Ashlaur Construction Co. v. The Levy Company

2023 IL App (1st) 210795-U
CourtAppellate Court of Illinois
DecidedMay 30, 2023
Docket1-21-0795
StatusUnpublished

This text of 2023 IL App (1st) 210795-U (Ashlaur Construction Co. v. The Levy Company) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ashlaur Construction Co. v. The Levy Company, 2023 IL App (1st) 210795-U (Ill. Ct. App. 2023).

Opinion

2023 IL App (1st) 210795-U

SECOND DIVISION May 30, 2023

No. 1-21-0795

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________

IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT ______________________________________________________________________________

) ASHLAUR CONSTRUCTION COMPANY, ) Appeal from the Plaintiff-Appellant, ) Circuit Court of ) Cook County ) v. ) 18 CH 00580 ) THE LEVY COMPANY, ) Honorable Defendant-Appellee. ) James Snyder, ) Judge Presiding. ) _____________________________________________________________________________

JUSTICE ELLIS delivered the judgment of the court. Justices Howse and Cobbs concurred in the judgment.

ORDER

¶1 Held: Affirmed as modified. Court’s judgment for defendant on third-party beneficiary claim affirmed, as plaintiff did not establish elements of underlying breach of contract. Judgment denying plaintiff’s claim for “extras” compensation was not against manifest weight of evidence. Judgment in favor of plaintiff on quantum meruit claim affirmed but modified to correct mathematical error on calculation of damages.

¶2 Seeking to build a new marquee hotel at the McCormick Center complex in Chicago, the

Metropolitan Pier and Exposition Authority (MPEA) entered into a joint venture with several

large construction contractors. That joint venture subcontracted with defendant Levy Company

to perform work on the interior walls of the hotel. Levy in turn hired Ashlaur Construction, a

minority business enterprise (MBE), a sub-subcontractor and plaintiff here, to hang and tape No. 1-21-0795

drywall in the hotel. Ashlaur and Levy valued the contract between them at approximately $6.34

million, about half of which went to cover labor costs, the rest going to materials and Ashlaur’s

hiring of a subcontractor to install insulation.

¶3 But things did not go to plan—at least in Ashlaur’s opinion. It estimated that it would

take approximately 32,000 hours of labor to complete their part of the project. However, when

everything was done, Ashlaur’s president went back to Levy, said it had taken 47,000 hours of

work to complete the project and demanded more than $1 million in payment to cover those

unexpected costs.

¶4 When Levy refused, Ashlaur filed suit. The case went to a bench trial, where Ashlaur

argued three things. First, it claimed that, although Ashlaur was not a party to the contract

between the Joint Venture and Levy, it should be considered an intended third-party beneficiary

and thus allowed to sue for additional money it believed was owed to it as an MBE on the

project. Second, it argued that Levy was in breach of the Levy-Ashlaur contract because Levy

refused to pay for the additional hours it took to complete the job. Finally, Ashlaur sought relief

under quantum meruit, seeking recompence for the benefit of the extra work it bestowed on

Levy.

¶5 At the close of Ashlaur’s case, the court entered judgment for Levy on the first two

counts but eventually awarded Ashlaur about $110,000 in quantum meruit damages. For the

following reasons, we affirm the judgment in full but modify the award of damages to Ashlaur

on its quantum meruit claim to correct a mathematical error.

¶6 BACKGROUND

¶7 In the mid-2010s, MPEA commissioned a hotel to be built near the McCormick Center

campus in Chicago. MPEA and several large construction companies (none of whom are parties

-2- No. 1-21-0795

here) entered into a joint venture (JV). In March 2016, the Levy Company and the JV agreed to a

$12 million contract (which we will refer to as the JV-Levy contract) for Levy to construct the

interior walls of the hotel.

¶8 In Exhibit B of the JV-Levy Contract, the parties laid out what they expected to be the

process of the drywall work. Relevant here, the work was expected to “progress on two (2) floors

concurrently,” and the drywall in the guestrooms would “be completed in two (2) separate

sequences[.]”

¶9 The contract also included minority-inclusion obligations, requiring Levy to hire and use

MBEs for a portion of the work, in accordance with MPEA requirements. Specifically, the

relevant clause said: “Subcontractor shall provide the minimum MBE/WBE participation in

accordance with Appendix A of the Design Build Agreement: MBE 50%.” However, the

contract did not specify a particular MBE or otherwise detail how that 50 percent was to be

distributed. When Levy signed the contract with the JV, it had not identified the MBE or MBEs

it would use.

¶ 10 Levy began to search for an MBE and eventually picked Ashlaur. On May 20, 2016,

Levy and Ashlaur signed off on a $6 million contract (the Levy-Ashlaur contract). That contract

specified that Levy would pay Ashlaur approximately $3 million for the labor to hang and tape

drywall in the hotel and purchase the materials Ashlaur would use for $3 million.

