Costanzo v. Stewart

453 P.2d 526, 9 Ariz. App. 430, 1969 Ariz. App. LEXIS 456
CourtCourt of Appeals of Arizona
DecidedApril 24, 1969
Docket1 CA-CIV 843
StatusPublished
Cited by28 cases

This text of 453 P.2d 526 (Costanzo v. Stewart) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Costanzo v. Stewart, 453 P.2d 526, 9 Ariz. App. 430, 1969 Ariz. App. LEXIS 456 (Ark. Ct. App. 1969).

Opinion

KRUCKER, Judge.

Travis Stewart, plaintiff below, here ap-pellee, filed suit for the value of work done on the Costanzo home, naming the following defendants. First, plaintiff sued Strong Asphalt Sealcoating, Inc., contractor, for breach of a subcontracting contract, and Jim and Verna Nugent, mother and son, as alter egos of the above corporations, for breach of contract. Plaintiff sued Milton Husky, Treasurer of the State-of Arizona, on the corporation’s contractor’s bond. Lastly, he sued appellant, Samuel Costanzo, for unjust enrichment to his. property due to the completed subcontracting work. The plaintiff won his judgment *431 against the corporation with interest. A directed verdict in favor of the defendants Nugent was had. The cause was dismissed with prejudice as to the State Treasurer. Also, judgment was ordered against appellant Costanzo. A motion by Costanzo to amend the judgment was heard and denied. Costanzo appeals from the judgment and the denial of his motion to amend.

Plaintiff is a subcontractor who installs curbing, gutters, and sidewalks. Having done one project for Jim Nugent, he verbally agreed to do the job in question. He also spoke to the property owner, Mr. Cos-tanzo, who assured him the money for the job was in escrow and that he would write a check to him and Jim Nugent when the job was finished and passed by City Inspectors. The job was completed and inspected, and a check from Nugent to plaintiff was written. The check was deposited and not honored. Plaintiff made several efforts to get payment from both Jim Nu-gent and Costanzo, b,ut without success.

No mechanics’ lien was filed prior to the bringing of this action. The corporation is bankrupt. The federal government ■ has a withholding and income tax lien on the corporation bond. The Nugents are no longer in the state. Costanzo has paid no one anything for the work done, valued at $2,123.56, plus interest.

The initial question for determination raised by plaintiff is whether a timely appeal has been made. The time sequence of events is as follows:

July 21, 1967 Judgment entered

July 31, 1967 Motion to amend judgment

October 13, 1967 Formal, order denying motion to amend . (Minute entry was October 9, but the judge set the denial date as the date of the formal order

December 11, 1967 •Notice of appeal “from judgment of October 13”

December 27, 1967 Amended notice of appeal from “judgment entered on July 21, and order of October 13”

Parties have sixty days to appeal from a judgment or entered order. 16 A.R.S. Rule 73(b). From the dates above, and reading the December 11th notice as appealing from the October 13th proceeding, defendant has met the time requirement However, denials of motions to amend a judgment under Sahlin v. American Casualty Company of Reading, Pa., 5 Ariz. App. 126, 423 P.2d 897 (1967), vacated on other grounds, 103 Ariz. 57, 436 P.2d 606 (1968), are not appealable. The theory is that motions which do not raise new issues are not appealable because the more appropriate route is to appeal from the judgment itself. In this case the motion substantively only asked to change the result. The question then becomes, was the defendant within the limits of time to appeal from the judgment?

Rule 73(b) does extend the time from which one begins to count the sixty days, upon the final order (iii) granting or denying the motion under Rule 59(1) to amend the judgment. This means one begins to count from October 13. This is despite the general rule that one takes the Minute Entry date, here October 9, because in this case the judge specifically conditioned his order on the formal order. The notice of appeal filed December 11 is within the limit from October 13 if that notice can be read to appeal from a judgment, not the order. The wording of the notice uses the word “judgment”, not “order”, but indicates the date of the order. In’light-of *432 the later amended notice, it appears the party meant to appeal from the judgment, but inappropriately listed the order date. In light of the valid extension of time to that date, we find the appeal is perfected as required.

Defendant Costanzo makes three general allegations of error: (1) A mechanics’ lien is plaintiff’s sole remedy; (2) No action for unjust enrichment has been stated; hnd (3) The judgment is not supported by the evidence.

