§ 33-993 — Procedure to perfect lien; notice and claim of lien; service; recording; definitions

Arizona § 33-993
JurisdictionArizona
Title 33Arizona Revised Statutes
Ch. 7LIENS
Art. 6Mechanics' and Materialmen's Liens

This text of Arizona § 33-993 (Procedure to perfect lien; notice and claim of lien; service; recording; definitions) is published on Counsel Stack Legal Research, covering Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ariz. Rev. Stat. Ann. § 33-993 (2026).

Text

A.In order to impress and secure the lien provided for in this article, every person claiming the benefits of this article, within one hundred twenty days after completion of a building, structure or improvement, or any alteration or repair of such building, structure or improvement, or if a notice of completion has been recorded, within sixty days after recordation of such notice, shall make duplicate copies of a notice and claim of lien and record one copy with the county recorder of the county in which the property or some part of the property is located, and within a reasonable time thereafter serve the remaining copy upon the owner of the building, structure or improvement, if he can be found within the county. The notice and claim of lien shall be made under oath by the claimant or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. Stockwell
671 P.2d 394 (Arizona Supreme Court, 1983)
34 case citations
Able Distributing Co. v. James Lampe
773 P.2d 504 (Court of Appeals of Arizona, 1989)
24 case citations
Adams Tree Service, Inc. v. Transamerica Title Insurance
511 P.2d 658 (Court of Appeals of Arizona, 1973)
16 case citations
Commercial Cornice & Millwork, Inc. v. Camel Construction Services. Corp.
739 P.2d 1351 (Court of Appeals of Arizona, 1987)
15 case citations
Hayward Lumber & Investment Company v. Graham
449 P.2d 31 (Arizona Supreme Court, 1968)
15 case citations
Gene McVety, Inc. v. Don Grady Homes, Inc.
581 P.2d 1132 (Arizona Supreme Court, 1978)
14 case citations
Bobo v. John W. Lattimore, Contractor
468 P.2d 404 (Court of Appeals of Arizona, 1970)
13 case citations
Hartford Accident & Indemnity Co. v. Federal Insurance
834 P.2d 827 (Court of Appeals of Arizona, 1992)
12 case citations
Environmental Liners, Inc. v. Ryley, Carlock & Applewhite
930 P.2d 456 (Court of Appeals of Arizona, 1996)
10 case citations
Hunnicutt Construction, Inc. v. Stewart Title & Trust of Tucson Trust No. 3496
928 P.2d 725 (Court of Appeals of Arizona, 1996)
10 case citations
Fagerlie v. MARKHAM CONTRACTING CO., INC.
258 P.3d 185 (Court of Appeals of Arizona, 2011)
8 case citations
Hanson Aggregates Arizona, Inc. v. Rissling Construction Group, Inc.
127 P.3d 910 (Court of Appeals of Arizona, 2006)
7 case citations
C S & W Contractors, Inc. v. Southwest Savings & Loan Ass'n
852 P.2d 1239 (Court of Appeals of Arizona, 1992)
4 case citations
Egan-Ryan Mechanical Co. v. Cardon Meadows Development Corp.
818 P.2d 146 (Court of Appeals of Arizona, 1990)
4 case citations
Gene McVety, Inc. v. Don Grady Homes, Inc.
580 P.2d 726 (Court of Appeals of Arizona, 1977)
4 case citations
Cemex Construction Materials South, LLC v. Falcone Brothers & Associates, Inc.
349 P.3d 210 (Court of Appeals of Arizona, 2015)
3 case citations
Allstate Utility Construction, LLC v. Towne Bank
263 P.3d 694 (Court of Appeals of Arizona, 2011)
2 case citations
Amfac Distribution Corp. v. Union Rock & Materials Corp.
711 P.2d 607 (Court of Appeals of Arizona, 1985)
Babicky v. Copper State
(Court of Appeals of Arizona, 2025)
Collins v. Stockwell
671 P.2d 415 (Court of Appeals of Arizona, 1983)

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Arizona § 33-993, Counsel Stack Legal Research, https://law.counselstack.com/statute/az/33-993.