Amfac Distribution Corp. v. J.B. Contractors, Inc.

703 P.2d 566, 146 Ariz. 19, 1985 Ariz. App. LEXIS 544
CourtCourt of Appeals of Arizona
DecidedJuly 5, 1985
Docket1 CA-CIV 7924
StatusPublished
Cited by14 cases

This text of 703 P.2d 566 (Amfac Distribution Corp. v. J.B. Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amfac Distribution Corp. v. J.B. Contractors, Inc., 703 P.2d 566, 146 Ariz. 19, 1985 Ariz. App. LEXIS 544 (Ark. Ct. App. 1985).

Opinion

*21 OPINION

EUBANK, Judge.

This appeal arises out of a suit brought by Amfac Distribution Corporation to foreclose its materialmen’s liens for electrical materials and supplies used in the construction of the Southern Palms Shopping Center in Tempe, Arizona.

Hahn Devcorp, Inc., was the owner of the property on which the Southern Palms Shopping Center was being constructed. J.B. Contractors, Inc. was the general contractor on the project. Between April and June of 1981, J.B. Contractors entered into three subcontracts with SWL Electric Corporation for electrical work on three separate buildings or groups of buildings in the project distinguished hereinafter as the Southern Palms stores, the Boston Store, and Thrifty Drug Store. The payments from J.B. Contractors to SWL under these three subcontracts were to be respectively $285,775.70, $48,587.17, and $43,925.26. SWL in turn entered into verbal agreements with Amfac to obtain electrical materials and supplies for each of the three subcontracts. When Amfac began supplying materials to the project in July, 1981, it notified J.B. Contractors and the property owner that it was supplying materials and supplies to the project by sending them preliminary lien notices as required by A.R.S. § 33-992.01 as a prerequisite to filing materialmen’s liens.

In September, 1981, J.B. Contractors became concerned that SWL was not properly performing its subcontracts, including failing to pay its suppliers. At that time J.B. Contractors’ president issued instructions to his accounting staff that no further checks go to SWL for monthly progress payments until J.B. Contractors received lien waivers in full from SWL and its suppliers. Accordingly, J.B. Contractors released the October progress payment to SWL on October 22, 1981, only after it had received lien waivers from both SWL and Amfac which waived all claims incurred through that date. Again in November, J.B. Contractors released payment to SWL on November 24, 1981, only after both SWL and Amfac signed lien waivers which waived all claims incurred through that date. Soon afterward, J.B. Contractors removed SWL from the project for breach of contract and hired replacements to finish the three phases of the project. At the time of its removal, SWL had been paid the following amounts by J.B. Contractors under the subcontracts: $245,607.25 for Southern Palms, $41,530.00 for the Boston Store, and $37,886.13 for Thrifty Drug. SWL’s payments to Amfac for materials and supplies had been $151,089.67 broken down as follows: $115,781.80 for Southern Palms, $18,374.61 for the Boston Store, and $16,933.26 for Thrifty Drug.

On January 12, 1982, Amfac recorded three notices and claim of liens for materials supplied to the project for which it had not received payment:

Southern Palms $131,017.18

Boston Store 23,136.00

Thrifty Drug 21,785.58

TOTAL $175,938.76

Of these claims, only small amounts were attributable to materials furnished after November 24, 1981, the date when Amfac’s last three lien waivers were signed:

Southern Palms $1,117.69

Boston Store 40.40

Thrifty Drug 7,634,50

TOTAL $8,792.59

After Amfac’s liens were recorded, J.B. Contractors recorded three statutory discharge of lien bonds issued by Federal Insurance Company for one and one-half times the amount of the liens pursuant to A.R.S. § 33-1004.

