Jet Construction, Inc. v. Terna

2024 IL App (3d) 220284-U
CourtAppellate Court of Illinois
DecidedOctober 15, 2024
Docket3-22-0284
StatusUnpublished

This text of 2024 IL App (3d) 220284-U (Jet Construction, Inc. v. Terna) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jet Construction, Inc. v. Terna, 2024 IL App (3d) 220284-U (Ill. Ct. App. 2024).

Opinion

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1).

2024 IL App (3d) 220284-U

Order filed October 15, 2024 ____________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

THIRD DISTRICT

JET CONSTRUCTION, INC., ) Appeal from the Circuit Court ) of the 18th Judicial Circuit, Plaintiff-Appellant, ) Du Page County, Illinois. ) v. ) Appeal No. 3-22-0284 ) Circuit No. 19-CH-1224 PAUL A. TERNA; THERESA L. TERNA; ) FIRSTMERIT BANK, N.A.; THE ) The Honorable HUNTINGTON NATIONAL BANK; ) Robert G. Gibson, UNKNOWN OWNERS AND NON-RECORD ) Judge, presiding. CLAIMANTS, ) ) Defendants-Appellees. ) ) ____________________________________________________________________________

PRESIDING JUSTICE McDADE delivered the judgment of the court. Justices Brennan and Albrecht concurred in the judgment. ____________________________________________________________________________

ORDER

¶1 Held: (1) We reverse the circuit court’s entry of a directed finding on Count I of plaintiff’s complaint for foreclosure of a mechanic’s lien, and remand for further proceedings. (2) We affirm the circuit court’s denial of plaintiff’s request for an award of interest, attorney’s fees, and costs, on different grounds.

¶2 On October 28, 2019, plaintiff, Jet Construction, Inc. (Jet Construction), filed a four-count

complaint against defendants, Paul Terna; Theresa Terna; Firstmerit Bank, N.A.; The Huntington National Bank; and unknown owners and non-record claimants. The complaint alleged claims of

(1) foreclosure of mechanic’s lien (Count I), (2) breach of contract (Count II), (3) quantum meruit

(Count III), and (4) unjust enrichment (Count IV). Jet Construction sought an award of interest,

attorney’s fees, and costs under Count II. The Ternas filed two counterclaims, one of which was

for a setoff.

¶3 During a two-day bench trial, and following the close of Jet Construction’s case, the Circuit

Court of DuPage County entered a directed finding against Jet Construction and in favor of the

Ternas on Count I, awarded Jet Construction judgment in the amount of $22,000.00 on Count II,

dismissed Counts III and IV as moot, and denied Jet Construction an award of interest, attorney’s

fees, and costs. Jet Construction now appeals from the circuit court’s entry of a directed finding on

Count I and denial of interest, attorney’s fees, and costs under Count II. For the following reasons,

we reverse the entry of a directed finding, remand the matter for further proceedings with respect

to Count I, and affirm the denial of interest, attorney’s fees, and costs.

¶4 I. BACKGROUND

¶5 The following facts and evidence were presented at trial. The Ternas owned a residence

located in Wheaton, Illinois. In 2017, they employed Chris Alfirevich, an interior designer and

their friend, to help them renovate the bathrooms at the residence. Chris introduced the Ternas to

John Ratkovich and Jet Construction, who were to perform the construction work. At that time,

Chris had known John for around 28 years and had worked with him on three other construction

projects.

¶6 In May or June 2017, Theresa, Chris, and John performed a walk-through of the Ternas’

residence and discussed the details of the renovation project, which was to involve the installation

of new tile, cabinetry, plumbing, faucets, and other items into the master and hall bathrooms at the

2 Ternas’ residence (Project). Following the walk-through, the Ternas asked John to prepare and

send them a proposal for the Project (Proposal).

¶7 John testified about how he prepared the Proposal, explaining that, when he is working on

a bathroom, he typically provides his clients allowances on items such as the tile and cabinets. If

the clients exceed the amount of the allowances, then he charges them extra; if they incur a lesser

amount than the allowances, he provides them credits. He further testified that the specific charges

listed in the Proposal were based on the items discussed during the walk-through, the amounts that

his subcontractors informed him that they would need to be paid to complete the work, and the

cost of various materials and labor. The cost of the Project was intended to be based on the amount

listed in the Proposal.

