Weitz Co. v. Heth

314 P.3d 569, 233 Ariz. 442, 674 Ariz. Adv. Rep. 29, 2013 WL 6188406, 2013 Ariz. App. LEXIS 241
CourtCourt of Appeals of Arizona
DecidedNovember 26, 2013
DocketNo. 1 CA-CV 11-0788
StatusPublished
Cited by4 cases

This text of 314 P.3d 569 (Weitz Co. v. Heth) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weitz Co. v. Heth, 314 P.3d 569, 233 Ariz. 442, 674 Ariz. Adv. Rep. 29, 2013 WL 6188406, 2013 Ariz. App. LEXIS 241 (Ark. Ct. App. 2013).

Opinion

OPINION

BROWN, Judge.

¶ 1 The question we address is whether Arizona’s statutory provision governing the priority of mechanics’ liens (Arizona Revised Statutes (“AR.S.”) section 33-992(A)) permits a court to shift lien priorities by applying the doctrine of equitable subrogation. Because § 33-992(A) expressly provides that mechanics’ liens have priority over all subsequent encumbrances (subject to a narrow exception not applicable here), we hold that allowing a subsequent lienholder to equitably subrogate its loan to a position ahead of a mechanic’s lien would contravene the plain statutory requirement. We therefore affirm the superior court’s grant of summary judgment.

BACKGROUND

¶ 2 First National Bank of Arizona provided a $44,000,000 construction loan to Summit at Copper Square, LLC (“Summit”) to build a 165-unit mixed-use commercial and residential condominium project in downtown Phoenix. The bank recorded a deed of trust on the project to secure Summit’s payment obligations under the construction loan, which was later increased by approximately $10,000,000.

¶ 3 Summit contracted with The Weitz Company (“Weitz”) to serve as the general contractor on the project. Construction commenced, and on January 18, 2006, Weitz served a preliminary twenty-day mechanic’s lien notice. See A.R.S. § 33-992.01. The project continued according to the parties’ agreement, with Summit paying Weitz on a monthly basis in response to Weitz’s payment applications. As the project neared completion, however, Summit was unable to pay about $4,000,000 of Weitz’s billed work.

¶ 4 Summit started selling individual condominium units in September 2007, before construction was completed. Ultimately, as relevant here, 92 units were sold. Most of the purchases were financed by various commercial lenders, but some units were sold for cash. Proceeds from the sales were applied to pay off allocated portions of the construction loan, but the outstanding balance of Weitz’s construction contract remained unpaid.

¶ 5 Weitz recorded a mechanic’s lien against the project in May 2008. In November, Weitz filed a complaint seeking to foreclose its lien against, inter alia, the purchasers of the units and the lenders who provided the funds used to finance the purchases (collectively “Lenders”). Lenders moved for partial summary judgment, arguing they were equitably subrogated to First National Bank’s position, and thus had priority over Weitz’s lien. In response, Weitz also sought partial summary judgment, asserting that its lien had priority under A.R.S. § 33-992(A) over all other liens or encumbrances attaching after commencement of the project.

¶ 6 Following oral argument on the motions, the superior court ruled in favor of Weitz, finding it would be improper to apply equitable subrogation because the construction loan had not been fully discharged. The court therefore concluded Weitz’s lien was superior to Lenders’ liens under AR.S. [445]*445§ 33-992(A), which specifies the priority afforded to “mechanics’ and materialmen’s liens” (“mechanics’ liens”). The parties agreed to a stipulated judgment lien amount of $2,123,000, subject to Lenders’ right to appeal the court’s summary judgment ruling. We have jurisdiction over this appeal pursuant to AR.S. § 12-2101(A)(1).

DISCUSSION

¶ 7 We review the grant of summary judgment de novo, Duncan v. Scottsdale Med. Imaging, Ltd., 205 Ariz. 306, 308, ¶ 2, 70 P.3d 435, 437 (2003), and we may affirm a summary judgment if it is correct for any reason, City of Tempe v. Outdoor Sys., Inc., 201 Ariz. 106, 111, ¶ 14, 32 P.3d 31, 36 (App.2001). Because we conclude that priority of the liens at issue is conclusively established by statute, we need not address the superior court’s implied determination that Arizona law does not permit partial equitable subrogation.

I. Historical Preference of Mechanics’ Liens

¶ 8 A lien is defined as a “legal right or interest that a creditor has in another’s property, lasting [usually] until a debt or duty that it secures is satisfied.” Black’s Law Dictionary 941 (8th ed.2004). Every person who provides labor or materials for the construction of any building “shall have a lien” on such building for the work done or materials supplied. AR.S. § 33-981. Enforcement of the lien is contingent upon compliance with detailed statutory procedures, see A.R.S. §§ 33-981 to -1008, and the lien’s priority is governed by § 33-992(A), which provides in part:

The hens provided for in this article ... are preferred to all liens, mortgages or other encumbrances upon the property attaching subsequent to the time the labor was commenced or the materials were commenced to be furnished except any mortgage or deed of trust that is given as security for a loan made by a construction lender ... if the mortgage or deed of trust is recorded within ten days after labor was commenced or the materials were commenced to be furnished.

(Emphasis added.) Legislative recognition that mechanics’ liens have priority over subsequent liens has been in existence since 1865, almost half a century before statehood:

[T]he liens created by this act shall be preferred to every other lien or incum-brance, which shall have been attached upon said property subsequent to the time at which the work was commenced or the materials furnished; but nothing herein contained shall be construed as impairing any valid incumbrance upon the said lands, duly made and recorded before such work was commenced or materials furnished.

Acts of Arizona, 1865, p. 38 sec. 4; see also Compiled Laws of the Territory of Arizona as Chapter XXVII, see. 4 (1874); Revised Statutes of Arizona Territory, Title 40, Ch. 2, p. 759-64 (1901); Revised Statutes of Arizona Civil Code, Title 29, Ch. 2, p. 1256, ¶ 3658 (1913).

¶ 9 As recognized by our supreme court, the purpose of the mechanics’ lien statutes is to protect the rights of those who furnish labor and materials to improve another person’s property. Collins v. Stockwell, 137 Ariz. 416, 418, 671 P.2d 394, 396 (1983). Because these statutes are remedial, we construe them liberally to achieve their primary purpose. See Kerr-McGee Oil Indus., Inc. v. McCray, 89 Ariz. 307, 311, 361 P.2d 734, 736 (1961); Wylie v. Douglas Lumber Co., 39 Ariz. 511, 515, 8 P.2d 256, 258 (1932) (recognizing that the legislature “intended that laborers and materialmen, who contribute of their labor and means to enhance the value of the property of another, should be jealously protected”).

II. Plain Statutory Language

¶ 10 In construing AR.S. § 33-992(A), our fundamental goal is to give effect to legislative intent. Hall v. Read Dev., Inc., 229 Ariz. 277, 279, ¶ 6, 274 P.3d 1211

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haci v. Bmo
Court of Appeals of Arizona, 2015
The Weitz Company v. Nicholas Heth
Arizona Supreme Court, 2014
Weitz Co. v. Heth
333 P.3d 23 (Arizona Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
314 P.3d 569, 233 Ariz. 442, 674 Ariz. Adv. Rep. 29, 2013 WL 6188406, 2013 Ariz. App. LEXIS 241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weitz-co-v-heth-arizctapp-2013.