Defendant’s initial contention is erroneous. A mechanics’ lien is:

“ ‘ * * * a charge or encumbrance upon property to secure the payment or performance of a debt, duty, or other obligation. It is distinct from the obligation which it secures.’ ” Matlow c. Matlow, 89 Ariz. 293, 361 P.2d 648 (1961)

In Keefer v. Lavender, 74 Ariz. 24, 243 P.2d 457 (1952), in an action to foreclose a lien, the lower court held the lien was not perfected but entered a personal judgment against the property owner. In reversing on evidentiary grounds, the Supreme Court stated the applicable rule.

“The rule laid down in 36 Am.Jur., Mechanics’ Liens, Sec. 283, p. 172, adequately states the law on this issue:
‘The great weight of authority seems to be to the effect that in an action to foreclose a mechanic’s lien, a personal .judgment may be rendered against a party t.o the action who .is personally liable, in addition, to a judgment foreclosing the lien. Although there are cases to the contrary, this is generally held true even where the'lien fails. The right to such a judgment is dependent on a contractual relation being shown between the plaintiff and the defendant against whom the personal judgment is sought.
So, -there must be a contractual relation established between the owner of property on- which lien is claimed and the lienor to support a personal judgment against the owner in an action for the foreclosure of the lien. * * * ’ ” (Emphasis supplied) 74 Ariz., at 25-26, 243 P.2d at 458

Clearly, a personal judgment is available against defendant if proven. That a materialmen’s lien is an exclusive remedy has been denied in other contexts as well. Glitsos v. Kadish, 4 Ariz.App. 134, 418 P.2d 129 (1966) (forbearance of exercising lien for promise to pay held a valid agreement on doctrine promissory estoppel between landowner and materialmen); United States Fidelity and Guaranty Co. v. Hirsh, 94 Ariz. 331, 385 P.2d 211, (1963) (materialman can sue on contractor’s license bond and on lien for excess); Porter v. Eyer, 80 Ariz. 169, 294 P.2d 661 (1956) (materialman can sue on contractor’s completion bond).

Defendant’s next allegation is that no personal judgment for unjust enrichment will lie because:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Markham v. Cahava
Court of Appeals of Arizona, 2025
Richard Randall v. Thomas Koch
Court of Appeals of Washington, 2020
Cavan v. Maron
182 F. Supp. 3d 954 (D. Arizona, 2016)
Williams Carpet Contractors, Inc. v. Skelly
734 S.E.2d 177 (Court of Appeals of South Carolina, 2012)
Wang Electric, Inc. v. Smoke Tree Resort, LLC
283 P.3d 45 (Court of Appeals of Arizona, 2012)
Vulcan Materials Co. v. Atofina Chemicals Inc.
355 F. Supp. 2d 1214 (D. Kansas, 2005)
Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.
621 N.W.2d 502 (Nebraska Supreme Court, 2001)
Commerce v. Equity
695 So. 2d 383 (District Court of Appeal of Florida, 1997)
Columbia Wholesale Co. v. Scudder May N.V.
440 S.E.2d 129 (Supreme Court of South Carolina, 1994)
Williams v. Williams
801 P.2d 495 (Court of Appeals of Arizona, 1990)
A M Leasing, Ltd. v. Baker
786 P.2d 1045 (Court of Appeals of Arizona, 1989)
Flooring Systems, Inc. v. Radisson Group, Inc.
772 P.2d 578 (Arizona Supreme Court, 1989)
Flooring Systems, Inc. v. Radisson Group, Inc.
761 P.2d 733 (Court of Appeals of Arizona, 1988)
Guarantee Electric Co. v. Big Rivers Electric Corp.
669 F. Supp. 1371 (W.D. Kentucky, 1987)
Commercial Cornice & Millwork, Inc. v. Camel Construction Services. Corp.
739 P.2d 1351 (Court of Appeals of Arizona, 1987)
Horseshoe Estates v. 2M Co., Inc.
713 P.2d 776 (Wyoming Supreme Court, 1986)
Amfac Distribution Corp. v. J.B. Contractors, Inc.
703 P.2d 566 (Court of Appeals of Arizona, 1985)
Green Quarries, Inc. v. Raasch
676 S.W.2d 261 (Missouri Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
453 P.2d 526, 9 Ariz. App. 430, 1969 Ariz. App. LEXIS 456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/costanzo-v-stewart-arizctapp-1969.