Jet Construction, Inc. v. Terna

2024 IL App (3d) 220284-U
Appellate Court of Illinois·Decided October 15, 2024·No. 3-22-0284·Unpublished

Opinion

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1).

2024 IL App (3d) 220284-U

Order filed October 15, 2024

IN THE

APPELLATE COURT OF ILLINOIS THIRD DISTRICT

2024

JET CONSTRUCTION, INC., ) Appeal from the Circuit Court ) of the 18th Judicial Circuit, Plaintiff-Appellant, ) Du Page County, Illinois.

)

v. ) Appeal No. 3-22-0284 ) Circuit No. 19-CH-1224 PAUL A. TERNA; THERESA L. TERNA; ) FIRSTMERIT BANK, N.A.; THE ) The Honorable HUNTINGTON NATIONAL BANK; ) Robert G. Gibson, UNKNOWN OWNERS AND NON-RECORD ) Judge, presiding. CLAIMANTS, )

)

Defendants-Appellees. )

)

PRESIDING JUSTICE McDADE delivered the judgment of the court.

Justices Brennan and Albrecht concurred in the judgment.

ORDER

¶1 Held: (1) We reverse the circuit court’s entry of a directed finding on Count I of plaintiff’s complaint for foreclosure of a mechanic’s lien, and remand for further proceedings.

(2) We affirm the circuit court’s denial of plaintiff’s request for an award of interest, attorney’s fees, and costs, on different grounds.

¶2 On October 28, 2019, plaintiff, Jet Construction, Inc. (Jet Construction), filed a four-count complaint against defendants, Paul Terna; Theresa Terna; Firstmerit Bank, N.A.; The Huntington

National Bank; and unknown owners and non-record claimants. The complaint alleged claims of (1) foreclosure of mechanic’s lien (Count I), (2) breach of contract (Count II), (3) quantum meruit (Count III), and (4) unjust enrichment (Count IV). Jet Construction sought an award of interest, attorney’s fees, and costs under Count II. The Ternas filed two counterclaims, one of which was for a setoff.

¶3 During a two-day bench trial, and following the close of Jet Construction’s case, the Circuit Court of DuPage County entered a directed finding against Jet Construction and in favor of the Ternas on Count I, awarded Jet Construction judgment in the amount of $22,000.00 on Count II, dismissed Counts III and IV as moot, and denied Jet Construction an award of interest, attorney’s fees, and costs. Jet Construction now appeals from the circuit court’s entry of a directed finding on Count I and denial of interest, attorney’s fees, and costs under Count II. For the following reasons, we reverse the entry of a directed finding, remand the matter for further proceedings with respect to Count I, and affirm the denial of interest, attorney’s fees, and costs.

¶4 I. BACKGROUND

¶5 The following facts and evidence were presented at trial. The Ternas owned a residence located in Wheaton, Illinois. In 2017, they employed Chris Alfirevich, an interior designer and their friend, to help them renovate the bathrooms at the residence. Chris introduced the Ternas to John Ratkovich and Jet Construction, who were to perform the construction work. At that time, Chris had known John for around 28 years and had worked with him on three other construction projects.

¶6 In May or June 2017, Theresa, Chris, and John performed a walk-through of the Ternas’ residence and discussed the details of the renovation project, which was to involve the installation of new tile, cabinetry, plumbing, faucets, and other items into the master and hall bathrooms at the

Ternas’ residence (Project). Following the walk-through, the Ternas asked John to prepare and send them a proposal for the Project (Proposal).

¶7 John testified about how he prepared the Proposal, explaining that, when he is working on a bathroom, he typically provides his clients allowances on items such as the tile and cabinets. If the clients exceed the amount of the allowances, then he charges them extra; if they incur a lesser amount than the allowances, he provides them credits. He further testified that the specific charges listed in the Proposal were based on the items discussed during the walk-through, the amounts that his subcontractors informed him that they would need to be paid to complete the work, and the cost of various materials and labor. The cost of the Project was intended to be based on the amount listed in the Proposal.

¶8 The Ternas and Jet Construction subsequently executed an agreement dated September 12, 2017 (Agreement). The Agreement was wholly comprised of a signed copy of the Proposal, and provided that Jet Construction would furnish the materials and perform the labor necessary to “[r]emove old plumbing fixtures, tile, cabinets and flooring”; “[i]nstall new wonder board and ceramic tile, owner’s choice”; “[i]nstall owner’s plumbing fixtures, cabinets, light fixtures and shower door”; and painting. The Agreement also provided for an allowance of $5.00 per square foot of ceramic tile and a credit of $4,030.00 for cabinets and tops. The agreed total price of the Project was $32,534.00, and the Ternas paid an initial deposit of $20,000.00 to Jet Construction to begin work.

