Commercial Cornice & Millwork, Inc. v. Camel Construction Services. Corp.

739 P.2d 1351, 154 Ariz. 34, 1987 Ariz. App. LEXIS 431
CourtCourt of Appeals of Arizona
DecidedJuly 2, 1987
Docket1 CA-CIV 8756
StatusPublished
Cited by15 cases

This text of 739 P.2d 1351 (Commercial Cornice & Millwork, Inc. v. Camel Construction Services. Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Cornice & Millwork, Inc. v. Camel Construction Services. Corp., 739 P.2d 1351, 154 Ariz. 34, 1987 Ariz. App. LEXIS 431 (Ark. Ct. App. 1987).

Opinion

NOREEN SHARP, Judge Pro Tern.

This is an appeal from the trial court’s orders denying appellant’s two motions to amend the complaint, and granting appellee’s motion to dismiss for failure to state a claim. We affirm the denial of the motions to amend the complaint. We affirm the dismissal of the claim for foreclosure of the mechanic’s lien. We reverse the dismissal of the claims for breach of contract and restitution.

Commercial Cornice & Millwork, Inc. (Subcontractor) contracted with Camel Construction Services Corporation (General Contractor) to furnish labor and materials to Malarkey’s, Incorporated and its officers, Timothy Herbst, Ronald Heberly, Seymour Brier, and their spouses (Owner). After numerous change orders, Subcontractor claimed it was owed $177,773. Subcontractor alleged that during construction Owner agreed to pay Subcontractor the full amount due under the subcontract and the change orders. Owner paid part of the amount claimed by Subcontractor, but Subcontractor has not been paid $99,773 by either Owner or General Contractor.

In Count I of the complaint Subcontractor apparently sought the remaining amount due from Owner and General Contractor, and to foreclose its mechanics’ lien on Owner’s property. In Count II Subcontractor claimed from Owner the reasonable value of the labor and materials provided.

Subcontractor filed two motions to amend the complaint which were both denied by the superior court. Owner filed a motion to dismiss for failure to state a claim which was granted as follows:

As stated at the time of oral argument, the complaint does NOT make any allegations of a direct contract between plaintiff and defendants other than Camel. The complaint affirmatively alleges a contract between Camel and Commercial and since the exhibits appended thereto seem to prove the existence of such a contract, there can be no personal judg *36 ment against the owners on the theory of quantum meruit. A review of the complaint and the attachments [sic] discloses that plaintiff has failed to allege compliance with essential requirements of the mechanics lien statutes.
IT IS THEREFORE ORDERED granting defendants (other than Camel)’s [sic] Motion to Dismiss for Failure to State a Claim.

In September, 1985, pursuant to a stipulation between General Contractor and Subcontractor, the superior court entered judgment in favor of Subcontractor and against General Contractor for $99,773, and costs and attorney’s fees.

We consider the following four questions:

(1) did the superior court abuse its discretion in denying Subcontractor’s motions to amend its complaint;
(2) did the superior court err in dismissing Subcontractor’s claim for foreclosure of its mechanics’ lien because of the failure to comply with A.R.S. § 33-993(A)(6);
(3) did the superior court err in concluding that Subcontractor failed to state a claim against Owner for breach of contract;
(4) did the superior court err in dismissing Subcontractor’s claim against Owner for restitution?

DENIALS OF MOTIONS TO AMEND COMPLAINT

Subcontractor complains that the trial court abused its discretion in denying two motions to amend the complaint. We disagree.

The complaint was filed March 22, 1983. Trial was originally set for October 29, 1984, and was continued four times between January, 1985, and June, 1985.

