Lane Myers v. National City Bank

2014 UT 58
CourtUtah Supreme Court
DecidedDecember 19, 2014
DocketNo 20121004
StatusPublished
Cited by1 cases

This text of 2014 UT 58 (Lane Myers v. National City Bank) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lane Myers v. National City Bank, 2014 UT 58 (Utah 2014).

Opinion

This opinion is subject to revision before final publication in the Pacific Reporter

2014 UT 58

IN THE

SUPREME COURT OF THE STATE OF UTAH

LANE MYERS CONSTRUCTION, LLC, Respondent, v. NATIONAL CITY BANK, NATIONAL CITY BANK OF INDIANA, Petitioners.

No. 20121004 Filed December 19, 2014

On Certiorari to the Utah Court of Appeals

Third District, Silver Summit Dep’t The Honorable Bruce C. Lubeck No. 070500707

Attorneys: Rick L. Sorensen, Salt Lake City, for respondent Lincoln Harris, Zachary E. Peterson, Paul P. Burghardt, Salt Lake City, for petitioners

JUSTICE LEE authored the opinion of the Court, in which JUSTICE PARRISH joined and in which CHIEF JUSTICE DURRANT and JUSTICE DURHAM each joined in part. CHIEF JUSTICE DURRANT filed a concurring opinion, in which ASSOCIATE CHIEF JUSTICE NEHRING joined in part. JUSTICE DURHAM filed a concurring opinion, in which ASSOCIATE CHIEF JUSTICE NEHRING joined in part. ASSOCIATE CHIEF JUSTICE NEHRING filed a concurring opinion. LANE MYERS CONSTR. v. NAT’L CITY BANK Opinion of the Court

JUSTICE LEE, opinion of the Court: ¶1 Dick and Kim Kyker hired Lane Myers Construction to build two separate homes. The Kykers secured a construction loan through National City Bank, and the bank periodically paid Lane Myers on draw request forms that included language stating that Lane Myers had no lien on the property. The question presented is whether the draw request forms effected an enforceable lien waiver under the Utah Mechanics’ Lien Act. 1 ¶2 The district court entered summary judgment for the Kykers and National City, holding that the draw requests were in substantial compliance with the Act and thus effected a waiver foreclosing Lane Myers’s lien claim. The court of appeals reversed. It held that the forms were not in substantial compliance with the Act because they failed to incorporate the essential elements of the “forms” included in the Act. UTAH CODE § 38-1-39(4)(b) (2010). ¶3 We reverse and remand. In the circumstances of this case, we interpret the Act to require only “a waiver and release that is signed by the lien claimant or the lien claimant’s authorized agent.” Id. § 38-1-39(2)(a)(i). And we interpret that requirement to incorporate the established, term-of-art understanding of the elements of a “waiver.” Thus, we view the forms set forth in the statute as only a safe harbor, and not a requirement. Under the standard as clarified below, however, we decline to affirm entry of summary judgment for the Kykers and National City. Instead, finding genuine issues of material fact on the current record, we remand to the district court for further proceedings. I ¶4 In 2006, Lane Myers agreed to build two homes for Kim and Dick Kyker, one in Park City and the other in Oakley. Although Lane Myers also asserted a lien against the Oakley

1 UTAH CODE §§ 38-1-1 to –40 (2010). The 2010 version of the Act is identical to the version that was in place at the time of the events in question here, Lane Myers Constr., LLC v. Countrywide Home Loans, Inc., 2012 UT App 269, ¶ 1 n.2, 287 P.3d 479, and the court of appeals elected to cite to that version in its opinion. To remain consistent with the court of appeals and for ease of reference we also cite to the 2010 version of the Act in this opinion.

2 Cite as: 2014 UT 58 Opinion of the Court property, only the facts concerning the Park City home are relevant to this appeal. ¶5 The Kykers obtained a construction loan from National City in order to pay Lane Myers for the construction of the Park City home. Lane Myers commenced construction that year, and between June 14, 2006, and August 22, 2008, it submitted a total of sixteen draw requests to National City. Although Lane Myers submitted these draw requests directly to National City, it alleges that it did not know the total amount of the construction loan. But despite this fact, when it signed each of these draw requests Lane Myers certified that the “available proceeds of the loan are sufficient to finally and fully complete and pay for completion of improvements” and that “no suppliers, subcontractors, laborers, or other persons are claiming or are entitled to claim a lien against the property securing the loan.” ¶6 Although Lane Myers submitted sixteen draw requests, National City fully funded only five of them. Lane Myers repeatedly asked National City why its requests were being only partially funded, and each time National City responded by stating that there were either unauthorized cost overages in the requests or that, based on an inspection of the property, a full disbursement was not warranted. Lane Myers also informed the Kykers of the shortages, and the Kykers repeatedly assured Lane Myers that they would “take care of it.” In fact, at one point the Kykers even sent Lane Myers funds from a different account to cover the shortages, but then requested that those funds be applied to the Oakley property. ¶7 At the time, Lane Myers submitted its fifteenth draw request it was owed a balance of $357,560.98. When it received a disbursement of just $21,140.60 from National City, it again called National City to inquire about the discrepancy. This time, National City informed Lane Myers that the only funds left in the account were “retainage that National City was holding until a certificate of occupancy was issued by the city.” According to Lane Myers, this was the first time it realized that the Kykers’ construction loan would not cover all of the construction costs for the Park City home. ¶8 Nevertheless, despite being owed over $300,000, Lane Myers submitted its sixteenth and final draw request to National City on August 22, 2008, for just $105,702.99. National City instructed Lane Myers to use the same form for the final draw request as it had for the prior requests, but to handwrite “Final

3 LANE MYERS CONSTR. v. NAT’L CITY BANK Opinion of the Court Draw” at the top of the form, presumably to make the following language operative: IF THIS IS THE FINAL DRAW I/WE FURTHER CERTIFY THAT: 1. The General Contractor has to date been paid in full for all work performed and for all labor, materials furnished by the General Contractor and all sub-contractors, materialmen, suppliers and laborers and that no such sub-contractors, suppliers, or materialmen, laborers or other persons providing goods and services used in the improvements to the property have unpaid claims. . . . 2. That no liens or claims that may result in liens exist against the above-described property other than as set forth herein. 3. That the General Contractor has received payments for all stages of construction/rehabilitation of the property other than the final disbursement. 4. That the borrower(s) has/have requested, from the Lender, final disbursement of the construction/rehab funds in order to make final payment to the General contractor and that upon said disbursement by Lender the General Contractor will be paid in full under the Construction Contract. ¶9 Lane Myers alleges that it had reservations about submitting a “final” draw request that would not cover the total amount it was owed, but asserts that it did so because (a) the Kykers had informed it that they would pay any remaining balance after the final draw personally, (b) the Kykers were working with a mortgage broker in order to secure the funds to do so, and (c) National City explained to Lane Myers that the handwritten words “final draw” only referred to “the ‘final draw’ of the amounts available for reimbursement from the loan and not to a final payment of any amounts that may still be owed by the homeowner . . . for costs in excess of the amounts available for reimbursement from the loan.” Allegedly in reliance on these assurances, Lane Myers signed the request on August 30, 2007, and received $105,702.99.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lane Myers Construction, LLC v. National City Bank
2014 UT 58 (Utah Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2014 UT 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lane-myers-v-national-city-bank-utah-2014.