Lyons Federal Trust & Savings Bank v. Moline National Bank

549 N.E.2d 933, 193 Ill. App. 3d 108, 140 Ill. Dec. 282, 1990 Ill. App. LEXIS 19
CourtAppellate Court of Illinois
DecidedJanuary 10, 1990
DocketNos. 3—89—0066, 3—89—0136 cons.
StatusPublished
Cited by13 cases

This text of 549 N.E.2d 933 (Lyons Federal Trust & Savings Bank v. Moline National Bank) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lyons Federal Trust & Savings Bank v. Moline National Bank, 549 N.E.2d 933, 193 Ill. App. 3d 108, 140 Ill. Dec. 282, 1990 Ill. App. LEXIS 19 (Ill. Ct. App. 1990).

Opinion

JUSTICE SCOTT

delivered the opinion of the court:

Two separate appeals from the circuit court of Rock Island County have been consolidated for review. Both appeals involve the same parties and operative facts; however, the primary issues raised in each appeal are distinct.

A mortgage foreclosure action was brought in Rock Island County by Lyons Federal Trust & Savings Bank (Lyons) principally against George Guritz, Gerald Huge, Paul Murray and John Stevenson (Stevenson), d/b/a GHMS Real Estate Partnership (GHMS), as the beneficial owners of a land trust, wherein Lyons supplied financing for GHMS to build an apartment complex commonly known as Pebble Creek. Stevenson was subsequently determined bankrupt and dismissed as a defendant. Robert J. Wolfe, d/b/a Action Plumbing (Wolf), was included as a defendant in the action because of various electrical and plumbing services provided by Wolfe at Pebble Creek resulting in Wolfe recording a mechanic’s lien against the property. Wolfe then filed an intervening claim against GHMS and Lyons to foreclose on the mechanic’s lien and additionally filed a counterclaim against GHMS for alleged breach of oral contract to perform work at Pebble Creek. After a bench trial on Wolfe’s mechanic’s lien and breach of contract claims and hearing post-trial motions, the circuit court by order dated February 16, 1989, entered a judgment of $107,104.71 against GHMS on Wolfe’s breach of contract claim and denied judgment of Wolfe’s mechanic’s lien foreclosure based on Wolfe’s failure to give notice of the lien to Lyons as required by section 24 of the Mechanics’ Liens Act (Ill. Rev. Stat. 1987, ch. 82, par. 24). One appeal was initiated by GHMS, arguing the trial court erred in finding in favor of Wolfe on the breach of contract claim and, alternatively, that the award of damages was excessive. The second appeal was instituted by Wolfe based on the circuit court’s denial of its mechanic’s lien foreclosure action.

Lyons mortgage on Pebble Creek was recorded November 19, 1982. Wolfe’s mechanic’s lien was filed on February 23, 1984, and alleged that “on or about April 29, 1983, *** [Wolfe] *** made an oral contract with John Stevenson,” a former partner of GHMS. In Wolfe’s verified claim to foreclose on the mechanic’s lien, Wolfe first alleged that the oral contract inception date was April 29, 1983, and engaged Wolfe to do a variety of electrical and plumbing work on a “time and material basis.” Wolfe claimed to have completed the work on December 23, 1983, and a balance of $107,161.75 was owed under the contract. Wolfe was subsequently granted leave to amend the counterclaim and changed the alleged inception date of the oral agreement to August 23, 1982, rather than April 29, 1983. In its answer to the amended pleadings, GHMS admitted the existence of an oral agreement on August 23, 1982, but denied the terms encompassed all that Wolfe alleged and GHMS affirmatively alleged that all work performed under the August 23, 1982, contract had been paid for in full.

Only two witnesses testified at trial, Robert Wolfe and John Stevenson. The evidence centered primarily around the date and scope of the agreement entered into between Wolfe and Stevenson on August 23, 1982, the amount due Wolfe by Stevenson for work performed at Pebble Creek and the billing and payment practices of Wolfe and Stevenson.

GHMS APPEAL

The appeal of GHMS centers on the oral contract between Wolfe and Stevenson, as agent for GHMS. GHMS essentially claims that there were multiple contracts entered into between Wolfe and Stevenson, some of which were paid in full, and on others, partial payments were made. GHMS further claims that Wolfe was paid in full for the contract entered into on August 23, 1983, and therefore, GHMS was entitled to judgment for the contract entered into on that date. Wolfe, on the other hand, disagrees there was a succession of contracts and claims the terms of the contract entered into on August 23, 1982, were the cornerstone for all work performed by Wolfe at Pebble Creek. Wolfe alleged the August 23, 1982, contract set hourly rates for skilled and unskilled labor, set hourly rates for the use of certain equipment, and provided that Wolfe would do whatever Stevenson said to do on a time and material basis. The circuit court determined an oral contract existed.