On April 25, 1985, Subcontractor moved to amend its complaint to add a $30,000 tax assessment to the damages sought in the restitution claim. Subcontractor asserted that “Defendants have known for some time that Plaintiff suffered a penalty in the amount of approximately $30,000.00.” The existence of the federal tax lien was apparently known to Subcontractor at least since July, 1984 and, in light of the multiple trial settings, Subcontractor could have moved to amend the complaint much earlier than it did. The superior court, therefore, could have determined that this issue was untimely, would require additional research and discovery, would cause unnecessary delay and would unduly prejudice Owner. See Spitz v. Bache & Co., Inc., 122 Ariz. 530, 596 P.2d 365 (1979). See also Green Reservoir Flood Control District v. Willmoth, 15 Ariz.App. 406, 489 P.2d 69 (1971).

On June 20, 1985, after the trial court granted Owner’s motion to dismiss for failure to state a claim, Subcontractor again moved to amend its complaint. This time it apparently desired to allege that it had taken all steps required by law to perfect its lien, that General Contractor was the agent of Owner, and that Owner had not paid anyone for the benefit conferred on it. No copy of the proposed amended complaint was attached to this motion. In fact, not until September 26,1985, when Subcontractor filed a motion to reconsider the denial of the second motion to amend, did Subcontractor provide the court with a copy of the proposed amended complaint. Subcontractor gives no reason why the second motion to amend the complaint was not filed until June, 1985, after the fifth trial setting. We conclude that the superior court properly exercised its discretion in denying this second motion to amend.

DISMISSAL FOR FAILURE TO STATE A CLAIM—FORECLOSURE OF MECHANICS’ LIEN

Subcontractor next argues that the trial court erred in ruling that the complaint did not state a cause of action for lien foreclosure. We disagree. Section 33-993(A)(6) of the Arizona Revised Statutes provides that a notice and claim of lien shall contain “[a] statement of the date that the labor, materials, machinery, fixtures or tools were first furnished to the jobsite.” Subcontractor’s notice and claim of lien violated A.R.S. § 38-998(A)(6) be *37 cause it did not contain the date labor was first furnished.

Arizona courts have considered whether a failure to comply with various specific requirements of A.R.S. § 33-993(A) invalidates a lien. See, e.g., Old Adobe Office Properties, Ltd. v. The Honorable Harry Gin, 151 Ariz. 248, 727 P.2d 26 (App.1986) (depositing a copy of the notice and claim of lien in first-class regular mail without obtaining a certificate of mailing does not constitute a valid method of service under A.R.S. § 33-993(A)); Smith Pipe & Steel Co. v. Mead, 130 Ariz. 150; 634 P.2d 962

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MARKHAM v. CAHAVA
Arizona Supreme Court, 2026
Evans v. McAllister
D. Arizona, 2023
Snyder v. Arizona Board of Regents
Court of Appeals of Arizona, 2015
Snyder v. HSBC Bank, USA, N.A.
913 F. Supp. 2d 755 (D. Arizona, 2012)
Wang Electric, Inc. v. Smoke Tree Resort, LLC
283 P.3d 45 (Court of Appeals of Arizona, 2012)
Delmastro & Eells v. Taco Bell Corp.
Court of Appeals of Arizona, 2011
Jeffs v. Stubbs
970 P.2d 1234 (Utah Supreme Court, 1998)
MLM Const. Co., Inc. v. Pace Corp.
836 P.2d 439 (Court of Appeals of Arizona, 1992)
S.K. Drywall, Inc. v. Developers Financial Group, Inc.
799 P.2d 1362 (Court of Appeals of Arizona, 1990)
A M Leasing, Ltd. v. Baker
786 P.2d 1045 (Court of Appeals of Arizona, 1989)
Flooring Systems, Inc. v. Radisson Group, Inc.
772 P.2d 578 (Arizona Supreme Court, 1989)
Flooring Systems, Inc. v. Radisson Group, Inc.
761 P.2d 733 (Court of Appeals of Arizona, 1988)
Northwest Federal Savings & Loan v. Tiffany Construction Co.
761 P.2d 174 (Court of Appeals of Arizona, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
739 P.2d 1351, 154 Ariz. 34, 1987 Ariz. App. LEXIS 431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-cornice-millwork-inc-v-camel-construction-services-corp-arizctapp-1987.