On July 8, 1982, Amfac filed suit against Hahn Devcorp, Inc.; J.B. Contractors, Inc.; Federal Insurance Company; and various other defendants having an interest in the Southern Palms property to foreclose its liens or to collect against the lien discharge bonds. Soon after suit was filed, J.B. Contractors and Federal Insurance Company made an offer of judgment to Amfac of $9,175.14 which was not accepted. J.B. Contractors and Federal Insurance Company then filed a motion for partial summary *22 judgment requesting that Amfac’s recovery be limited to $8,792.59, the cost of the materials furnished by Amfac after November 24, 1981, the date of the last lien waivers submitted by Amfac for each of the three parts of the project. The trial court agreed that the lien waivers limited Amfac’s recovery, but ruled that they did so only to the extent that J.B. Contractors had paid SWL for the items for which Amfac was making its claims. J.B. Contractors then furnished proof that it had paid SWL or the other subcontractors who finished the projects all monies due under the subcontracts except for $39,353.39. Thereafter, Amfac moved for summary judgment and the trial court, in ruling on the cross-motions for summary judgment before it, entered formal judgment in the amount of $30,873.39 1 against J.B. Contractors and Federal Insurance Company and dismissed all remaining claims. Both parties appeal from the judgment.

The lien waivers executed and delivered by Amfac on November 24, 1981 for each of the three phases of the project were all in essentially the same general form and language. The lien releases for materials supplied to the Thrifty Drug Store, for example, provided as follows:

WAIVER OF LIEN FOR LABOR AND/OR MATERIALS

November 24 , 19 81

KNOW ALL MEN BY THESE PRESENTS:

WHEREAS, the undersigned Claude G. Moore of Phoenix , Arizona, is an authorized representative of Amfac Electric Supply under a verbal agreement to furnish materials for the construction project known as Southern Palms Center, Thrifty .

NOW, THEREFORE, BE IT KNOWN that the undersigned, for and in consideration of $ 16,933.26 , and other good and valuable considerations, receipt of which is hereby acknowledged, does hereby waive and release any and all lien, claim or right of lien on the above described building and premises on account of labor or materials, or both, furnished to date by the undersigned pursuant to the aforesaid agreement for said building and/or premises.

INV. # AMOUNT Dated this 24 day of November , 19 81 see attached invoices

_Claude G. Moore_

Title: District Credit Manager

Subscribed and sworn to before me this 24 day of November , 19 81 .

Dorothy Groeneveld

Notary Public

The only differences between this lien release and those executed the same date concerning materials supplied for the other two buildings were the amount of consideration recited and the words typed at the bottom of the form under the heading *23 showing “Inv. #Amount.” On the lien release for Thrifty Drug, the words “see attached invoices” had been typed. The lien release for the Boston Store contained the words “see attached sheets” and that for Southern Palms stated “see attached check.” It is undisputed that no invoices, sheets, or check were in fact attached to the lien waivers when they were delivered to J.B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re the Estate of Susan Ruth Chalker
Court of Appeals of Arizona, 2023
Manicom v. Citimortgage, Inc.
336 P.3d 1274 (Court of Appeals of Arizona, 2014)
Cumis Ins. Society, Inc. v. Merrick Bank Corp.
680 F. Supp. 2d 1077 (D. Arizona, 2010)
United Metro Materials, Inc. v. Pena Blanca Properties, L.L.C.
4 P.3d 1022 (Court of Appeals of Arizona, 2000)
General Motors Corp. v. Arizona Department of Revenue
938 P.2d 481 (Court of Appeals of Arizona, 1996)
Hill v. Chubb Life American Insurance
870 P.2d 1133 (Court of Appeals of Arizona, 1994)
C S & W Contractors, Inc. v. Southwest Savings & Loan Ass'n
852 P.2d 1239 (Court of Appeals of Arizona, 1992)
Hellon & Associates, Inc. v. Phoenix Resort Corp.
958 F.2d 295 (Ninth Circuit, 1992)
Neiderhauser Builders & Development Corp. v. Campbell
824 P.2d 1193 (Court of Appeals of Utah, 1992)
Overberg v. Lusby
727 F. Supp. 1091 (E.D. Kentucky, 1990)
United Masonry Inc. v. Riggs National Bank
357 S.E.2d 509 (Supreme Court of Virginia, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
703 P.2d 566, 146 Ariz. 19, 1985 Ariz. App. LEXIS 544, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amfac-distribution-corp-v-jb-contractors-inc-arizctapp-1985.