MLM Const. Co., Inc. v. Pace Corp.

836 P.2d 439, 172 Ariz. 226, 112 Ariz. Adv. Rep. 61, 1992 Ariz. App. LEXIS 154
CourtCourt of Appeals of Arizona
DecidedMay 14, 1992
Docket1 CA-CV 90-0502
StatusPublished
Cited by7 cases

This text of 836 P.2d 439 (MLM Const. Co., Inc. v. Pace Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MLM Const. Co., Inc. v. Pace Corp., 836 P.2d 439, 172 Ariz. 226, 112 Ariz. Adv. Rep. 61, 1992 Ariz. App. LEXIS 154 (Ark. Ct. App. 1992).

Opinion

OPINION

YOSS, Presiding Judge.

MLM Construction Co., Inc. appeals from an adverse judgment on its claim against Pace Corporation and Aetna Casualty and Surety Co., Pace’s surety, for recovery on a mechanics lien discharge bond. See Ariz. Rev.Stat.Ann. (“A.R.S.”) § 33-1004. The appeal presents the following issues: (1) whether MLM’s lien was invalid because the preliminary twenty day notice served by MLM omitted part of a statement required by A.R.S. § 33-992.01(C)(5); and (2) whether MLM’s lien was invalid because proof of service of the preliminary twenty day notice under A.R.S. § 33-992.02 was not attached to MLM’s notice and claim of lien as required by A.R.S. § 33-993(A)(7). We hold that both defects were independently sufficient to invalidate MLM’s lien and therefore affirm.

FACTS AND PROCEDURE BELOW

Appellee Pace Corporation contracted to construct a shopping center on real property owned by Garden Lakes Center Associates in Phoenix. BCN Lumber, Inc., not a party to this appeal, was a subcontractor to Pace on the project. Appellant MLM Construction Company entered into a subcontract with BCN to provide rough carpentry labor and materials for $64,945.00.

MLM furnished the required materials and labor to BCN. MLM engaged a San Diego-based lien service to prepare and serve an Arizona preliminary twenty day notice pursuant to A.R.S. § 33-992.01. The lien service sent Pace a form entitled “Arizona Preliminary Notice in accordance with Arizona Revised Statutes § 33-992.01 and 33-992.02.”

At all times material to this action A.R.S. § 33-992.01(C)(5) required a preliminary twenty day notice to state in bold-faced type:

In accordance with Arizona Revised Statutes § 33-992.01, this is not a lien and this is not a reflection on the integrity of any contractor or subcontractor.
Notice to Property Owner
If bills are not paid in full for the labor, professional services, materials, machinery, fixtures or tools furnished or to be furnished, a mechanic’s lien leading to the loss, through court foreclosure proceedings, of all or part of your property being improved may be placed against the property. You may wish to protect yourself against this consequence by either:
1. Requiring your contractor to furnish a release signed by the person or *228 firm giving you this notice before you make payment to your contractor.
2. Using any other method or device which is appropriate under the circumstances.

The printed form on which MLM presented its preliminary twenty day notice in this case nowhere contained the language “this is not a lien and this is not a reflection on the integrity of any contractor or subcontractor.”

MLM later alleged that BCN had failed to pay it $61,212.04 for materials and labor furnished. MLM timely recorded a notice and claim of lien against the Garden Lakes project. Attached was a copy of MLM’s preliminary twenty day notice. At the time MLM recorded its notice and claim of lien A.R.S. § 33-993(A)(7) required a lien claimant to attach to the notice, in addition to his preliminary twenty day notice, a copy of “the proof of service required by § 33-992.02....” The form of “affidavit of proof of service of preliminary twenty day notice” on MLM’s preliminary twenty day notice was entirely blank. No separate proof of service pursuant to § 33-992.02 was attached to MLM’s notice and claim of lien.

MLM later commenced this action seeking damages for breach of contract against BCN, quantum meruit recovery against the project and its joint venturers, and foreclosure of its mechanic’s lien. BCN filed a Chapter 11 bankruptcy petition in the United States Bankruptcy Court. Pace thereafter recorded a statutory discharge of lien bond underwritten by appellee Aetna Casualty and Surety Company. See A.R.S. § 33-1004.

MLM responded with a second amended complaint that dropped BCN as a defendant, reasserted its quantum meruit claim against Garden Lakes and its joint venturers, and sought recovery against Aetna on Pace’s lien discharge bond. Pace and Garden Lakes both filed counterclaims that sought damages on the theory that MLM had reason to know the lien it recorded was invalid. See A.R.S. § 33-420. Garden Lakes moved for partial summary judgment on MLM’s claim for recovery in quantum meruit. Pace and Aetna moved for judgment on the pleadings on MLM’s claim against the lien discharge bond.

MLM filed a cross-motion for summary judgment on its bond claim and for judgment on the counterclaims. MLM simultaneously filed a notice conceding Garden Lakes’ motion for partial summary judgment on MLM’s claim for quantum meruit recovery. After the motions were fully briefed the trial court granted partial summary judgment for Garden Lakes on the quantum meruit claim and granted judgment on the pleadings for Pace and Aetna on MLM’s bond claim. The court explained:

The Court in granting the motion adopts a strict interpretation of the lien statute and the requirements thereof. The Court does recognize that equities lie in favor of MLM Construction, but the Court refuses to substitute its opinion for the clear mandate of the legislature in A.R.S. 33-992.01.b wherein the legislature states, “shall, as a necessary prerequisite to the validity of any claim of lien, serve ...”

The parties later stipulated that if MLM did not appeal from the trial court’s judgment, Garden Lakes’ and Pace’s counterclaims would be dismissed with prejudice, but that if MLM appealed from the judgment their dismissal would be without prejudice. The trial court entered judgment in accordance with its rulings and the parties’ stipulation. This timely appeal followed. We have jurisdiction pursuant to A.R.S. § 12-2101(B).

SUFFICIENCY OF MLM’S PRELIMINARY TWENTY DAY NOTICE

MLM acknowledges that A.R.S. § 33-992.01

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S & S Paving & Construction, Inc. v. Berkley Regional Insurance
372 P.3d 1036 (Court of Appeals of Arizona, 2016)
S&S Paving v. Berkley
Court of Appeals of Arizona, 2016
Wang Electric, Inc. v. Smoke Tree Resort, LLC
283 P.3d 45 (Court of Appeals of Arizona, 2012)
Allstate Utility Construction, LLC v. Towne Bank
263 P.3d 694 (Court of Appeals of Arizona, 2011)
Delmastro & Eells v. Taco Bell Corp.
Court of Appeals of Arizona, 2011
Fagerlie v. MARKHAM CONTRACTING CO., INC.
258 P.3d 185 (Court of Appeals of Arizona, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
836 P.2d 439, 172 Ariz. 226, 112 Ariz. Adv. Rep. 61, 1992 Ariz. App. LEXIS 154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mlm-const-co-inc-v-pace-corp-arizctapp-1992.