, which represents the unpaid contract price of $1,900 for work performed and $7,700 for “extra” work. Defendant raises three issues on appeal: (1) whether plaintiff was entitled to additional payment for alleged extra work; (2) whether plaintiff’s failure to file plans pursuant to the Chicago Building Code (Ordinance) precludes him from recovering for extra work; and (3) whether the circuit court erred in denying defendant’s request for a continuance.

The record reveals that defendant owns a three-flat apartment building in Chicago. In March 1986 defendant entered into a contract with plaintiff to modify the single boiler in the building, which heated all three apartments, by cutting it down to heat only the first floor. The original radiators were to remain on the first floor. Plaintiff was to install a new steam boiler to heat the third floor with the original radiators remaining, and a new hot water boiler to heat the second floor, which would be connected to new baseboard radiators. Pursuant to the contract, all three boilers were to be connected to separate gas meters. The contract price was listed as $5,900, which included all labor and materials.

Shortly thereafter, the parties entered into a second contract which modified their original agreement and stated:

“Building is a 3-flat building. Boiler is now heating the entire building. Present boiler will be cut down and only used for 1st floor and present radiators. Other 2 floors will be heated with 260,000 BTU boilers steam with lo-cut offs and automatic water feeders. Use present radiators and hook up all three boilers to separate gas meters. 3 gas meter connections. Price includes all labor and material and work to be done in a workmanlike manner.”

The contract amount was listed as $7,000, “one half xk down payment on delivery — balance to be paid on completion.”

After the work was completed, plaintiff brought this cause of action. Defendant asserted a number of affirmative defenses and filed a counterclaim alleging that plaintiff had performed faulty work.

On August 29, 1988, the case was set final for trial. However, on that date defense counsel presented an oral motion for a continuance on the ground that defendant’s expert witness was suddenly and unexpectedly unavailable. The trial court denied defendant’s motion and proceeded with trial. Following the trial, the court entered judgment on behalf of plaintiff on counts I and II of his complaint and judgment for the defendant on her counterclaim in the amount of $450.

We first address defendant’s argument that because the work in question was required by the original contract it could not be considered as extra work. In order for a contractor to recover additional payment from an owner for extra work, he must establish by clear and convincing evidence each of the essential elements in his case. He must establish that: (1) the work was outside the scope of the original contract; (2) the extra items were ordered at the direction of the owner; (3) the owner agreed either expressly or impliedly to pay extra; (4) the extra items were not voluntarily furnished by the contractor; and (5) the extra items were not rendered necessary by any fault of the contractor. (Watson Lumber Co. v. Guennewig (1967), 79 Ill. App. 2d 377, 389-90, 226 N.E.2d 270.) Moreover, our courts have continually reiterated that the proof that the items are extra, that the defendant ordered them as such and agreed to pay for them must be by clear and convincing evidence. R & R Construction Co. v. Junior College District No. 529 (1977), 55 Ill. App. 3d 115, 118, 370 N.E.2d 549, citing Guennewig, 79 Ill. App. 2d at 390; see also Athens v. Prousis (1989), 190 Ill. App. 3d 349, 356, 546 N.E.2d 695; Cencula v. Keller (1989), 180 Ill. App. 3d 645, 652, 536 N.E.2d 93; Ambrose v. Biggs (1987), 156 Ill. App. 3d 515, 520, 509 N.E.2d 614; Wingler v. Niblack (1978), 58 Ill. App. 3d 287, 289, 374 N.E.2d 252.

Defendant argues that plaintiff failed to establish by clear and convincing evidence that the work in question was extra. She urges that the trial' court’s judgment for plaintiff was against the manifest weight of the evidence.

It is well established that “clear and convincing evidence is considered to be more than a preponderance while not quite approaching the degree of proof necessary to convict a person of a criminal offense.” (In re Estate of Ragen (1979), 79 Ill. App. 3d 8, 14, 398 N.E.2d 198.) “The manifest weight of the evidence is that which is ‘the clearly evident, plain and indisputable weight of the evidence.’ [Citations.] In order for a finding to be contrary to the manifest weight of the evidence, an opposite conclusion must be clearly apparent. [Citation.]” In re Application of County Collector (1978), 59 Ill. App. 3d 494, 499, 375 N.E.2d 553.

At the trial below, 1 four witnesses testified. Plaintiff testified, inter alia, that the extra work included installation of 12 new steam pipe lines, which were run from the new boilers in the basement to 12 radiators in the second- and third-floor apartments, and work on the walls and floors of the premises to accommodate the lines; defendant orally requested the new steam lines and promised to pay for them; the work was outside the scope of the contract since it was always his intent to use the existing pipe lines to hook up the boilers to the radiators; he did not submit plans to the city because he did not believe the Ordinance applied to the job; and the boiler installation was subcontracted out to a third party.

Mr. Poulas, an expert witness for plaintiff, testified that he was not a licensed plumber but had been in the heating business in the Chicago area for over 35 years. He stated “that he did not know how many lines were run from the basement to the *** floors” but, “individual lines were run from the basement to the radiators in the second and third floor apartments.” However, Mr. Poulas offered no other testimony to establish that the work was extra, and what he did testify to was based on his visit to the second floor only.

Defendant testified on her counterclaim as to the faulty work provided by plaintiff as well as the case in chief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ashlaur Construction Co. v. The Levy Company
2023 IL App (1st) 210795-U (Appellate Court of Illinois, 2023)
Ritacca v. Girardi
2013 IL App (1st) 113511 (Appellate Court of Illinois, 2013)
K. MILLER CONST. CO., INC. v. McGinnis
938 N.E.2d 471 (Illinois Supreme Court, 2010)
Czapla v. Commerz Futures, LLC
114 F. Supp. 2d 715 (N.D. Illinois, 2000)
A.D. Powers v. Miller
1999 NMCA 080 (New Mexico Court of Appeals, 1999)
M.P. Kenes, Incorporated v. Technicote, Incorporated
36 F.3d 1099 (Seventh Circuit, 1994)
Mani Electrical Contractors v. Kioutas
611 N.E.2d 1167 (Appellate Court of Illinois, 1993)
Fitzwilliam v. 1220 Iroquois Venture
598 N.E.2d 1003 (Appellate Court of Illinois, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
561 N.E.2d 1147, 204 Ill. App. 3d 160, 149 Ill. Dec. 451, 1990 Ill. App. LEXIS 1455, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duncan-v-cannon-illappct-1990.