¶ 11 The Levy-Ashlaur contract included a section titled “Work” that, coupled with an exhibit

that was incorporated into the contract, laid out the scope of the job, as well as the process by

which Levy and Ashlaur would address the need for extra work. As to the latter, the contract

said: “No extra work or changes under this Sub-subcontract will be recognized or paid for unless

agreed to in writing before the work is done or changes are made.”

-3- No. 1-21-0795

¶ 12 In the exhibit attached and adopted by the contact, the parties broke down the scope of

the work and added several “clarifications.” The parties expected that the materials—drywall,

steel, and blocking—would cost approximately $2.5 million. They added another $835,000 for

insulation, and Levy agreed to pay Ashlaur a service charge of $125,000 to manage the

materials. The exhibit estimated the hotel would require more than 3 million square feet of

hanging and another 2.1 million square feet of taping. The contract also budgeted $3 million for

the labor costs. In the clarifications section, the exhibit said that “[h]anging and taping square

footages that are enclosed are the basis for the agreed upon price.”

¶ 13 Work began, and Levy and Ashlaur (among many other contractors) began constructing

the walls on the 5th through 40th floors of the hotel. Since the project was ultimately paid for

and overseen by MPEA, a municipal corporation created by law, the project required any

contractor working on it to submit extensive documentation on such details as payments that

were made and work that was completed.

¶ 14 To document its progress, Ashlaur submitted standard construction schedule of values

(SOVs) each month. These SOVs included estimates on the completion percentage of particular

projects on individual floors and tasks, payroll records and proof of hours worked, and costs for

supplies and materials. Ashlaur was to complete the work in two sequences, hanging and taping

drywall on each floor. The first step was to finish the bathrooms, then move on to the guest

rooms and corridors. Each step was to be completed before Ashlaur moved onto the next floor.

¶ 15 However, it was common for Ashlaur to leave some work on individual floors unfinished

and move on because of various delays, mostly due to other work being done on the hotel. But

the parties anticipated as much, and Ashlaur would always return later to finish whatever needed

Free access — add to your briefcase to read the full text and ask questions with AI

Related

XL Disposal Corp. v. John Sexton Contractors Co.
659 N.E.2d 1312 (Illinois Supreme Court, 1995)
Thrall Car Manufacturing Co. v. Lindquist
495 N.E.2d 1132 (Appellate Court of Illinois, 1986)
People v. Johnson
803 N.E.2d 442 (Illinois Supreme Court, 2003)
People Ex Rel. Sherman v. Cryns
786 N.E.2d 139 (Illinois Supreme Court, 2003)
Kokinis v. Kotrich
407 N.E.2d 43 (Illinois Supreme Court, 1980)
Barnes v. Michalski
925 N.E.2d 323 (Appellate Court of Illinois, 2010)
Farwell Construction Co. v. Ticktin
405 N.E.2d 1051 (Appellate Court of Illinois, 1980)
Carlton at the Lake, Inc. v. Barber
928 N.E.2d 1266 (Appellate Court of Illinois, 2010)
Pedrick v. Peoria & Eastern Railroad
229 N.E.2d 504 (Illinois Supreme Court, 1967)
W. H. Lyman Construction Co. v. Village of Gurnee
403 N.E.2d 1325 (Appellate Court of Illinois, 1980)
Comm. v. Goodman
286 N.E.2d 758 (Appellate Court of Illinois, 1972)
Hayes Mechanical, Inc. v. First Industrial, L.P.
812 N.E.2d 419 (Appellate Court of Illinois, 2004)
Duncan v. Cannon
561 N.E.2d 1147 (Appellate Court of Illinois, 1990)
Benford v. Everett Commons, LLC.
2014 IL App (1st) 130314 (Appellate Court of Illinois, 2014)
Wiczer v. Wojciak
2015 IL App (1st) 123753 (Appellate Court of Illinois, 2015)
Carson Pirie Scott & Co. v. Parrett
178 N.E. 498 (Illinois Supreme Court, 1931)
Village of Belle Rive v. Illinois Central R.R. Co.
2018 IL App (5th) 170036 (Appellate Court of Illinois, 2018)
Jameson Real Estate, LLC v. Ahmed
2018 IL App (1st) 171534 (Appellate Court of Illinois, 2019)
Lyons Federal Trust & Savings Bank v. Moline National Bank
549 N.E.2d 933 (Appellate Court of Illinois, 1990)
Bank of Ravenswood v. Polan
256 Ill. App. 3d 470 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
2023 IL App (1st) 210795-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ashlaur-construction-co-v-the-levy-company-illappct-2023.