Metropolitan Federal Bank of Iowa v. A.J. Allen Mechanical Contractors, Inc.

477 N.W.2d 668, 1991 Iowa Sup. LEXIS 431, 1991 WL 239860
CourtSupreme Court of Iowa
DecidedNovember 20, 1991
Docket90-1380
StatusPublished
Cited by9 cases

This text of 477 N.W.2d 668 (Metropolitan Federal Bank of Iowa v. A.J. Allen Mechanical Contractors, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metropolitan Federal Bank of Iowa v. A.J. Allen Mechanical Contractors, Inc., 477 N.W.2d 668, 1991 Iowa Sup. LEXIS 431, 1991 WL 239860 (iowa 1991).

Opinion

McGIVERIN, Chief Justice.

This case presents the question of whether certain contractors waived their rights to claim mechanics' liens prior in right to the claims of a construction mortgagee. The district court concluded that the contractors had not waived their rights. We agree and affirm.

I. Background facts and proceedings. This dispute arose out of the construction of a strip mall in Des Moines by ABAS Partnership and its individual partners A.Y. Al-Shash, Ala Daghestani, and Jeffrey Smith (ABAS). ABAS began construction of the project in early 1986, obtaining financing in late October from First Financial Savings Bank, the predecessor-in-interest to plaintiff Metropolitan Federal Bank of Iowa (Metropolitan).

None of the parties contest the fact that certain contractors began work on the project before ABAS obtained its construction financing from Metropolitan. Defendant A.J. Allen Mechanical Contractors, Inc. (Allen) commenced work on the project on January 15, 1986. Hansen Contractors, Ltd. (Hansen), who is not a party to the present appeal, commenced its work on July 23, 1986. Defendant Baker Electric, Inc. (Baker) started its work on September 4, 1986. Two other contractors, not parties to the present appeal, commenced work on September 15, 1986.

ABAS did not obtain construction financing from Metropolitan until October 21, 1986. ABAS obtained a four million dollar loan from Metropolitan, giving the bank a mortgage on the mall premises in return. Metropolitan recorded its mortgage on October 24, 1986. 1 At that time, none of the contractors involved in this appeal was aware of Metropolitan’s involvement in the project.

On October 24,1986, the date that Metropolitan recorded its mortgage, sums were paid to certain of the contractors for work previously done on the project. Allen was paid $161,238.75. In exchange for payment, Allen submitted to ABAS four documents entitled “Subcontractor’s Partial Waiver of Lien” (emphasis in original). These lien waivers were dated July 30, August 29, September 26, and October 24, 1986, respectively. They purported to *670 waive Allen’s rights to claim mechanic’s and other liens for work furnished up to and including the date of partial payment. 2

Baker also received partial payment on October 24, 1986. In consideration for receiving $11,555.31 for work previously performed, Baker submitted to ABAS, on the date of payment, two lien waivers, similar to those submitted by Allen, purporting to waive Baker’s rights to liens on ABAS’s property for work rendered or furnished by Baker. 3

Additionally, Hansen received, on October 24, 1986, $633,625 for work previously performed on the project. Hansen also submitted to ABAS a lien waiver, similar to those submitted by Allen and Baker, purporting to waive any right to claim a lien for work furnished prior to the date of the lien waiver. Hansen did not submit this waiver to ABAS until November 5, 1986, the date stated thereon.

The sums paid to these contractors were drawn from the funds provided to ABAS by Metropolitan’s construction loan. Although there was testimony in the hearing before the district court that these payments were drawn on Metropolitan’s own checks, representatives of the contractors testified that none of them was aware of the fact that Metropolitan was the source of construction financing.

Work continued on the project through 1986 and 1987. At periodic intervals throughout construction, the contractors would submit invoices or other requests for progress payments. With each such request, the contractors would submit lien waivers, as outlined above, containing language purporting to waive their rights to claim mechanics’ liens. The contractors were paid from draws made on Metropolitan’s loan. In all, ABAS made seven draws on the loan from Metropolitan subsequent to the first draw of October 24,1986. The last draw came on May 29, 1987.

ABAS ultimately defaulted on its loan from Metropolitan. Allen thereafter filed a mechanic’s lien on November 23, 1987, in the amount of $89,995.10 for work for which it had not yet been paid. Baker filed a mechanic’s lien on December 4, 1987, in the amount of $82,085.91. Hansen also filed an amended mechanic’s lien on July 20, 1988, in the amount of $339,702.70. Several other contractors not involved in this appeal also filed mechanic’s liens.

Metropolitan then filed a petition in equity seeking judgment on its note and foreclosure of its mortgage. After appropriate pleadings, Metropolitan and certain contractors filed motions requesting the district court to determine the priority of the parties’ respective claims and liens. After a trial, the district court entered an order establishing the priority of the parties’ respective claims and liens, concluding that the liens of Allen, Hansen, and Baker, respectively, were prior in right to Metropolitan’s construction mortgage. The court also found that the contractors had not intended to alter their priority positions, in relation to Metropolitan’s construction mortgage, by periodic use of the lien waivers.

Metropolitan appealed, and we now consider its contentions.

II. Interpretation of Iowa Code section 572.18. As an initial matter, we note that the scope of our review is de novo since this case was maintained and tried as an equitable proceeding in the district court. See Iowa R.App.P. 4.

This case involves an interpretation of Iowa Code section 572.18 (1991), which provides, in pertinent part:

Mechanics’ liens shall be preferred to all other liens which may attach to or upon a building or improvement and to the land upon which it is situated, except liens of record prior to the time of the original commencement of the work or improvements. However, construction *671 mortgage liens shall be preferred to all mechanics’ liens of claimants who commenced their particular work or improvement subsequent to the date of the recording of the construction mortgage lien....

(Emphasis supplied.) Metropolitan contends that the phrase “particular work or improvement” refers only to that for which a claimant is unpaid and which forms the basis for the filing of a mechanic’s lien. Metropolitan argues that the priority of such a claimant’s lien thus relates back only to the earliest day that labor or materials were supplied on that particular, unpaid claim. It believes that, since the “particular work or improvement” for which Allen and Baker remain unpaid was provided subsequent to the recordation of Metropolitan’s construction mortgage, the mechanic’s liens of Allen and Baker are subordinate to Metropolitan’s construction mortgage.

Allen and Baker argue that the phrase “particular work or improvement” refers to any work or material supplied by the mechanic lien claimant. They further contend that the priority of such a claimant’s lien thus relates back to the first date that any labor or materials were supplied to the project by that particular claimant, and that such priority is not affected by any payments for work done before the construction mortgage was recorded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wachovia Bank National Ass'n v. Superior Construction Corp.
718 S.E.2d 160 (Court of Appeals of North Carolina, 2011)
Schnittjer v. Pippert (Carney)
396 B.R. 22 (N.D. Iowa, 2008)
In Re Carney
396 B.R. 22 (N.D. Iowa, 2008)
Action Mechanical, Inc. v. Deadwood Historic Preservation Commission
2002 SD 121 (South Dakota Supreme Court, 2002)
Landvatter Ready Mix, Inc. v. Buckey
963 S.W.2d 298 (Missouri Court of Appeals, 1997)
Midland Savings Bank FSB v. Stewart Group, LC
533 N.W.2d 191 (Supreme Court of Iowa, 1995)
Conrad American v. Cooperative Grain & Product Co.
488 N.W.2d 450 (Supreme Court of Iowa, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
477 N.W.2d 668, 1991 Iowa Sup. LEXIS 431, 1991 WL 239860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metropolitan-federal-bank-of-iowa-v-aj-allen-mechanical-contractors-iowa-1991.