GHMS makes two arguments as to why the circuit court erred in granting judgment in favor of Wolfe on the oral contract claim. First, GHMS argues that Wolfe’s sworn statement of mechanic’s lien and verified countercomplaint alleging the April 29, 1983, contract date are judicial admissions denying judgment as a matter of law or, alternatively, are serious inconsistencies rendering Mr. Wolfe’s testimony unbelievable and therefore against the manifest weight of the evidence. GHMS avers that Wolfe’s change of the contract date was done solely for the purpose of obtaining priority over mortgagee Lyons. Curiously, however, GHMS never objected to Wolfe’s amendment alleging August 23, 1982, as the contract date, and in fact, admitted that a contract was entered into between the parties on that date but denied the scope of the contract covered all work done by Wolfe on the Pebble Creek project. Thus, GHMS argues that since the evidence shows there were a series of contracts entered into between the parties and the contract dated August 23, 1982, was paid in full, judgment must be entered against Wolfe and in favor of GHMS. We disagree.

Undeniably, Wolfe’s statement of mechanic’s lien did state that the contract date was April 29, 1983. Nonetheless, Wolfe sought leave and was allowed, without objection, to amend the pleadings and allege a contract date of August 23, 1982. We disagree with GHMS’ contention that the date alleged in the statement of mechanic’s lien constituted a binding judicial admission, since a statement of mechanic’s lien does not necessarily require a contract date to be alleged (see Ill. Rev. Stat. 1987, ch. 82, par. 7), nor is the lien statement necessary for Wolfe’s contract claim. We consider the variance in the two alleged contract dates amounts to adverse evidence entitled to little consideration since there was no showing that GHMS in any way relied on the verified claim for lien to its detriment. See Office Electronics, Inc. v. Grafic Forms, Inc. (1979), 72 Ill. App. 3d 456, 390 N.E.2d 953 (principle of estoppel applied to inconsistent original and amended pleadings); Precision Extrusions, Inc. v. Stewart (1962), 36 Ill. App. 2d 30, 183 N.E.2d 547 (an amended, abandoned or withdrawn original pleading is treated as an ordinary admission); Nolan v. American Telephone & Telegraph Co. (1945), 326 Ill. App. 328, 61 N.E.2d 876 (inconsistent statement in an abandoned pleading is adverse evidence, but not a conclusive judicial admission).

The trial court’s finding that the contract was entered into on August 23, 1982, is supported by the following evidence: that the only time labor and machinery hourly rates were discussed was pursuant to the August 23, 1982, contract; that the contract was not based on a bid of a job but was for time and material; and that all of the work was performed on the same general project. It is also not fatal that no specific amount of work or the length of Wolfe’s employment at Pebble Creek were not expressly defined by the terms of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jet Construction, Inc. v. Terna
2024 IL App (3d) 220284-U (Appellate Court of Illinois, 2024)
Ashlaur Construction Co. v. The Levy Company
2023 IL App (1st) 210795-U (Appellate Court of Illinois, 2023)
Cordeck Sales v. Construction Systems
Appellate Court of Illinois, 2008
Cordeck Sales, Inc. v. Construction Systems, Inc.
887 N.E.2d 474 (Appellate Court of Illinois, 2008)
Action Mechanical, Inc. v. Deadwood Historic Preservation Commission
2002 SD 121 (South Dakota Supreme Court, 2002)
Brown and Kerr, Inc. v. American Stores Properties, Inc.
715 N.E.2d 804 (Appellate Court of Illinois, 1999)
Brown & Kerr v. American Stores Properties
715 N.E.2d 804 (Appellate Court of Illinois, 1999)
Braun-Skiba, Ltd. v. La Salle National Bank
665 N.E.2d 485 (Appellate Court of Illinois, 1996)
Venus Drywall, Inc. v. Kullman Industries, Inc.
5 Mass. L. Rptr. 70 (Massachusetts Superior Court, 1996)
Stoebner v. Horizon Fabricators, Inc.
153 B.R. 840 (D. Minnesota, 1993)
Lyons Fed. T. & S. Bk. v. Moline Nat'l Bk.
549 N.E.2d 933 (Appellate Court of Illinois, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
549 N.E.2d 933, 193 Ill. App. 3d 108, 140 Ill. Dec. 282, 1990 Ill. App. LEXIS 19, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lyons-federal-trust-savings-bank-v-moline-national-bank-illappct-1990.