¶9 Regarding the individual roles on the Project, John testified that he believed that Chris was the general contractor and Jet Construction was the subcontractor. Jet Construction was expected to supply all the materials for the Project, except for the cabinets, countertops, and plumbing fixtures, which the Ternas were instead responsible to pay for. Prior to the work on the Project

beginning, and as suggested by John, the Ternas selected the cabinets, shower fixtures, and tiles that they wanted, and John later purchased the items at costs to be applied to the allowance and credit in the Proposal. Chris testified that she was involved in the design selections and purchased some of the lighting and plumbing fixtures.

¶ 10 Sometime after the Agreement was executed, the Ternas and Chris modified the Project in two ways. The first modification entailed replacing the carpet in the master closet with tile, and the second involved substituting a one-unit tub and shower with a tub and tile. Theresa and Chris testified that they believed that the second modification would reduce the total plumbing costs of the Project, whereas John testified that the modification required more complicated work and delayed the completion of the Project.

¶ 11 Demolition for the Project began in late September 2017. John testified that, during the work, Theresa raised no issues regarding the construction, other than the delayed completion, and she stated that she “loved it.” Theresa testified that there appeared to be a lack of planning throughout the Project, and that there were days when no work was done. She would call and leave John a message, and then someone would show up and a little work would be done. Additionally, some workers would come without notice, including a painter who showed up at around 7:00 p.m. while the Ternas were eating dinner. There were also two instances in which a plumber arrived and claimed that the supplies were not there, and Chris reordered the supplies before it was later realized that they had been there all along.

¶ 12 On December 8, 2017, Theresa, Chris, and John performed a final walk-through of the Project, the purpose of which was to gauge whether the Ternas were satisfied with all the items scheduled to be completed, and to note anything that needed to be adjusted or fixed. During the walk-through, Chris was responsible for taking notes and listing all the items that were mentioned.

John testified that the Ternas complained of a divot in the granite, drawers that stuck when they were pulled out, and that the bathroom casings did not touch the floor. Theresa testified that, in addition to these issues, she and Paul also pointed out missing trim around a mirror and a hole in a bathroom wall.

Free access — add to your briefcase to read the full text and ask questions with AI

Jet Construction, Inc. v. Terna, 2024 IL App (3d) 220284-U (Ill. Ct. App. 2024).

2024 IL App (3d) 220284-U (Jet Construction, Inc. v. Terna) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sherman v. Ryan
911 N.E.2d 378 (Appellate Court of Illinois, 2009)
G.M. Fedorchak & Associates, Inc. v. Chicago Title Land Trust Co.
822 N.E.2d 905 (Appellate Court of Illinois, 2005)
Aluminum Coil Anodizing Corp. v. First National Bank & Trust Co.
381 N.E.2d 301 (Appellate Court of Illinois, 1978)
Aluma Systems, Inc. v. Frederick Quinn Corp.
564 N.E.2d 1280 (Appellate Court of Illinois, 1990)
Ferrara v. Collins
457 N.E.2d 109 (Appellate Court of Illinois, 1983)
Evans v. Gurnee Inns, Inc.
645 N.E.2d 556 (Appellate Court of Illinois, 1994)
Dyduch v. Crystal Green Corp.
582 N.E.2d 302 (Appellate Court of Illinois, 1991)
Mirar Development, Inc. v. Kroner
720 N.E.2d 270 (Appellate Court of Illinois, 1999)
Favia v. Ford Motor Co.
886 N.E.2d 1182 (Appellate Court of Illinois, 2008)
Parkway Bank and Trust Co. v. Meseljevic
940 N.E.2d 215 (Appellate Court of Illinois, 2010)
In re Donald A.G.
850 N.E.2d 172 (Illinois Supreme Court, 2006)
PML Development LLC v. Village of Hawthorn Woods
2022 IL App (2d) 200779 (Appellate Court of Illinois, 2022)
Lyons Federal Trust & Savings Bank v. Moline National Bank
549 N.E.2d 933 (Appellate Court of Illinois, 1990)
Pepper Construction Co. v. Palmolive Tower Condominiums, LLC
2021 IL App (1st) 200753 (Appellate Court of Illinois, 2021)