Neiderhauser Builders & Development Corp. v. Campbell

824 P.2d 1193, 178 Utah Adv. Rep. 21, 1992 Utah App. LEXIS 5, 1992 WL 9666
CourtCourt of Appeals of Utah
DecidedJanuary 21, 1992
Docket910419-CA
StatusPublished
Cited by15 cases

This text of 824 P.2d 1193 (Neiderhauser Builders & Development Corp. v. Campbell) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neiderhauser Builders & Development Corp. v. Campbell, 824 P.2d 1193, 178 Utah Adv. Rep. 21, 1992 Utah App. LEXIS 5, 1992 WL 9666 (Utah Ct. App. 1992).

Opinion

OPINION

GREENWOOD, Judge:

Plaintiff Neiderhauser Builders and Development Corporation (Neiderhauser) appeals from the trial court’s order granting summary judgment for defendants Scott and Claudia Campbell (the Campbells). We affirm in part, and reverse and remand in part.

FACTS

Because we are reviewing the trial court’s order granting the Campbells’ summary judgment motion, we state the facts in the light most favorable to Neiderhauser. Frontier Founds. v. Layton Constr., 818 P.2d 1040, 1041 (Utah App.1991).

On July 12, 1988, Neiderhauser and the Campbells entered into a contract wherein Neiderhauser agreed to construct a house for the Campbells for $87,700. The contract documents included a standard form agreement, the bid proposal, and the specifications and drawings. The agreement also provided that Neiderhauser was to submit authorized written change orders for all work not specifically included in the contract.

After the agreement was signed, the parties discovered that applicable building covenants and restrictions required that the house be larger than the parties had originally planned. Consequently, they added a clause to the agreement stating that the additional costs incurred because of the additional footage would be treated as extras and settled at closing.

The Campbells obtained a construction loan from First Security Bank’s (FSB) Lay-ton branch. During the course of construction, Neiderhauser submitted draws to FSB and FSB issued checks drawn on the Camp-bells’ construction loan account directly to Neiderhauser. The following language appears on the back of each check:

Lien Waiver
In consideration of the payment of this check, the payee by endorsing, causing to be endorsed, stamping this check with a deposit stamp, or otherwise negotiating the same, waives[,] releases and relinquishes all right of lein[sic] or claims payee now has to date upon the premises described on the reverse side hereof. The payee certifies that this check is payment for labor and/or materials that were actually performed upon and/or furnished to the described premises. Payee warrants and guarantees under penalty of fraud that payment in full has been made by payee to all laborers and *1195 suppliers of labor and all materials to said premises incurred to date at the instance of payee. Payee agrees to indemnify and to hold harmless the owner and First Security Bank of Utah, N.A. and/or it[s] assigns from any loss, claims or expenses by reason of or arising out of said lien or claim.

Neiderhauser signed the lien waiver on each check.

Neiderhauser submitted its last draw to FSB on December 28, 1988. The draw was for $14,007.80, which exceeded the remaining balance of the loan. The bank paid a portion of the draw and designated checks in the amount of $5,639.33 for the remainder, to be paid at closing out of the Camp-bells’ long-term financing loan, which they obtained from the Bountiful branch of FSB. Prior to closing, employees of the FSB’s Layton branch told employees of the Bountiful branch to issue the additional checks and give them to the title company to present to Neiderhauser. The title company, however, never received the checks from the Bountiful branch and therefore never gave them to Neiderhauser.

Neiderhauser prepared a settlement statement entitled “addendum” which set forth the revised price of the house, including $25,000 for the lot, the cost of all extras and overruns, and costs for the additional footage. Although Neiderhauser had not presented any written change orders, the extra costs were incurred at the request, or at least with the concurrence of the Campbells. The Campbells were informed of and agreed that there had been extras included in the home and overruns of cost allowances totaling $12,514, making the total price of the home and lot $125,-214, exclusive of financing and appraisal costs. Both Neiderhauser and the Camp-bells signed the addendum at the closing on December 30, 1988. The settlement statement signed by the parties at closing specified the sum of $10,204.24 to be paid to Neiderhauser as a full payoff. When the parties signed the addendum and the settlement statement, they assumed all of the draws submitted by Neiderhauser had been paid. The bank, however, had not yet paid the extra $5,639.33. Therefore, the settlement statement inaccurately represented the payoff amount owed to Neiderhauser. Based on its assumption that the final draw would be paid in full and that the settlement statement was correct, Neiderhauser accepted a check at closing which was presented as the final payment due and owing for its work.

