Collins v. Stockwell
This text of 671 P.2d 394 (Collins v. Stockwell) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Robert W. COLLINS, Plaintiff-Appellant,
v.
James C. STOCKWELL and Jane Doe Stockwell, his wife; Title Insurance Company of Minnesota, Additional Defendants-Appellees.
Supreme Court of Arizona, In Banc.
*416 Atmore Baggot, Phoenix, for plaintiff-appellant.
O'Connor, Cavanagh, Anderson, Westover, Killingsworth & Beshears by Wilbert G. Anderson, Phoenix, for additional defendants-appellees.
Mariscal, Weeks, McIntyre & Friedlander, P.A. by Donald N. McIntyre, Gary L. Birnbaum, Fred C. Fathe, Phoenix, for amici curiae Sec. Title Agency, Safeco Title Ins. Co. and First American Title Ins. Co. of Arizona.
Renaud, Cook & Videan, P.A. by Scott M. Clark, Phoenix, for amicus curiae Larry Clark Const. Co.
GORDON, Vice Chief Justice:
In 1978 Robert Collins, a licensed subcontractor, performed tile work for Diplomat Homes, Inc., a developer in Phoenix. Diplomat became insolvent prior to paying Collins for the work. As a result and pursuant to A.R.S. § 33-993, Collins recorded a timely mechanic's lien on the property on September 21, 1978. Collins served the lien on Diplomat because it was listed as the owner of the home. Thereafter, on September 26, 1978, Collins filed an action to foreclose the lien within the six-month period required by A.R.S. § 33-998. At no time was a notice of lis pendens filed.
On December 18, 1979, Collins filed a supplemental complaint naming Paul and Arlene Blonsky as defendants after learning that they had acquired an interest in the property. After the supplemental complaint was filed the Blonskys, in March 1980, conveyed title to James Stockwell, a subsequent purchaser for value. At all times after September 21, 1978 the records at the Maricopa County Recorder's Office reflected that a notice and claim of lien had *417 been filed on the property which is the subject of this action. At the time of the sale from the Blonskys to Stockwell, Minnesota Title prepared a title report and insured the title. The title report failed to disclose the presence of Collins' mechanics lien in the county records. Collins subsequently joined Stockwell and Minnesota Title as defendants in a supplemental complaint filed in June, 1980.
Stockwell and Minnesota Title filed a motion for summary judgment claiming that since they did not have notice of the foreclosure action, Collins had no enforceable claim against Stockwell's interest in the property. The trial court granted the motion for summary judgment and dismissed the claim against Stockwell and Minnesota Title with prejudice. The Court of Appeals affirmed the trial court's decision. We have jurisdiction pursuant to Ariz. Const. art. 6, § 5(3) and Ariz.R.Civ.App.P. 23.
The following issue is presented for our disposition: Is it necessary to file a notice of lis pendens in order to give constructive notice of a mechanic's lien after the six-month period within which a foreclosure action must be filed has expired? Minnesota Title searched the County Recorder's records on Stockwell's behalf more than six months after the notice of claim of lien was filed. Although it found that a lien had been recorded, Minnesota Title claims that since no lis pendens had been filed to indicate that a foreclosure action had been instituted the title company could logically conclude that the contractor's claim had either been settled or had extinguished by operation of law. On the other hand, Collins argues that he was not required to file a notice of lis pendens because the mechanic's lien statutes did not require it and under Arizona's general notice statutes the effect of recording the notice of claim of lien was to impart constructive notice to all persons of the existence of the instrument, its contents, and its potential legal effects. A.R.S. § 33-416. Collins asserts that upon discovering that a notice of claim of lien had been filed Minnesota Title should have made further inquiry to ensure that the contractor's claim had either been satisfied or had extinguished due to Collins' failure to file a timely foreclosure action. After reviewing the record and the law applicable to this matter we agree with Collins' position and therefore vacate the decision of the Court of Appeals and reverse the trial court's entry of summary judgment in favor of defendants Stockwell and Minnesota Title.
The purpose of mechanic's lien statutes is to protect the rights of those who furnish labor and materials which enhance the value of another's property. Pioneer Plumbing Supply Co. v. Southwest Sav. & L. Assn., 102 Ariz. 258, 428 P.2d 115 (1967); Kerr-McGee Oil Industries, Inc. v. McCray, 89 Ariz. 307, 361 P.2d 734 (1961); Price v. Sunmaster, 27 Ariz. App. 771, 558 P.2d 966 (1976). We have consistently held that such liens are remedial and are to be liberally construed to effect their purpose. Gene McVety, Inc. v. Don Grady Homes, Inc., 119 Ariz. 482, 581 P.2d 1132 (1978); Kerr-McGee Oil Industries, Inc. v. McCray, supra. The lien constitutes a preference over subsequent encumbrances or over other encumbrances as to which there has been no actual or constructive notice. A.R.S. § 33-992. The lien is perfected if, within a specified time after the completion of construction, the contractor, subcontractor, or supplier files a notice of claim of lien in the office of the County Recorder of the county in which the property is located and served a copy on the owner of the property. A.R.S. § 33-993. The effect of filing a notice and claim of lien, an instrument which must be acknowledged and recorded, is stated in A.R.S. § 33-416:
"Record of instrument duly recorded as notice
"The record of a grant, deed or instrument in writing authorized or required to be recorded, which has been duly acknowledged and recorded in the proper county, shall be notice to all persons of the existence of such grant, deed or instrument, but a mortgage of real property may be recorded and constructive notice and the contents thereof given as *418 provided in § 33-415." (emphasis added).
An action to foreclose the lien must be brought within six months after the notice of claim of lien has been recorded. A.R.S. § 33-998. Once a lien has been satisfied, either by foreclosure, settlement or otherwise, a release of lien must be issued. A.R.S.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
671 P.2d 394, 137 Ariz. 415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/collins-v-stockwell-ariz-1983.