¶8 The Ternas and Jet Construction subsequently executed an agreement dated September 12,

2017 (Agreement). The Agreement was wholly comprised of a signed copy of the Proposal, and

provided that Jet Construction would furnish the materials and perform the labor necessary to

“[r]emove old plumbing fixtures, tile, cabinets and flooring”; “[i]nstall new wonder board and

ceramic tile, owner’s choice”; “[i]nstall owner’s plumbing fixtures, cabinets, light fixtures and

shower door”; and painting. The Agreement also provided for an allowance of $5.00 per square

foot of ceramic tile and a credit of $4,030.00 for cabinets and tops. The agreed total price of the

Project was $32,534.00, and the Ternas paid an initial deposit of $20,000.00 to Jet Construction to

begin work.

¶9 Regarding the individual roles on the Project, John testified that he believed that Chris was

the general contractor and Jet Construction was the subcontractor. Jet Construction was expected

to supply all the materials for the Project, except for the cabinets, countertops, and plumbing

fixtures, which the Ternas were instead responsible to pay for. Prior to the work on the Project

3 beginning, and as suggested by John, the Ternas selected the cabinets, shower fixtures, and tiles

that they wanted, and John later purchased the items at costs to be applied to the allowance and

credit in the Proposal. Chris testified that she was involved in the design selections and purchased

some of the lighting and plumbing fixtures.

¶ 10 Sometime after the Agreement was executed, the Ternas and Chris modified the Project in

two ways. The first modification entailed replacing the carpet in the master closet with tile, and

the second involved substituting a one-unit tub and shower with a tub and tile. Theresa and Chris

testified that they believed that the second modification would reduce the total plumbing costs of

the Project, whereas John testified that the modification required more complicated work and

delayed the completion of the Project.

¶ 11 Demolition for the Project began in late September 2017. John testified that, during the

work, Theresa raised no issues regarding the construction, other than the delayed completion, and

she stated that she “loved it.” Theresa testified that there appeared to be a lack of planning

throughout the Project, and that there were days when no work was done. She would call and leave

John a message, and then someone would show up and a little work would be done. Additionally,

some workers would come without notice, including a painter who showed up at around 7:00 p.m.

while the Ternas were eating dinner. There were also two instances in which a plumber arrived

and claimed that the supplies were not there, and Chris reordered the supplies before it was later

realized that they had been there all along.

¶ 12 On December 8, 2017, Theresa, Chris, and John performed a final walk-through of the

Project, the purpose of which was to gauge whether the Ternas were satisfied with all the items

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sherman v. Ryan
911 N.E.2d 378 (Appellate Court of Illinois, 2009)
G.M. Fedorchak & Associates, Inc. v. Chicago Title Land Trust Co.
822 N.E.2d 905 (Appellate Court of Illinois, 2005)
Aluminum Coil Anodizing Corp. v. First National Bank & Trust Co.
381 N.E.2d 301 (Appellate Court of Illinois, 1978)
Aluma Systems, Inc. v. Frederick Quinn Corp.
564 N.E.2d 1280 (Appellate Court of Illinois, 1990)
Ferrara v. Collins
457 N.E.2d 109 (Appellate Court of Illinois, 1983)
Evans v. Gurnee Inns, Inc.
645 N.E.2d 556 (Appellate Court of Illinois, 1994)
Dyduch v. Crystal Green Corp.
582 N.E.2d 302 (Appellate Court of Illinois, 1991)
Mirar Development, Inc. v. Kroner
720 N.E.2d 270 (Appellate Court of Illinois, 1999)
Favia v. Ford Motor Co.
886 N.E.2d 1182 (Appellate Court of Illinois, 2008)
Parkway Bank and Trust Co. v. Meseljevic
940 N.E.2d 215 (Appellate Court of Illinois, 2010)
In re Donald A.G.
850 N.E.2d 172 (Illinois Supreme Court, 2006)
PML Development LLC v. Village of Hawthorn Woods
2022 IL App (2d) 200779 (Appellate Court of Illinois, 2022)
Lyons Federal Trust & Savings Bank v. Moline National Bank
549 N.E.2d 933 (Appellate Court of Illinois, 1990)
Pepper Construction Co. v. Palmolive Tower Condominiums, LLC
2021 IL App (1st) 200753 (Appellate Court of Illinois, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2024 IL App (3d) 220284-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jet-construction-inc-v-terna-illappct-2024.