One week after closing, Neiderhauser received the checks for reimbursement of the final draw it had presented on December 28, 1988. The checks were less than the draw amount by $5,639.33. Neiderhauser then demanded payment from the Camp-bells. When the Campbells refused to pay, Neiderhauser filed a lien on their house and a complaint alleging breach of contract, lien foreclosure, failure to bond and quantum meruit. The Campbells counterclaimed, alleging that the lien was void, breach of contract, and slander. Neider-hauser then moved for summary judgment on the lien foreclosure. The Campbells also moved for summary judgment; arguing that Neiderhauser had waived its right to file a lien by signing the waivers on the checks.

The trial court denied Neiderhauser’s motion for summary judgment and granted the Campbells’ motion for summary judgment. The court order addressed only the lien theory. In its written ruling, the trial court stated that because Neiderhauser filed a lien after agreeing to not do so, it violated its agreement and the lien was therefore void. The court later clarified that it intended its ruling to cover all of Neiderhauser’s causes of action, even though they were not all addressed in either the parties’ memoranda or the court’s ruling.

On appeal, Neiderhauser claims the trial court erred in granting summary judgment to the Campbells on the issues of lien waiver, mistake, quantum meruit, and failure to bond. Neiderhauser also argues that the trial court should not have granted summary judgment on the quantum meruit and bonding issue claims because they were neither argued nor briefed before the trial court. The Campbells urge that accord and *1196 satisfaction precludes Neiderhauser’s claims entirely.

STANDARD OF REVIEW

Summary judgment shall be granted if “there is no genuine issue as to any material fact and [if] the moving party is entitled to a judgment as a matter of law.” Utah R.Civ.P. 56(c). In determining whether the trial court correctly found that there were no genuine issues of material fact, “we view the facts and all reasonable inferences in a light most favorable to the party opposing the motion.” Frontier Founds. v. Layton Constr., 818 P.2d 1040, 1041 (Utah App.1991) (citing Blue Cross and Blue Shield v. State, 779 P.2d 634, 636 (Utah 1989)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Magleby v. Schnibbe
2023 UT App 54 (Court of Appeals of Utah, 2023)
Rusk v. Harstad
2017 UT App 27 (Court of Appeals of Utah, 2017)
Lane Myers v. National City Bank
2014 UT 58 (Utah Supreme Court, 2014)
Lane Myers Construction, LLC v. National City Bank
2014 UT 58 (Utah Supreme Court, 2014)
Ellis-Walker Builders, Inc. v. Don Reynolds Properties, LLC
695 S.E.2d 832 (Court of Appeals of North Carolina, 2010)
Traco Steel Erectors, Inc. v. Comtrol, Inc.
2007 UT App 407 (Court of Appeals of Utah, 2007)
Cherry v. Utah State University
966 P.2d 866 (Court of Appeals of Utah, 1998)
England v. Horbach
944 P.2d 340 (Utah Supreme Court, 1997)
England v. Horbach
905 P.2d 301 (Court of Appeals of Utah, 1995)
Palmer v. Hayes
892 P.2d 1059 (Court of Appeals of Utah, 1995)
Brown v. Weis
871 P.2d 552 (Court of Appeals of Utah, 1994)
Frontier Properties Corp. v. Swanberg
488 N.W.2d 146 (Supreme Court of Iowa, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
824 P.2d 1193, 178 Utah Adv. Rep. 21, 1992 Utah App. LEXIS 5, 1992 WL 9666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neiderhauser-builders-development-corp-v-campbell-utahctapp-1992.